CITY OF BOULDER
WATER RESOURCES ADVISORY BOARD
AGENDA ITEM
MEETING DATE: December 21, 2009
AGENDA TITLE: Recommendation on Financing City Matching Funds for a Grant to
Modernize the Boulder Canyon Hydroelectric Facility
PRESENTERS:
Ned Williams, Director of Public Works for Utilities
Carol Ellinghouse, Water Resources Coordinator
Carol Linn, Utilities Finance Manager
EXECUTIVE SUMMARY:
In Aug. 2009, city staff submitted an application for rehabilitation of the city's Boulder
Canyon Hydro (BCH) facility to the Department of Energy (DOE) under a grant offering
for modernization of hydroelectric facilities through the Recovery Act stimulus funding
program. On Nov. 4, 2009, the city received notice that its application had been accepted
for negotiation of an award of $1,180,000 toward the total project cost of $5,155,000.
Therefore, the amount to be paid by the city if the grant is accepted is $3,975,000.
A decision regarding the city's acceptance of the grant and the funding source for the
city's portion of project costs must be made soon because of a grant requirement that the
rehabilitated hydro project be on-line by Dec. 2011. This drives a very tight schedule
that requires design of the project to begin in Jan. 2010 so that construction can be
completed in two years.
STAFF RECOMMENDATION:
Suggested Motion Language:
Staff requests WRAB consideration of this matter and action in the form of the following
motion:
Motion to recommend to City Council acceptance of DOE grant funding for Boulder
Canyon Hydro modernization and use of Lakewood Pipeline Remediation Reserve funds,
to be repaid with 3% interest, for funding of Boulder's share of the modernization
proj ect.
COMMUNITY SUSTAINABILITY ASSESSMENTS AND IMPACTS:
• Economic: Over the fifty-year life of the new BCH generating equipment, sale of the
electricity will provide a net increase in present worth revenue for the city of $6.1
AGENDA ITEM 9 6 PAGE 1
• Environmental: Rehabilitating BCH will offset the need to burn 278,000 tons of coal
over the 50-year life of the new equipment, resulting in a reduction of 281,000 tons of
COz emissions.
• Social: BCH is considered eligible for listing on the National Register of Historic
Places. Retaining original function is commonly recognized as one of the most
effective means of historic preservation. While modernization will affect the
interior/equipment of the historic power plant, the city has included provisions to
mitigate adverse effects in the modernization project scope.
OTHER IMPACTS:
• Fiscal: The present worth of the revenues from rehabilitating BCH over a twenty-year
period is $6,554,000. With the grant, the present worth of the construction and O&M
costs is $3,970,000, which puts the present worth of net revenues for the water utility
over twenty years at $2,584,000 with a benefit/cost ratio for the project of 1.65. One
financing option is to borrow $5.155 million from the Lakewood Pipeline
Remediation Reserve to fully appropriate the funds for the project. The grant funds
would replenish the reserve by $1.18 million as they are received. The water utility
would repay the reserve the remaining $3.975 million at a 3% annual interest rate.
Another option is to reprioritize the water utility capital improvement program (CIP)
while acknowledging the short-term implications for the utilities bond rating and
longer-term implications for costs of postponed maintenance projects.
• Staff time: Staff time for the BCH modernization project can be accommodated with
existing staff levels, but with some reprioritization of work assignments required.
BACKGROUND:
The existing BCH turbine-generator was installed in 1936 and is not expected to remain
operational for more than five years. Rehabilitation of BCH with a new generation unit
was included as a recommended project in the Source Water Master Plan and in the 20-
year water utility CIP. If a new turbine-generator unit is not installed, BCH could be
decommissioned when the existing unit fails. Decommissioning would involve costs and
would cause a loss of future revenue potential at BCH, as well as a decrease in generation
of electricity with the city water system.
As part of the 2010 recommended budget submitted to Council, it was noted that the
Utilities division was pursuing federal stimulus funds through the American Recovery
and Reinvestment Act of 2009 (ARRA) on a case by case basis as opportunities arise. It
was also noted that some of the funding programs require a city match and, should the
city be successful in an award, Utilities may need to re-prioritize its capital improvement
program, use financial reserves or a combination of both in order to accept the award and
fund the city's share of the project.
In Aug. 2009, city staff submitted an application for rehabilitation of BCH to the
Department of Energy (DOE) under a grant offering for modernization of hydroelectric
facilities through the Recovery Act stimulus funding program (Attachment A: Grant
AGENDA ITEM 9 6 PAGE 2
Application Summary). On Nov. 4, 2009, the city received notice that its application
had been accepted for negotiation of an award of $1.18 million.
The grant offering had stated that up to 50% matching funds were available from DOE
for selected projects, and this was the basis of the city's application. The city had
submitted a proposed project cost of $5,155,000, had requested a matching grant of at
least $2.5 million from DOE and anticipated that the city's share of project costs would
be $2,655,000. With the actual grant award being $1,180,000, the city's share of funding
will be $3,975,000 if the DOE grant is accepted. This is $1,320,000 more than reflected
in the grant application.
The electricity generated at BCH is sold by the city to Xcel Energy and is renewable
energy that can be sold for a premium. The financial benefits of rehabilitating BCH
exceed the costs with or without the grant, but the grant funding makes the project even
more attractive. The investment in construction of the rehabilitated BCH with the grant
would be recovered after ten years (ten year pay-back period) of operation and would be
recovered in 14 years without the grant.
The grant requires that the rehabilitated hydro project be on-line by Dec. 2011. This
drives a very tight schedule that requires design of the project to begin in Jan. 2010 so
that construction can be completed in two years. Information obtained as the grant
application was being developed indicated that manufacturing the new turbine-generator
will require approximately 16 months, so the order for this equipment would be made in
Mar. 2010 to allow sufficient time for installation in 2011.
ANALYSIS:
Hydroelectric production at BCH provides revenue for the water utility from sale of the
power to Xcel Energy. It also provides green renewable energy with environmental
benefits due to offsetting the need to burn coal for electricity production. The amount of
energy production and environmental benefits for the existing BCH unit and the proposed
replacement unit are shown in Attachment B: Technical Memorandum regarding
BCH Grant. This memo also provides a technical analysis of the project economics and
a detailed discussion of the city's funding options for the project.
Rehabilitation of BCH was not planned for or budgeted in 2009 or 2010. However, when
Recovery Act funds/grants became available in 2009, staff applied for a DOE grant to
replace the turbine-generator at the BCH facility. This project was not in the 6-year CIP
because there are higher priority Water Utility projects.
Staff has evaluated the following four options for funding the city's share of the BCH
rehabilitation project:
1. Borrow from the Lakewood Pipeline Remediation Reserve and repay with 3%
interest
2. Reprioritize the existing 2009-2015 CIP
3. Combination of borrowing from the Lakewood Pipeline Remediation Reserve and
reprioritizing the existing CIP
4. Decline the grant money
AGENDA ITEM 9 6 PAGE 3
Temporary use of a limited portion of the funds in the Lakewood Pipeline Remediation
Reserve would allow the city to take advantage of the awarded grant funds and support
the city's Climate Action Plan goals while providing some long term revenue benefits to
the Water Utility. Use of this fund would not have a negative impact on water system
infrastructure by diverting funds from maintenance projects in the CIP. Staff believes that
reprioritization of CIP projects would create an undesirable increase in risk for the city's
ability to provide safe, reliable water service. Use of the Lakewood Pipeline
Remediation Reserve also would not negatively affect the utilities bond rating in 2010
when utilities is planning to issue a Water & Sewer revenue bond to fund ultraviolet light
disinfection, headworks rehabilitation and digester improvements at the Wastewater
Treatment Facility.
Staff and consultants have performed six internal inspections of Lakewood Pipeline since
it began operating in May of 2004. One of the primary objectives of the inspections has
been to monitor steel corrosion that has formed underneath cracks in the cement mortar
lining. Observations made during the sixth internal inspection, which was completed in
Dec. 2009, indicate that the corrosion issue has stabilized and extensive remediation
measures will not be necessary in the next five to ten years. Therefore, the risk of
borrowing some of the funds in the Lakewood Pipeline Remediation Reserve for a ten-
year period is low.
Rehabilitation of BCH will not affect current streamflows in Middle Boulder Creek and
main Boulder Creek. Following the purchase of the BCH facilities from Public Service
Company of Colorado (PSCO) in 2001, the city established minimum instream flow
levels for Middle Boulder Creek below Barker Dam. The city also discontinued the
PSCo practice of ramping up generation during peak demand periods on winter evenings
because this produced extremely high surges of water flow in Boulder Creek that were
harmful to aquatic habitat.
The city is in the process of negotiating a new power purchase agreement (PPA) with
PSCo/Xcel Energy for sale of the electricity generated at BCH. Under this new twenty-
year agreement, the city may be paid a flat generation fee of $40/ MW-hr, which would
result in about $465,000 of annual revenue for the water utility beginning in 2012. This
is more than the previous agreement for BCH, which paid an average of $24/1\4W-hr.
Under the new PPA, PSCo/Xcel would be allowed to use the Renewable Energy Credits
(RECs) associated with the BCH project. Negotiation of the PPA is expected to be
completed and presented in the first quarter of 2010.
The city has applied for and is awaiting issuance of a conduit exemption from licensing
from the Federal Energy Regulatory Commission for BCH. If approved, the exemption
would be issued in perpetuity, thus avoiding costly project relicensing efforts in the
future. The exemption would be amended to reflect the new generation capacity once the
modernization project is completed.
ATTACHMENTS:
Attachment A: Grant Application Summary
Attachment B: Technical Memorandum regarding BCH Grant
AGENDA ITEM 9 6 PAGE 4
Attachment A
Grant Application .Summary for
Modernization of the Boulder Canyon
Hydroelectric Project
DE-FOA-0000120
.ifA .,rr J 1 : k
K 4 Y I ~
Y-1
XMLNI'71-7 -.4
4ff~
t Project Narrative
DenrerPnblic Libram, Mestern History Collec rio!r
~ee ra F~
City of Boulder, Colorado
Department of Public Works,
DenrerPnblic Librarn Wfestern History Collection J
Utilities Division
7 P. O. Box 791
Boulder, CO. 80305
F 3! - _L Jr9 August 2009
sY ~ F Y ■ -
J
1
Project Overview and Objectives
The City of Boulder, Colorado ("the city' or "Boulder") is proposing to modernize its existing
Boulder Canyon Hydroelectric facility. Boulder Canyon Hydro was originally constructed in
1910 and has continuously produced electricity since that time. Some equipment in the facility
has been replaced, but much of it is decades old. The existing turbine and generator are more
than seventy years old and should be replaced soon if Boulder Canyon Hydro is to continue
operating. The facility is unique due to its history, the very high pressure of its water supply, its
construction, and its incorporation into the city's municipal water supply system. Rehabilitating
Boulder Canyon Hydro could provide a useful example for owners of other older projects of how
to deal with modernizing equipment within an existing building with existing connections to the
electrical grid and could also highlight the potential for power generation that might exist within
other municipal water supply systems.
Boulder is located on the Front Range of the Rocky Mountains and provides water service to
approximately 29,000 residential, commercial and industrial accounts with an annual treated
water demand of approximately 19,000 acre-feet or 6.2 billion gallons. The Boulder Creek
watershed is the city's primary municipal water supply source. The Boulder Creek watershed
water supply system also provides clean, renewable energy from generation of electricity at
hydroelectric plants installed on municipal water supply pipelines.
Beginning in the early 1980s, Boulder recognized the potential for hydroelectric energy
generation within its water system and began developing facilities to produce electricity as a by-
product of its water utility operations. Today, Boulder owns and operates eight hydroelectric
facilities on its raw water transmission and treated water distribution systems. These
hydroelectric plants produce environmentally-friendly hydroelectricity by making use of
pressure developed in municipal water supply pipelines due to the large elevation drop between
the city's diversion points in the mountains and delivery points on the plains. This pressure must
be reduced to treat and deliver the water for municipal purposes and would otherwise be wasted
through pressure-reducing valves.
The city's hydro plants are operated in a manner that does not diminish the primary purpose of
supplying municipal water. Revenue from the sale of the electricity allows the city's Water
Utility to maintain lower water rates for its customers. At the end of 2008, the city had generated
468,550,000 kilowatt-hours (kWh) of electricity since its first hydroelectric project went into
operation in 1985. Sale of this power has generated $22,674,000 of revenue for the Water
Utility, while providing environmental benefits through displacing the need to burn over 241,300
tons of coal and avoiding air emissions resulting from traditional coal-fired generation facilities.
The city's hydro facilities have frequently been cited in industry literature as an example of how
electricity can be derived with no additional environmental effects from water facilities that are
in existence and required for other purposes.
The existing Boulder Canyon Hydroelectric facility is located on Boulder Creek west of the city.
The power plant generates using untreated water diverted at Barker Reservoir located near the
town of Nederland at an elevation of about 8500 feet. The water is transported approximately
2
11.5 miles in the Barker Gravity Pipeline to a small regulating reservoir and then through
Boulder Canyon Penstock to the Boulder Canyon Hydro building at an elevation that is 1800 feet
lower, thereby producing 840 psi of pressure. Although the hydro plant originally operated with
two 10 megawatt (MW) turbine/generators, one of the generators failed in 2000. The remaining
operational turbine and generator date to 1936 and are at the end of their expected lives. Without
a new turbine and generator, operation of the hydro is expected to cease within 5 years or less.
Originally constructed in 1910 by the Central Colorado Power
Company for the sole purpose of hydroelectric power production, Objective:
the project began delivering water for Boulder's municipal water
supply in the 1950s. Almost all of the Barker Reservoir storage Increase generation and
has been converted to municipal water supply storage over efficiency of the 100-year-
space the course of the past few decades, so Boulder Canyon Hydro old Boulder Canyon
now operates almost exclusively using direct streamflows Hydroelectric facility
diverted from Middle Boulder Creek at Barker Reservoir. The
city purchased the hydro facilities from Public Service Company of Colorado in 2001 and
immediately established a minimum instream flow level below Barker Dam. Most of the water
for Boulder Canyon Hydro is now available from April to October when streamflows are higher
due to melting of the annual high mountain snowpack. The redirection of much of the historic
water flow to meet the city's municipal and minimum instream flow uses means that the existing
Boulder Canyon Hydro turbine is too large to operate efficiently. The city is proposing to install
a new turbine/generator unit approximately 5 MW in size that is appropriately sized for the
available water flow. This unit could generate about 580,000 MW-hours (MW-hr) over its fifty-
year life that would not otherwise occur. Even at a smaller capacity, actual annual generation
can increase in the future as compared to the past because of increased turbine efficiency with
proper sizing and decreased operational downtime compared to that presently experienced with
the old equipment.
Average annual Boulder Canyon Hydro generation from 2002 through 2008 has been about 8500
MW-hr, whereas annual generation with the proposed project could average about 11,000 to
12,000 MW-hr. The incremental change in annual generation is an additional 2500 to 2600
MW-hr per year, which is a 30% increase in generation over current conditions. However,
generation at Boulder Canyon Hydro will soon drop to zero without replacement of the existing
turbine and generator because they are beyond their expected life.
The one currently operational turbine/generator is a single nozzle Pelton turbine with a 5-to-1
flow turndown and a maximum turbine/generator efficiency of 81.8%. The proposed turbine
would be a double nozzle Pelton turbine with a 10-to-1 flow turndown and a maximum
turbine/generator efficiency of 88%. This alone represents a more than 6% increase in overall
efficiency. The existing operational turbine is estimated to operate with actual efficiencies in the
range of 40 to 70% due to age and non-optimal sizing of the turbine for the water flow available
to the unit. The turbine currently must be shut down whenever water flow drops to less than
about 8 cfs. An appropriately sized new turbine could likely operate in the range of 70 to 88%
through a large portion of the existing flow range and would not have to be shut down at low
flow rates.
3
In addition to turbine/generator replacement, upgrades to wiring,
improved lightning protection and installation of a remotely Objective:
operated turbine isolation valve is proposed to address safety and
operational efficiency issues with the aging power plant. Increase safety at Boulder
Deteriorated wiring insulation throughout the plant may cause Canyon Hydro
electrical shorts that can harm both personnel and equipment. The
city has purchased a thermal imaging camera to monitor rising
temperatures of the high voltage wiring in anticipation of risk
increasing to the point that the equipment must be retired.
Asbestos testing on existing wiring has been positive, constituting an additional safety hazard.
New electrical and control systems associated with the new turbine/generator installation would
address this issue.
Aging transformers with minimal protection from lightning strikes
at Boulder Canyon Hydro represent a safety hazard, an Objective:
environmental threat, and a source of decreased generation. For
example, lightning damage caused a two-month outage of the Increase protection of the
power plant in 2008, resulting in the loss of approximately 5225 Boulder Creek environment
MWh of generation. Two of the aging transformers are located
immediately adjacent to Boulder Creek. If lightning were to strike
these transformers directly, it could result in an oil spill into the
creek and cause significant environmental damage. An old on-site single-walled hydraulic oil
storage tank is another potential environment hazard. In conjunction with installation of a new
turbine/generator, the city proposes to install additional protection from lightning-caused surges,
remove the two transformers adjacent to the creek, and replace the on-site hydraulic oil storage
tank.
The existing turbine isolation valve (TIV), which was installed in
1910, cannot be remotely operated, nor does the valve close Objective:
automatically upon an emergency turbine stop. The existing TIV
would be prohibitively expensive to modify. Without remote TIV Modernize and integrate
operation, a runaway turbine condition could occur and cause control equipment into the
considerable damage to the turbine or possibly a penstock rupture. municipal water system
The environmental damage to Boulder Creek from rupture of the
840 psi penstock might take decades to mitigate. The only cost
effective way to rectify this situation is to install a state-of-the-art TIV at the time the turbine is
replaced.
When Boulder Canyon Hydro was constructed in 1910, it was the
highest head hydro plant west of the Mississippi River and Objective:
possibly in the United States. The project, backed by several
investors of historic importance both nationally and within the Preserve significant
state of Colorado, was notable in terms of construction difficulty historical engineering
and technological challenges. Due in part to its unique information prior to plant
engineering features and innovative construction techniques, modernization
4
Boulder Canyon Hydro is considered eligible for listing on the National Register of Historic
Places.' The power plant today exists in close to original condition. Prior to modernization,
Boulder proposes to document and preserve technical engineering data in accordance with
Historic American Engineering Record standards. This effort would include collection, review
and organization of the abundant historic documentation that exists for Boulder Canyon Hydro.
Completion of the modernization effort would have a long-term beneficial effect on the
historically significant Boulder Canyon Project. Modernization will allow for continued
operation of the hydroelectric plant, which will preserve the original function and use of the
power plant. Retaining original function is commonly recognized as one of the most effective
means of historic preservation.
Boulder has anticipated the need to upgrade and modernize the
Boulder Canyon Hydroelectric facility since the city's purchase in
2001 and, as a result, is in a position to move this project forward Objective:
to completion within two years of grant award. Boulder Canyon Complete modernization
Hydro currently operates under a license (P-1005) from the with minimal regulatory
Federal Energy Regulatory Commission (FERC) which expires on delay
August 31, 2009. The city began discussing options for
relicensing the project with the FERC in 2003. Recognizing both
capacity reduction and conversion of project facilities from primarily hydroelectric power
generation purposes to municipal water supply objectives, the city completed its consultation
process for project reauthorization in 2007 and 2008 and on March 9, 2009 filed its final
application for exemption of the Boulder Canyon facilities from licensing as a small conduit
hydroelectric facility. The city anticipates issuance of the order granting exemption of the
facilities by August 31, 2009. Conduit exemptions from licensing are issued in perpetuity,
eliminating the need for time-consuming and costly relicensing efforts in the future.
The conduit exemption order will reflect the continuing operation of a single 10 MW
turbine/generator as the project nameplate capacity. While the city is prepared to submit an
application to FERC for amendment of the exemption at such time that it replaces the existing
turbine unit, the city believes it meets the criteria for implementing the proposed changes without
prior FERC review and approval (as provided for in FERC regulations at 18 CFR §4.96).
Specifically, the city can provide assurances from fish and wildlife agencies that the proposed
change would be consistent with their understanding and expectations for the project. In
addition, installation of a new, appropriately sized turbine would not materially alter the design,
location or operation of the project.
In 2005, a feasibility study was completed to integrate municipal water supply reliability and
hydropower generation which showed that a 4.9 MW unit at Boulder Canyon Hydro would be an
appropriately sized replacement for the two 10 MW units currently installed. Modernization of
Boulder Canyon Hydro has a positive benefit-cost ratio and would allow the City of Boulder to
' In 1994, the Boulder Canyon Hydroelectric Facility Penstock was awarded the Historical Welded Structure Award
by the American Welding Society as it was the first structure to use acetylene welding in conjunction with the
ballpeen welding procedure and significantly advanced penstock technology when constructed in 1910.
5
maintain municipal water supply as a priority, improve reliability and flexibility of the water
supply system, reduce production of greenhouse gases in furtherance of the city's climate action
goals, and fully utilize hydroelectric potential while maintaining its existing instream flow
commitments for Boulder Creek.
The city has been a leader in development of hydroelectric potential in
municipal water supply systems. Through viewing the city water The project is part of a
system and its energy potential comprehensively as complementary comprehensive program to
resources, the city has developed innovations in methods for proper develop the energy potential
sizing of turbines when using consistent municipal water flows versus within the municipal water
more variable river flows and in use of pump/turbine units to maintain supply system.
proper pressures between water system pressure zones without wasting
the energy. BCH modernization is just one component of the city's overall comprehensive plan
to develop the hydroelectric potential of its municipal water supplies. Boulder has identified at
least three other potential hydro plant sites within its water system that could be developed if
funding can be accommodated within the Water Utility budget. If the city could reduce its costs
for BCH modernization, capital improvement budgets for other hydro improvements in the
system could be available sooner.
In general, the city policy for hydro potential development relies on economic as well as
environmental feasibility. Economic feasibility relies upon a project being able to pay for itself
during its expected lifetime.
The Boulder Canyon Hydro turbine/generator is at the end of its useful life and is expected to fail
in the next 5 years. Table 1, below, summarizes the incremental increase in energy production
and environmental benefits that would result from power plant modernization at the current time.
Modernization of the Boulder Canyon Hydro equipment was included in the city's master plans
for both the Middle Boulder Creek Watershed and the source water system. The Boulder City
Council adopted these plans in 2002 and 2009, respectively.
Required lead time for delivery of a turbine generator in the U.S. is
currently approximately 16 months. Notwithstanding, the city Boulder believes this project
believes project completion within 2 years of award is very possible will be operational within 2
for the following reasons: years of grant award.
■ Feasibility studies, including turbine sizing, have been
completed. This will allow the city to order the
turbine/generator as owner-procured materials shortly after grant award.
■ The city has completed the necessary consultation and application processes for the
FERC authorization of this project and expects to have a conduit exemption from
licensing in hand in the next several weeks.
■ AECOM will be the design engineer for this project. AECOM completed the feasibility
study for turbine replacement, has designed and constructed two of the city's other
hydroelectric plants and is very familiar with the existing and proposed facilities.
AECOM has extensive experience in planning designing and execution of hydroelectric
projects. AECOM has an extensive history of engineering consultation for the City of
Boulder and prepared the analysis of hydroelectric potential for the Boulder Canyon
6
Hydroelectric facility.
■ Final design, contracting, remaining minor permitting efforts, and other aspects of the
project (historic documentation, surge protection, transformer removal and oil storage
tank replacement) can be completed in advance of turbine delivery.
■ The power house is an existing structure. Therefore, modernization of the interior
equipment can be undertaken with no seasonal restrictions or weather-related delays.
The City of Boulder has successfully completed seven hydroelectric
installations on its municipal water supply system and has contracted The city/AECOMproject
with AECOM on its two most recent hydroelectric projects. Past team has a proven approach
experience has resulted in a proven, successful approach which will be to successful completion of
of immeasurable value in the completion of Boulder Canyon Hydro hydroelectric project design
modernization. and construction.
1. Equipment Procurement
The projected lead time for the turbine and generator package is estimated at 490 calendar
days (approximately 16 months) from receipt of Purchase Order. In order to assure
construction is completed by the end of the second year, issuance of the Purchase Order for
the turbine and generator package will be the first priority.
Initial engineering design efforts will consist of preparing technical specifications and
drawings for the 4.9 MW turbine generator procurement package by mid-February 2010. It
is anticipated that the Request for Proposal (RFP) document will be issued by the beginning
of March 2010. The bid review process is anticipated to be complete within two months,
and a purchase order will be issued to a vendor in mid-May 2010.
2. Engineering Design Services - Submittal coordination with turbine vendor
The technical specifications provided in the RFP document will include requirements for
equipment design submittals. It is anticipated that the following submittals will be reviewed
for conformity to the contract drawings and specifications:
• Manufacturer's design calculations including inertia calculations
• Manufacturer's design drawings of the turbine, generator, tailrace, hydraulic
power unit, and turbine inlet valve.
• Product data sheets of specific instrumentation.
3. Engineering Design Services - Preparation of final construction specifications and drawings
Final design and preparation of a complete specification and drawing bid package for
replacing the existing 10 MW Pelton unit at Boulder Canyon Hydroelectric facility with a
modern, more efficient 4.9 MW Pelton unit will be performed. The following technical
components will be included in final design activities:
• Geotechnical review - a review of the existing geotechnical data will be
performed to analyze the impact of the proposed modifications described below.
• Structural design - the existing unit is embedded in concrete. This concrete will
be removed and new concrete supports will be installed for the new unit.
7
• Civil design - minor modifications may be required in the tailrace area depending
on the new unit orientation. Piping modifications will be required upstream of the
new turbine to accommodate the smaller size and possibly a lower turbine setting.
• Hydro-mechanical - the design of the hydro-mechanical equipment will be in
close consultation with the turbine generator manufacturer. The equipment
includes the turbine, generator, hydraulic power unit, controls and switchgear and
inlet valve.
• Tie-in locations - two tie-in locations will be required. One will be for the new
turbine and one will be for the by-pass to the Betasso Hydro unit and the Water
Treatment Plant.
• Electrical and Controls - electrical and controls design will be based on upgrading
the existing equipment to meet the requirements of the new unit. The new unit
will be fully operational on the City's SCADA system.
• Operations and Maintenance Access - existing access to the facility will be
maintained for use with the new unit.
• Historic preservation considerations - the design will consider the requirements
for historic preservation of the existing facility.
Existing specifications used on previous City of Boulder projects will be used as a basis for
the Boulder Canyon Hydro specifications. Utilization of the existing technical specifications
will result in efficient use of the time and budget. AECOM understands the need to be
efficient and will thoughtfully implement measures to maximize the use of existing
information for this project.
The specifications and drawings will be prepared in consultation with the City and issued for
bid. Final design efforts will occur during the second, third and fourth quarters of the first
calendar year (2010). The final design package and construction bid documents will be
completed and ready for bid by the end of the first year (2010).
8
ATTACHMENT B
TECHNICAL MEMORANDUM
BY: Ned Williams
Carol Ellinghouse
Carol Linn
SUBJ: Boulder Canyon Hydro Modernization Grant and Possible Funding Sources for City
share
DATE: December 16, 2009
Summary
In October 2009, city staff submitted an application for rehabilitation of the city's Boulder
Canyon Hydro (BCH) facility to the Department of Energy (DOE) under a grant offering for
modernization of hydroelectric facilities through the Recovery Act stimulus funding program.
On November 4, 2009, the city received notice that its application had been accepted for
negotiation of an award of $1,180,000. The grant offering had stated that up to 50% matching
funds were available from DOE for selected projects and this was the basis of the city's
application. The city had submitted a proposed project cost of $5,155,000, had requested a
matching grant of at least $2.5 million from DOE and anticipated that the city's share would be
$2,655,000. With the actual grant award being $1,180,000, the city's share of funding will be
$3,975,000 if the DOE grant is accepted, which is $1,320,000 more than the submittal forms
indicated.
A decision regarding the city's acceptance of the grant must be made soon because of the grant
requirement that the rehabilitated hydro project be on-line by December 2011. This drives a very
tight schedule that requires design of the project to begin in January 2010 so that construction
can be completed in two years. In particular, information obtained as the grant application was
being developed indicated the required lead time for manufacture and delivery of a turbine-
generator is currently approximately 16 months, so the specifications must be completed and the
order placed in March 2010 to achieve the required completion date for the project.
This memo discusses the benefits and costs of rehabilitating the BCH facility and reviews
options for the city's portion of the project funding.
BCH Background
The city purchased BCH from Public Service Company (PSCo) of Colorado in 2001. The hydro
project was originally constructed in 1910. It had two 10 megawatt (MW) turbine-generators,
but one of the units failed just prior to the city's purchase. The remaining operational unit was
installed in 1936 and is not expected to last longer than another 5 years.
Most of the water that once ran through BCH before the city's use of the Barker facilities began
in the 1950s is now carried to Betasso Hydro and the Betasso Water Treatment Facility, thereby
Page 1
reducing the amount of power generation when compared to PSCo's operating practice. The city
completed preliminary studies of turbine-generator replacement options and concluded that a
new 5 MW unit would be appropriately sized for the amount of water remaining to be run
through BCH. If a new unit is installed, it could be expected to have a fifty-year life.
Rehabilitation of BCH with a new 5 MW unit was included as a recommended project in the
Source Water Master Plan and in the 20-year CIP. Public comment and WRAB review during
the Source Water Master Plan process supported the development of the hydroelectric potential
within the municipal water system to the extent reasonably possible and advocated payback
periods of as much as twenty years using hydro revenues from the project to offset the costs.
If a new turbine-generator unit is not installed, BCH could be decommissioned when the existing
unit fails. This would require completing a Federal Energy Regulatory Commission (FERC)
process since it is a licensed hydro project. Decommissioning would involve costs and would
include loss of future revenue potential at BCH.
During some months, a portion of the water that had been run through BCH could be run through
Betasso Hydro and then returned to Boulder Creek through the new discharge line from Betasso
as shown in Figure 1 below.
Figure 1
Increased Betasso Hydro Flows with No BCH Generation
&0
7.0
0.0
N
5.0
3
0
~y 4.0
d
R
`y 3.0
a
2.0
1.0
0.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
Not all of the BCH water can be used in this manner because most of the pipeline capacity in the
Betasso penstock is filled with municipal water during much of the year. The portion of BCH
water that could be run through Betasso Hydro would generate less electricity than if it were run
through the BCH because the pressure at Betasso Hydro is about 600 psi and the pressure at
BCH is about 800 psi. Using the Betasso Hydro in this manner will cause increased wear and
tear and could cause the need for a major rehabilitation of Betasso Hydro to be required in
Page 2
twenty years instead of twenty-five years as is currently expected. Nevertheless, running more
water through Betasso Hydro is an option to recover some of the generation potential and
revenue that would be lost should the city choose to pursue decommissioning of BCH.
BCH Benefits and Costs
Hydroelectric production at BCH provides revenue for the water utility from sale of the power to
Xcel Energy. It also provides green energy with environmental benefits due to offsetting the
need to burn coal for electricity production. Over the past five years, BCH has provided 20% of
the city's total hydropower production and has produced enough electricity to power about 1,500
Boulder homes each year. The amount of electricity produced by a new 5 MW unit will be more
than the existing 10 MW unit because the new unit will be more efficient and will be
appropriately sized for the available water flows so that it can continue generating at low flow
levels. The amount of energy production and environmental benefits for the existing BCH unit
and the proposed replacement unit are shown in Table 1.
Table 1: Energy Production and Environmental Benefits of the Existing and Proposed
BCH Turbine-Generators
Existing 10 MW Proposed 5 MW Change from
Unit Unit Existing
Expected Life <5 years 50 years >45 years
Average Annual MW-hr 8,500 11,660 3,160
Total lifetime MW-hr 42,500 583,000 540,500
Offset in Coal Consumption (tons) 22,000 300,000 278,000
Offset in SOz Emissions (tons) 30 450 420
Offset in NOx Emissions (tons) 70 900 830
Offset in CO2 Emissions (tons) 22,000 303,000 281,000
If the existing BCH turbine-generator failed in five years and was not replaced, the portion of
BCH water that could be run up to Betasso Hydro could generate an additional 850 MW-hrs at
that facility every year. Therefore, only about 90% of the generation and environmental benefits
associated with BCH would be lost as long as investments were made in the Betasso Hydro
facilities to address its rehabilitation needs as the equipment aged. This means that an
investment of about $5 million would need to be made for the Betasso Hydro rehabilitation in
twenty years instead of in twenty-five years.
The city is completing negotiations with PSCo/Xcel for a new Power Purchase Agreement (PPA)
for sale of the electricity generated at BCH. Under this new twenty-year agreement, the city may
be paid a flat generation fee of $40/ MW-hr. This is more than the previous agreement for BCH,
which paid an average of $24/MW-hr, but less than the favorable contract for Betasso Hydro,
which pays an average of about $55/MW-hr. Under the new PPA, PSCo/Xcel would be allowed
to use the Renewable Energy Credits (RECs) associated with the BCH project. It is expected
that the PPA will be ready for consideration in the first quarter of 2010.
Page 3
The current turbine-generator at BCH has very high operating and maintenance costs due to its
age and its configuration. It is projected that $13,700 will be spent in each of the years that this
unit remains operational. Annual O&M costs for a new 5 MW unit are expected to be less than
$4,000. If the existing BCH unit were not replaced and a portion of the BCH water were run
through Betasso Hydro, it is projected that O&M costs for Betasso Hydro and for the discharge
pipeline would increase by $1,000 per year.
The present worth of the revenues from rehabilitating BCH, less the construction cost over two
years and the O&M costs of the new unit over the next 50 years of its expected life, is equal to
$8,074,000 at a discount rate of 3%. The revenues less the cost of operating the existing turbine
for its expected remaining 5 years of life expressed as present worth equals $1,539,000. If it is
assumed that the portion of the BCH water that can be run through Betasso Hydro is delivered
there following the demise of the existing BCH unit, the present worth of the revenues less the
costs over a comparable 52 year period is $1,975,000.
Table 2 shows that if a twenty year period is examined, the present worth of the revenues from
rehabilitating BCH is $6,554,000. The present worth of the construction and O&M costs is
$3,970,000, which puts net revenues at $2,584,000 with a benefit/cost ratio for the project of
1.65. This is $695,000 more in net revenues over twenty years than produced by running the
existing turbine for five years before delivering a portion of the water through Betasso Hydro,
which has net revenues of $1,889,000. Looked at from a different perspective, the investment in
construction of the rehabilitated BCH would be recovered after ten years (ten year pay-back
period) of operation, or by 2021.
Table 2: Revenues and Costs of Existing and Proposed BCH Turbine-Generators
Existing 10 MW Present Worth
BCH Unit plus Proposed 5 MW Change from
Increase at Betasso Unit at BCH Existing
Hydro after 5 ears
Construction Costs for City
with Grant (split between 2010 n/a $3,975,000
and 2011)
Average Annual Revenues $340,000 for 5 years; $466,400 beginning
$34,000 thereafter in 2012
$13,700 for 5 years;
$1000 thereafter with $4,000 beginning
Average Annual Costs $557,500 to rehab in 2013
Betasso Hydro earlier
in 2030
PW of Revenues for 20 years $1,964,000 $6,554,000 $4,590,000
PW of Costs for 20 years $75,000 $3,970,000 $3,895,000
PW of Net Revenues (Revenues
minus Construction and O&M $1,889,000 $2,584,000 $695,000
Costs) for 20 years
PW of Net Revenues for 50 $1,975,000 $8,074,000 $6,101,000
years
Page 4
Financing Options
As part of the 2010 recommended budget submitted to Council, it was noted that the Utilities
division was pursuing federal stimulus funds through the American Recovery and Reinvestment
Act of 2009 (ARRA) on a case by case basis as opportunities arise. It was also noted that some
of the funding programs require a city match and, should the city be successful in an award,
Utilities may need to re-prioritize its capital improvement program, use financial reserves or a
combination of both in order to accept the award and fund the city's share of the project.
Staff has evaluated the following four options for funding the city's share of the BCH
rehabilitation project:
1. Borrow from the Lakewood Pipeline Remediation Reserve and repay with 3% interest
2. Reprioritize the existing 2009-2015 capital improvement program (CIP)
3. Combination of borrowing from the Lakewood Pipeline Remediation Reserve and
reprioritizing the existing CIP
4. Decline the grant money
Each of these options is explained in more detail below. Each option assumes that the city would
appropriate the total costs of the project, $5.155 million, and that the grant money would come in
as revenue to offset project costs as the grant reimbursements occur.
Staff also considered whether or not to use any of the water fund capital reserve ($2,000,000) or
unappropriated fund balance to fund some or part of the project costs. Because of the 2009
shortfall in water sale revenues and an anticipated Water & Sewer revenue bond issuance in
2010, Utility staff recommends maintaining the capital reserve and fund balance as much as
possible as the four options mentioned above are evaluated.
1. Borrow from the Lakewood Pipeline Remediation Reserve and repay with interest
This option is to borrow the $5.155 million from the Lakewood Pipeline Remediation
Reserve. This reserve currently has a balance of approximately $16.4 million. In 2006, the
city received a $15 million settlement for work associated with the monitoring, testing, repair
and/or replacement of the Lakewood Pipeline. To date this reserve has earned approximately
$2,000,000 in interest and approximately $750,000 has been spent on pipeline inspections.
Staff and consultants have performed six internal inspections of Lakewood Pipeline since it
began operating in May of 2004, with the most recent occurring in December 2009. One of
the primary objectives of the inspections has been to monitor steel corrosion that has formed
underneath cracks in the cement mortar lining. Observations made during the sixth internal
inspection of the Lakewood Pipeline indicate that the corrosion issue has stabilized and
extensive remediation measures will not be necessary in the next five to ten years.
This option would borrow $5.155 million from the Lakewood Reserve to fully appropriate
the funds for the project. The grant funds would replenish the reserve by $1.18 million as
they are received. The water utility would repay the reserve the remaining $3.975 million at
a 3% annual interest rate (to compensate for lost interest earnings) using revenues generated
from the reconstructed BCH Facility. Beginning in 2012, projected net revenues of about
$462,400 annually would be used to repay the $3.975 million, with interest, over ten years.
Page 5
This option does not require the city to defer capital projects in order to fund the matching
portion of the grant. This is favorable for the water utility and its customers because it
provides for maintaining the water delivery and treatment infrastructure. It is also favorable
because the city is anticipating issuing a Water & Sewer revenue bond in 2010 that will have
a bond rating partially based upon the city's commitment to maintain its infrastructure.
2. Reprioritize the existing 2009-2015 capital improvement program (CIP)
In order to appropriate $5.155 million, the capital projects shown in Table 3, which are
currently reflected in the CIP, would be delayed to a future date.
Table 3: Proposed Delayed Capital Projects under Option 2
Year Capital Project Budget
2009 Source Water Transmission Pipe Inspections $ 80,000
2009 Barker Relicensing $1,000,000
2009 Subtotal $1,080,000
2010 Chautauqua Storage Tank $ 85,000
2010 Betasso Storage Tank $ 265,000
2010 Barker Gravity Pipeline Repair $ 200,000
2010 Boulder Reservoir WTP $ 100,000
2010 Waterline Replacement $ 460,000
2010 Subtotal $1,110,000
2011 Chautauqua Storage Tank $ 858,000
2011 Barker Gravity Pipeline Repair $ 382,000
2011 Waterline Replacement $1,030,000
2011 Watershed Improvements $ 317,000
2011 Subtotal $Z587,000
Total CIP $4,777,000
Additional funds $ 378,000
Total Project Cost $5,155,000
The additional $378,000 would come from unappropriated fund balance. This option would
require a significant reprioritization of the CIP and would expose the water utility to greater
risk of a possible equipment or infrastructure failure by not keeping up with infrastructure
rehabilitation and improvements in a preventative or timely fashion. This reprioritization
represents an 11% reduction to the 2009 adopted CIP, a 25% reduction to the current 2010
CIP and a 40% reduction to the 2011 CIP.
3. Combination of borrowing from the Lakewood Pipeline Remediation Reserve and
reprioritizing the existing CIP
This option would be funded by both borrowing from the Lakewood Pipeline Remediation
Reserve and reprioritizing the existing CIP. It is summarized in Table 4.
Page 6
Table 4: Proposed Delayed Capital Projects under Option 3
Year Capital Project Budget
Grant Funds $1,180,000
2009 Source Water Transmission Pipe Inspections $ 80,000
2009 Barker Relicensin $1,000,000
2009 Subtotal $1,080,000
2010 Betasso Storage Tank $ 265,000
2010 Boulder Reservoir WTP $ 100,000
2010 Waterline Replacement $ 250,000
2010 Barker Gravity Pipeline Repair $ 200,000
2010 Subtotal $ 81 5, 000
2011 Barker Gravity Pipeline Repair $ 180,000
2011 Waterline Replacement $ 263,000
2011 Watershed Improvements $ 317,000
2011 Subtotal $ 760,000
Total CIP $2,655,000
Borrowing from the Lakewood Reserve $1,320,000
Total Project Cost $5,155,000
The CIP reprioritization is equal to what the city's share of the project would have been if the
initial grant request of $2.5 million been granted. The $1,320,000 borrowed from the
Lakewood Reserve would be repaid from revenues generated by the BCH Facility over three
years beginning in 2012. This also assumes a 3% interest rate on funds borrowed from the
reserve. This option requires somewhat less of a reprioritization of the CIP than in Option 2
but also exposes the water utility to greater risk of possible equipment or infrastructure
failure by not keeping up with the infrastructure rehabilitation and improvements in a
preventative or timely fashion. This reprioritization represents an 11% reduction to the 2009
adopted CIP, an 18% reduction to the current 2010 CIP and a 12% reduction to the 2011 CIP.
4. Decline the grant money
With this option, based on the payback period of the project and the risk to the utility by
reprioritizing the CIP and/or borrowing funds from the Lakewood Pipeline Reserve, the city
decides it is not in its best interest to rehabilitate the BCH facility at this time.
The reprioritization of CIP projects required for Options 2 and 3 is extensive and Utility staff
believes it would create a very undesirable increase in risk for the city's ability to provide safe,
reliable water service. Staff recommends that if Option 1 is not selected, then Option 4,
declining the grant money, should be selected in preference to Options 2 or 3.