HomeMy WebLinkAbout5 - Final recommendation on Wastewater Utility Master Plan (WWUMP) CITY OF BOULDER WATER RESOURCES ADVISORY BOARD AGENDA ITEM MEETING DATE: May 18, 2009 AGENDA TITLE: Update on the Final Wastewater Utility Master Plan (WWUMP) PREPARING DEPARTMENT: Robert E. Williams - Director of Public Works for Utilities Robert J. Harberg -Utilities Planning and Project Management Coordinator Douglas Sullivan - Engineering Project Manager - Presenter FISCAL IMPACT: There are no fiscal impacts at this time. However, staff will need to analyze how to allocate future CIP funding associated with the recommended projects identified in the WIAMU v P. PURPOSE: This memorandum presents an update on the final Wastewater Utility Master Plan. EXECUTIVE SUMMARY: The Wastewater Utility Master Plan (WWUMP) is an overarching document that „'rr is intended to present key issues, programs, projects, and associated budgets for the City's Wastewater Utility including the collection system, wastewater treatment plant, and associated water quality and support programs. The WWUMP is supported by The Wastewater Utility Master Plan is the overarching three primary planning documents for the planning document for the Utility Wastewater Utility: Wastewater Collection System Master Plan (WWCSMP), Wastewater Treatment Plant Master Plan (WWTPMP), and the Water Quality Strategic Plan (WQSP). The mission of the Utilities Division is to provide quality water services, as desired by the community, in a manner which -emphasizes efficient management of fiscal and natural resources, and protects human and environmental health. In general, the planning process for the Wastewater Utility focuses on identifying opportunities that continue the high level of service AGENDA ITEM # 5 Page 1 provided to its customers and evaluating the associated cost of the opportunities. The opportunities and recommendations resulting from the planning process take the form of capital construction projects; system rehabilitation and repair projects; preparing systems and operational processes that anticipate future regulations; and evaluating staffing needs. Wastewater and water quality planning projects, such as the WWTPMP, WWCSMP, and WQSP are the primary tools that provide the detailed analysis that result in the opportunities and recommendations contained within the WWUMP. A series of guiding principles, policies and implementation measures were used to define the planning process for the Utility. The guiding principles for the WWUMP are based on Boulder's planning approach to community sustainability through evaluating social, environmental, and economic impacts associated with various program and projects within the city. Specifically, the guiding three principles for the WWCM' are: • Protect Public Health and Safety • Protect Boulder's Natural Resources and the Environment • Maximize the use of the Wastewater Utility's Funds In general, the policies that support the guiding principles noted above are defined by the Boulder Revised Code (BRC) and the Boulder Valley Comprehensive Plan (BVCP). The WWTPMP, WWCSMP and the WQSP provide the implementation measures by defining planning elements, requirements, recommendations, and, where applicable, identify capital improvement projects. BACKGROUND City staff presented a draft Wastewater Utility Master Plan (WWUMP) at the March 2009 Water Resources Advisory Board (WRAB) meeting. The WWTPMP was accepted by the WRAB in June 2007. The WWCSMP was accepted by the WRAB in December 2008. The WQSP was accepted by the WRAB in April 2009. FISCAL IMPACTS There are no fiscal impacts at this time. However, Utilities will need to analyze how to allocate future CIP funding associated with the recommended projects identified in the WWUMP. The Final WWUMP is included as Attachment A. The 20-year GIP (2010-2030) is included as Attachment B. Wastewater Utility CIP The Wastewater Utility Master Plan (WWUMP) includes a comprehensive list of Wastewater Utility projects to be completed during the 20-year planning period. These include wastewater treatment plant capital and maintenance related projects, as well as wastewater collection system capital and maintenance related projects. The 2010-2030 Wastewater Utility Fund CIP has numerous line items identifying various projects for the WWTP and the sanitary sewer collection system. The significant CIP expenditures fall into the following three categories: • WWTP Capital Projects • WWTP Rehabilitation Projects • WWCS Rehabilitation Projects AGENDA ITEM 4 5 Page 2 WWTP Capital Proiects There are five (5) significant WWTP capital projects currently identified in the 20-yr CIP. The total cost of these projects (in 2008 dollars) is estimated at $40,000,000. These projects, their estimated cost, and their projected timing are listed below: • UV Disinfection - $4,400,000 - 2010 • Digester Modifications - $4,000,000 - 2010 • Headworks Improvements - $15,600,000 - 2016 • Phase 2 Improvements (Nutrient removal) - $15,000,000 - 2020 • Endocrine Disrupting Compounds (EDC's) removal - $19,000,000 - 2030 Utilities staff is currently completing a WWTP Evaluation project which is an analysis of the UV Disinfection, Digester Modifications, and Headworks Improvements projects. This analysis will present several process alternatives for the various facilities, their respective estimated costs, and will provide a recommendation regarding their overall priority. WWTP Rehabilitation Proiects In addition to the WWTP capital projects listed above, there are numerous WWTP rehabilitation projects identified in the CIP to address the plant's aging infrastructure. These projects are listed in the CIP in years 2016 through 2030, and have a combined cost (in 2008 dollars) of $8,500,000. Utilities staff is in the process of reviewing the WWTP rehabilitation analysis and associated project recommendations. WWCS Rehabilitation Proiects There are numerous wastewater collection system improvement projects currently identified in the 20-yr CIP. These projects were identified in the Wastewater Collection System Master Plan which was accepted by the WRAB in December 2008. The CIP currently lists four (4) Tier 1 projects (highest priority) and seven (7) Tier 2 projects (second highest priority). The total cost (in 2008 dollars) for these eleven projects is estimated at $28,000,000. The Tier 1 and Tier 2 project groups are listed below with their estimated cost and projected timing: • Tier 1 Projects - $5,000,000 - 2016 through 2021 • Tier 2 Projects - $23,000,000 - 2021 through 2030 Water Quality Strategic Plan The Water Quality Strategic Plan (WQSP) identified a number of recommendations • Adopt the strategic plan's water quality goals in to the BVCP • Incorporate water quality goals into citywide planning efforts and City regulations, policies and procedures. • Develop annual work plans and water quality reports • Prepare for future water quality regulations. Wastewater and Environmental Laboratory Program • Perform Business Case Evaluation • Staffing Analysis AGENDA ITEM # 5 Page 3 Industrial Pretreatment • Modify existing City Code to address grease removal equipment and develop enhanced inspection process • Perform a Business Case Evaluation for investment in a Fats, Oil and Grease Program a Identify all food service establishments requiring grease removal o Develop a policy on how to address food service establishments that do not have grease removal equipment. Investment Program Options The W WUMP presents three Utility investment programs based on different levels of funding including: the Fiscally Constrained Plan, the Action Plan, and the Vision Plan. These programs implement the policy direction of the WVi UMP at the three funding levels. Fiscally Constrained Plan The Fiscally Constrained Program reflects an investment strategy which assumes an annual Wastewater Utility Fund rate increase of two percent (2%) in 2010, and a three percent (3%) annual increase in years 2011 through 2030. Under the Fiscally Constrained program, there are numerous programs and projects which would be either eliminated or have reduced funding. These include the following: • Either the UV Disinfection or the Digester Modifications project (both scheduled for construction in 2010) would have to be eliminated in the 20-year CIP • The 2016 Headworks Improvements project would be eliminated from the 20-year CIP • The 2020 Phase 2 Improvements project (Nutrient Removal) would be eliminated from the 20-year CIP o This project would likely be required to address CDPHE permit issues • The 2030 Endocrine Disrupting Compounds (EDC) removal project would be eliminated from the 20-year CIP o This project would likely be required to address CDPHE permit issues • The WWTP Rehabilitation funding would be eliminated from the 20-year CIP • The Wastewater Collection System Replacement projects (Tier 1 and Tier 2) would be eliminated from the 20-year CIP • The Sanitary Sewer System Rehabilitation funding would be eliminated from the 20-year CIP • Future budget supplementals would be eliminated from the 20-year CIP Action Plan The Action Program reflects an investment strategy which assumes an annual Wastewater Utility Fund rate increase of four percent (4%) in years 2016 through 2030, with the following exceptions. The Action Plan will follow the recommended 6-year (2010-2015) CIP which includes the following rate increases: 2010=2%, 2011-2012=3%, 2013=4%, 2014-2015=6%. There is one period of increased funding which is necessary to maintain a positive fund balance in 2030. Two consecutive years (2019 and 2020) of nine percent (9%) rate increase would be required to fund the Nutrient Removal project. Under the Action Plan, there are a few programs AGENDA ITEM # 5 Page 4 and projects which would be either eliminated or have reduced funding. These include the following: • The 2030 Endocrine Disrupting Compounds (EDC) removal project would be eliminated from the 20-year CIP o This project would likely be required to address CDPHE permit issues • The Wastewater Collection System Replacement projects (Tier 2) would be eliminated from the 20-year CIP Vision Plan The Vision Program reflects an investment strategy which assumes an annual Wastewater Utility Fund rate increase of four percent (4%) in years 2010 through 2030 with the following exceptions. There are three periods of increased funding necessary to maintain a positive fund balance in 2030. Two consecutive years (2014 and 2015) of eight percent (8%) rate increases would be required to fund the Headworks Improvements project. Two consecutive years (2019 and 2020) of eight percent (8%) rate increases would be required to fund the Nutrient Removal project. Two consecutive years (2029 and 2030) of eight percent (8%) rate increases would be required to fund the EDC Removal project. Under the Vision Plan, there are no programs that would have reduced funding. ANALYSIS A lengthy Analysis section was included in the March 23, 2009 Water Resources Advisory Board Agenda Item. OTHER IMPACTS: None OTHER BOARD AND COMMISSION FEEDBACK: None PUBLIC FEEDBACK: None STAFF RECOMMENDATION: Utilities staff recommends that the WRAB accept the Wastewater Utility Master Plan (WWUMP) recommendations including the priorities assigned to the various projects and provide any other recommendations concerning the allocation of Capital Improvement Program (CIP) funding to these projects and other funding options that the WRAB would like Utilities staff to consider. Attachments: A. Final Wastewater Utility Master Plan - Executive Summary B. 20-year CIP (2010-2030) AGENDA ITEM # 5 Page 5 Wastewater Utility Master Plan LA, im EXECUTIVE SUMMARY Introduction The Wastewater Utility Master Plan (WWUMP) is the overarching planning document that is intended to present key issues, programs, projects and associated budgets for the collection system, wastewater treatment plant and water quality programs. The WWUMP is supported by .three primary planning documents for the Wastewater Utility: the Wastewater Collection System Master Plan ("'CSMP), the Wastewater Treatment Plant Master Plan (WWTPMP), and the Water Quality Strategic Plan (WQSP). Boulder's wastewater collection system and the 75t" Street WWTP serve residences and businesses within the 26 sq. mule W,srewater Utility Service Area (W11S / E ! , _ 1 ~ Areas outside the WUS.A bOLIndar_y are served by other / bay, utility districts or septic systems. Boulder's wastewater collection system currently series a population of approximately 110,000 peopp le and 101,000 employees ~ ~J•-I_ associated with commercial and industrial business. CooseCreek - Projected growth is anticipated to occur primarily through in-fill and redevelopment projects resulting in an estimated 128,000 people and 156,000 employees within the W - S A. L Boulder Creek A series of guiding principles were used to define the SouM Boulder Creek planning process for the Utility. These guiding principles are based on Boulder's planning approach to Boulder's Wastewater Utility Service Area community sustainabihty through evaluating social, encompasses 26 sq.mi. and contains five environmental and economic impacts associated with interceptor sewer basins various program and projects within the city. Specifically, the three guiding principles for the WWUMP are: Protect Public Health and Safety / Protect Boulder's Natural Resources and the Environment / Maximize the use of the Wastewater Utility's Funds Wastewater Utility Master Plan Wastewater Treatment Plant Master Plan The Wastewater Treatment Plan Master Plan (WW'TPNfP) documents past decisions, the current facility, and presents the approach that has been used to reach decisions on process selection and introduce some future decisions that will be facing the utility. To continue to provide the level of service required by federal regulations and match the expectations of the community presented in the BVCP Goals, ongoing improvements to the treatment facility are necessary. The WW IP was upgraded in 2008 to meet fixture wastewater treatment capacity demands and new ammonia-nitrogen limits that were incorporated in the CDPS permit. The upgrades included improvements to both the liquid stream treatment and solids dewatering processes (Phase 1). The current treatment capacity is 25.0 million gallons per day (mgd) on a maximum month basis and provides adequate capacity to meet population growth past 2025 (the current average annual flow rate is approximately 15 mgd). The Phase 1 improvements also kept the future total nitrogen discharge at or below the current level. The solids dewatering process improvements increased solids from the liquid stream treatment process and reduced the volume of dewatered solids that must be transported from the WWTP site. Phase 1B construction, currently planned for 2010-2011, will jinclude a UV disinfection system, solids stabilization (anaerobic digester) improvements, and possibly improvements to the headworks facility. Phase 2 construction, scheduled for 2020, includes expansion of the bioreactor with improvements to biologically remove nitrate and phosphorus. WWTP Evaluation Even though the City of Boulder recently completed $45 million in major improvements to the liquid and solids handling processes at the 75th Street Wastewater Treatment Plant, new discharge permit requirements are expected in 2010 and will require bringing the entire facility up to the same level of treatment capacity. As such, the City is currently in the process of evaluating the WWTP's treatment process capabilities - specifically focusing on the following three areas: a Evaluate the plant's anaerobic digestion process (capacity, mixing, heating, etc.) and recommend improvements to provide greater capacity and operational stability. / Evaluate UV disinfection alternatives to replace the existing gas chlorine and sulfur dioxide systems. p Evaluate the WW'IP's ability to meet the City's upcoming CDPHE permit effluent. Wastewater Utility Master Plan LOA 1---J The WWI? Evaluation project is currently under way and recommendations are expected by the fall of 2009. Design of the recommended improvements is scheduled for the end of the year 2009 with construction beginning in 2010. Future WWTP Modifications Discharge permit limits are revisited every five years, and it is anticipated that some level of TIN and phosphorus removal may be required by future discharge permits. Additionally, the Boulder WWI'P may be required to remove microconstituents. Microconstituents include very small particles such as endocrine disrupting compounds and disinfection byproducts. Other future projects identified in the CIP include modifications to, or the replacement of the Headworks facility. Wastewater Collection System Master Plan The WWCSMP is a comprehensive planning document that assesses the conveyance capacity of Boulder's sanitary sewer system and identities recommendations with associated capital cost estimates to resolve conveyance capacity deficiencies. The collection system master planning process included the following key elements- Land Use and Flow Projections 1 Collection System Hydraulic Analysis ► Improvement Alternatives and Recommendations / Collection System Operation and Maintenance ► Collection System Rehabilitation Budgeting Land Use and Flog Projections Land use planning projections for both population and employment were developed within the WUSA. There are three prominent planning documents that establish population and employment projections for the WUSA. and included 1) 2007 DRCOG Traffic Analysis Zones, 2) 2007 WWTP Master Plan and 3) 2008 Boulder Valley Comprehensive Plan (BVCP). These documents include consideration for both existing and future land uses, as well as historical and projected population trends. The resulting land use population and employment projections are summarized in the following table. Wastewater Utility Master Plan Year 2008 2015 2020 2025 Buildout (2030) Population 110,092 119,072 122,529 124,266 128,162 Employment 100,598 128,918 134,381 136,706 155,864 Total average dry weather flow (ADWF) or base flow projections in the collection system for existing and fixture conditions are comprised of population, employment and Significant Industrial User (SIU) contributions. The population and employment contributions are combined with the unit flow factors of 102 gpd per capita and 50 gpd per employee. The SIU contributions are based on 2006/2007 flow data from each user adjusted for domestic flow. The resulting wastewater flow projections under annual average dry weather flow conditions are summarized in the following table. Year 2008 2015 2020 2025 Buildout (2030) Population ADWF (mgd) 111.3 12.1 12.5 12.7 13.1 Employment ADWF (mgd) 5.0 6.5 6.7 6.8 7.8 SIU ADWF (mgd) 0.6 0.6 0.6 0.6 0.6 Total ADWF (mgd) 16.9 19.2 19.8 20.1 21.5 Z, L The purposes of the conveyance system analysis were to 1) document the analysis of the existing collection system during dry weather and wet weather flows and 2) to identify and characterize hydraulic capacity issues. By analyzing the existing collection system under existing and buildout flow conditions, problem areas were identified for both land use scenarios. The primary source of data that was used for the collection system hydraulic model and analysis was Boulder's sanitary sewer Geographic Information System (GIS) layers for manholes and sewer pipes. The collection system pipes with identified capacity limitations, established from the model results, were examined to identify likely hydraulic issues under the various flow scenarios. There are a total of 138 pipes in the analyzed collection system with hydraulic deficiencies identified. A detailed problem identification and characterization process was completed to better understand the nature and extent of these problems. The hydraulic problems were separated into two categories: Type A and Type B. Type A problems consisted of a series of under capacity pipes that were hydraulically connected to one another. Type B iv Wastewater Utility Master Plan LAI problems are isolated hydraulic restrictions that are not hydraulically connected to other problem locations or series of problem pipes. Recommended Collection System Improvements The recommended system improvements were developed to resolve the existing and future capacity issues are shown on the following figure. This figure includes both improvements that address Type A and Type B problems. The recommended improvements were grouped in three tiers to establish implementation priority: ► Tier 1 projects address Type A problems and have the highest priority; ► Tier 2 projects also address Type A problems but have lower priority compared to Tier 1; ► Tier 3 projects address Type B problems which have the lowest priority. The improvement priorities were assigned based on a number of qualitative factors including the flow conditions in which they occur (existing versus future), extent of the problem, potential for sanitary sewer overflows (SSOs) and service lateral backups, ease of constructability, and relative benefit over other improvement projects. The resulting implementation priorities and associated estimates of capital construction cost are shown in the following table. Improvement Priority Capital Construction Cost Tier 1 $4,977,000 Tier iI $22,664,000 Tier III $2,296,000 $29,937,000 Collection System Operations and Maintenance The WWCSMP project team reviewed the collection system operations and maintenance (O&M) procedures. The purpose of this O&M procedure was to review the current state of collection system O&M practices and evaluate potential increases in service levels due to trends in the regulatory environment in the western United States. In addition, the 2008 QualServe peer review program and self assessment survey evaluated the Utility's overall performance, efficiency and customer service as well as maintaining industry best management practices. V Wastewater Utility Master Plan Both the QualScrv program and the WWCSMP O&M review found that the Gravity System's Maintenance group operates and maintains the collection system such that it continues to provide a high level of service to its cxisting customers. Collection System Rehabilitation Budgeting Boulder developed a methodology for determining the mileage and cost of the 20-year CIP for rehabilitating wastewater pipes and manholes. This methodology was based on spreadsheet model that characterized pipe failure as a function of time to assist in forecasting long-term budgetary needs for rehabilitation of sanitary sewer pipe. This analysis resulted in a recommendation for an annual manhole and sewer pipe rehabilitation budget of $850,000. This methodology was given an independent review which recommended that an annual sewer rehabilitation budget of $500,000 would be adequate for the 20-year planning period. Water Quality Strategic Plan The Water Quality Strategic Plan (WQSP) is the first comprehensive planning effort to address water quality policies and priorities for the City. The purpose of the WQSP is to develop clear and concise water quality goals, develop recommendations and performance measures to achieve these goals, and provide a process to address current and future water quality challenges. The WQSP has been developed, and will be implemented by the City's Water Quality and Environmental Services (WQES) Group within the city of Boulder Public Works, Utilities Division. The WQES Group is funded through the city's Water, Wastewater, and Stormwater enterprise funds and supports the Utilities Division water services with seven programs. The Industrial Pretreatment JPJ) and Laboratory Services programs are included in this WQSP as they are directly related to the wastewater utility planning effort. ► industrial Pretreatment / Water Conservation / Water Quality Planning ! Laboratory Services ► Water Quality Education / Stormwater Quality ► Drinking Water Quality industrial Pretreatment Program 'T'he City's IPT program is part of the Public Works, Utilities, Water WQES Group. The WQES Group serves as an in-house technical resource for Utilities and other City departments to help maintain compliance with various levels of regulations. The current, primary purpose of the city of Boulder IPT program is to control or limit the discharge of toxic or hazardous waste V; Wastewater Utility Master Plan into the sanitary sewers and thus the City's 75th Street WWTP. The primary objectives of the IPT program are described as follows: / To prevent the introduction of pollutants into the city of Boulder wastewater collection and treatment system that could interfere with plant operation. / To prevent the pass-through of untreated pollutants into Boulder Creek. ► To improve recycling capabilities of sludge. ► To protect the general health and safety of wastewater treatment plant workers and downstream users. / To encourage pollution prevention as a feasible alternative to treatment and disposal. IPT Gaps, Deficiencies and Recommendations In addition to the ongoing responsibilities of the IPT Program, special studies and/or additional programs are necessary to further characterize industrial and commercial discharges to the city's sanitary sewer system sources, support compliance with 1,VWTP discharge permit requirements and collect data and information in preparation for future regulatory requirements. The following programs or studies should be evaluated and modified or initiated as necessary. / Fats, Oil and (--'tease Program o Evaluate potential modifications to the existing FOG program and regulations. / Industrial Waste Survey o Consider initiating a comprehensive industrial waste surveys. / Business Inventory Mailing o Send out business questionnaires to determine if targeted businesses continue to be non-significant or move into a significant industrial user category. Wastewater and Environmental Laboratory Program The WEL Program currently provides broader support for the WWTP including biosolids analysis, field services including water quality monitoring and management of the laboratory information management system (LIMS) and database system. WEL program responsibilities will continue to expand as increasingly complex and interrelated water quality regulations develop. WEL Program Gaps, Deficiencies and Recommendations In addition to the ongoing responsibilities of the WEL Program, special studies and/or additional programs are necessary to further characterize WWTP performance, characterize water quality conditions in Boulder Creek and provide compliance support for State and Federal regulations. It is recommended that the following programs or studies should be evaluated and modified or initiated as necessary. A Wastewater Utility Master Plan / Evaluate Laboratory Size and Function o Perform Business Case Evaluation on the Wastewater and Environmental Laboratory Program / Staffing Analysis o Review staffing levels compared to other municipalities. / Laboratory Maintenance o Ongoing funding for equipment replacement and laboratory upgrades Wastewater Utility CIP The Wastewater Utility Master Plan (WWUMP) includes a comprehensive list of Wastewater Utility projects to be completed during the 20-year planning period. These include wastewater treatment plant capital and maintenance related projects, as well as wastewater collection system capital and maintenance related projects. The 2010-2030 Wastewater Utility Fund CIP has numerous line items identifying various projects for the WWTP and the sanitary sewer collection system. The significant CIP expenditures fall into the following three categories: / WW'I`P Capital Projects 1 WWTP Rehabilitation Projects ► WWCS Rehabilitation Projects 'T'here are five (5) significant WW IP capital projects currently identified in the 20-yr CIP. The total cost of these projects (in 2008 dollars) is estimated at $40,000,000. These projects, their estimated escalated cost, and their projected timing are listed below: / UV Disinfection - $4,400,000 - 2010 ► Digester Modifications - $4,000,000 - 2010 ► Headworks Improvements - $15,600,000 - 2016 / Phase 2 Improvements (Denitrification & Phosphorus removal) - $15,000,000 - 2020 ► Endocrine Disrupting Compounds (FDC's) removal - $19,000,000 - 2030 Utilities staff is currently completing a WW 1P Evaluation project which is an analysis of the UV Disinfection, Digester Modifications, and Headworks Improvements projects. This analysis will present several process alternatives for the various facilities, their respective estimated costs, and will provide a recommendation regarding their overall priority. Viii Wastewater Utility Master Plan WWTP Rehabilitation Projects In addition to the WWTP capital projects listed above, there are numerous WWTP rehabilitation projects identified in the CIP to address the plant's aging infrastructure. These projects are listed in the CIP in years 2016 through 2030, and have a combined cost (in 2008 dollars) of $8,500,000. Utilities staff will continue to review the WWTP Rehabilitation analysis annually to identify the estimated timing for the various rehabilitation projects within the 6-year CIP. WWCS Rehabilitation Projects Lastly, there are numerous wastewater collection system improvement projects currently identified in the 20-yr CIP. These projects were identified in the Wastewater Collection System Master Plan which was accepted by the WRAB in December 2008. The CIP currently lists four (4) Tier 1 projects (highest priority) and seven (7) Tier 2 projects (second highest priority). The total cost (in 2008 dollars) for these eleven projects is estimated at $28,000,000. The Tier 1 and Tier 2 project groups are listed below with their estimated cost and projecting timing: ► 'Pier 1 Projects - $5,000,000 - 2016 through 2021 ► Tier 2 Projects - $23,000,000 - 2021 through 2030 Investment Program Options The WWUMP presents three Utility investment programs based on different levels of funding including the following: ► Fiscally Constrained Plan ► Action Plan ► Vision Plan These programs implement the policy direction of the WWUMP at the three funding levels. Fiscally Constrained Plan The Fiscally Constrained Program reflects an investment strategy which assumes a Wastewater Utility Fund rate increase of two percent (2%) in 2010, and a three percent (3%) annual increase in years 2011 through 2030. Under the Fiscally Constrained program, there are numerous programs and projects which would be either eliminated or have reduced funding. These include the foll owing: ix Wastewater Utility Master Plan Lai ► Either the UV Disinfection or the Digester Modifications project (both scheduled for construction in 2010) would need to be eliminated from the 20-year CIP ► The 2016 Headworks Improvements project would be eliminated from the 20-year CIP / The 2020 Phase 2 Improvements project (Nutrient Removal) would be eliminated from the 20-year CIP o This project would likely be required to address CDPHE permit issues ► The 2030 Endocrine Disrupting Compounds (EDC) removal project would be eliminated from the 20-year CIP o This project would likely be required to address CDPHE permit issues / The WWTP Rehabilitation funding would be eliminated from the 20-year CIP ► The Wastewater Collection System Replacement projects (Tier 1 and Tier 2) would be eliminated from the 20-year CIP / The Sanitary Sewer System Rehabilitation funding would be eliminated from the 20-year CIP ► Future budget supplementals would be eliminated from the 20-year CIP .Ction Plan The Action Program reflects an investment strategy which assumes an annual Wastewater Utility Fund rate increase of four_ percent (4`%) in years 2016 through 2030, with the following exceptions. The Action Plan will follow the recommended 6-year (2010-2015) CIP which includes the following rate increases: 2010=2%, 2011-2012=3%, 2013=41%, and 2014- 1.015=6%. There is one period of increased funding which is necessary to maintain a positive fund balance in 2030. Two consecutive years (2019 and 2020) of nine percent (99/6) rate increases would be required to fund the Nutrient Removal project. Under the Action Plan, there are a few programs and projects which would be either eliminated or have reduced funding. These include the following: 1 The 2030 Endocrine Disrupting Compounds (EDC) removal project would be eliminated from the 20-year CIP o This project would likely be required to address CDPHE permit issues ► The Wastewater Collection System Replacement projects (Tier 2) would be eliminated from the 20-year CIP '~Zhsicn Plan The Vision Program reflects an investment strategy which assumes an annual Wastewater Utility Fund rate increase of four percent (4%) in years 2010 through 2030 with the following exceptions. There are three periods of increased funding necessary to maintain a positive fund balance in 2030. Two consecutive years (2014 and 2015) of eight percent (80/6) rate increases would be required to fund the Headworks Improvements project. Two consecutive years (2019 Y. Wastewater Utility Master Plan f a and 2020) of eight percent (80/6) rate increases would be required to fund the Nutrient removal Improvements project. Two consecutive pears (2029 and 2030) of eight perceni (8%) rate increases would be required to fund the EDC removal project. Under the Vision Plan, there are no programs that would have reduced funding. A A B C D E F G H I J K L M N 0 P 1 ACTION PLAN _ CITY OF BOULDER 12-May-DR. 2 2010.2015 CAPITAL IMPROVEMENT PROGRAM 3 WASTEWATER UTILITY FUND Assumed Inflation Rate 3.00% ESTIMATED 2008 2009 2010 2011 2012 2013 2014 2015 2018 201,7 2016 2019 2020 PROJECT NAME 2008 COST ACTUAL REVISED RECOMMENDEE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED Wastewater Treatment 77 WWTP Pumps 421339 _ $0 SO SO $150,000 $0 `;~36 Dui? S0 _ $0 _ $D _ 50 _ 50 77 WWTP Permit Improvements 421617 3572,876 $345,659 $D SO so $0 S115,921 SO So 54 $0 $1,560,153 $0 WWTP Permit Improvements - Projected Bon( 425xxx $10.000,000 s0 SO $0 s0 $0 SO $0 s0 so so so $0 $14,257,609 WWTP Laboratory s0 _ $0 $0 $0 50 _ $0 _ $0 SO SO $0 $0 $0 $0 Lower Boulder Creek Enhancement 421661 $0 $0 _ $0 $0 _ $0 50 _ $0 _ $0 $0 _ 54 _ SD SO . $o WWTP Headworks 421003 - $0 $300,000 SD so so $0 1 $0 $o So s0 $o WWTP Headworks-Projected Bend $12,320,000 $0 $9 $0 so s9 $0 $0 s!r St`,vSfr;lSQt so $0 s0 $0 WWTP InsirumantationrControl 421437 s0 s0 $75,000 $0 So $0 s0 $0 so $0 5o so $0 50 5100,000 ,Nri.],ID pn lt)0,0O0 iJ~?00 $O $0 _ So WWTP Electrical - 421439 1 $o $0 $o WWTP Activated Slodge _ $o $0 $o $0 $o ' :''1 $0 $0 $0 $o $0 - $o WWTPPrimary Clabfars 421005 $0 SO _ SD 30 _ $300,000 $0 $0 $0 . $0 $o $0 $o _ $o 21 WWTP Secondary Clarifiers 421006 $0 $200,000 s0 $0 so 50 $0 _ $o _ $0 _ _ $0 $0 50. SO WWTP UV Disinfeclica 421110 So 5443,456 so $D s0 SO $0 $0 $0 $0 $0 $0 So WWTP UV Disinfection -Projected Bond $4,180,000 $0 $0 $4,434,562 $0 s0 $0 $0 So $o so $0 $0 $0 WWTP Permit Improvements- Bond Proceed: 423900 $5,951,235 $173.650 $0 so $o $0 $0 $0 $0 s4 s0 so so Wastewater TreatmentRehabll4ation $0 so $0 $0 $o so $0 S1,000,000 $2,000,000 $2,000,000 5200,090 $200.000 Bond Issuance Costs 423998 $0 so $170,876 $o so s0 $0 S0 5102.954 SO so so S102,391 Subtotal - Wastewater Treatment Plant $6,524,111 51,462,965 34.680.438 5250,000 &300,000 5317,531 $215,927 $1,814,661 $16,809,561 $2,000,000 $2,000,000 $1,860,946 514,560.000 28 Marshall Landfill _ Marshall Land(ll $0 $0 5100,000 s0 So so $0 $0 $0 SD s0 $0 $0 Subtotal • Marshall Landfill L -1 SO s0 5100,000 so so so $0 $0 $0 $0 $0 so so Btosolids Recycling Valmont Butte 421675 5232,049 _ 5404,940 $0 _ $0 s0 SO _ SO $0 $0 $0 $0 _ $0 $0 0 s0 $0 _ $0 SO _ $o 35 Blosolids Handling & Dewaterin9 421670 $698,495 $106,270 _ $0 s0 $0 . 50 _ $150,000 S _ WWTP Biosolids Digester 421671 SO S963,074 $0 so 3'I SO $0 s0 $0 $0 so so so WWTPBlosolidsDigester - BondProeeeds 424xxx $7,370,000 $0 $0 s0 $0 SO $0 $0 $0 SO $0 $0 $0 WWTP Cogeneration 421329 SO S20OMO SO SO s0 re 921-1 $0 $0 $0_ $0 $o $0 7 x;15 WWTP DigesterComptex 421007 _ $0 $50,000 $D $0 50 $0 $0 _ $0 $0 $0 _ $0 $0 $0 geserCleaning 421360 $0 $0 5'•` ,!pan $0 ~.t SO SO S0 $o$0 $0 50 WWTPDi Subtotal - Bicsolids Recycling $980,544 81,774.284. 54.150.004 SD s0 $168,8_26 $150,000 $0. $0. $190,015 So $0 $207,635 42 Wastewater System Monitoring and Metering _ Yards Master Plan implementation 421039 $238,785 _ $121,215 _ 5D $0 s0 50 50 _ $0 _ SO $o $0 50 _ $0 Automated Meter Reading 421548 $4 SO s0 $0 $0 $0 $0 $0 $0 $0 so s0 $0 Utility Billing Computer System Replacement 421453 _ $10,920 S69.284 So $0 s0 so so s0 $0 $0 so $0 SD 47 Subtotal - Monitoring and Metering $249,705 $190,499 SO $0 s0 s0 $0 $0 50 so so 50 so 77 Collection and Conveyance System Rehabilitation Collection System Monltomng 421450 _ S0 s0 s0 s0 s0 SO $0 $0 570.01;a s0 $0 s0 Sanitary Sewer Rnhebilitallon 427002 5914,904 $803,946 $cS a 5) ; 74 y; i;'r :+'910 dl 58`2107 5 1 45a :;y' 117 ~7 sk.~.: 52 San tary Sewer Manhole Rehabilitation $109,273 $112,551 _$115,927 $119,405 $122,987 $126,677 S130,477 5134.392 5130,423 $142,576 421454 '5164.248 $1 ,004 510$490 6,r6275 5562,754 $0 s4 s0 $O $0 SO $O S0 IBM Pump Elation 421521 $500,000 $0 $0 s0 j 'J P',: I^'anProiecl ti7.lznu;i x202.025 i>> Creai Y 1A Master Plan P 7171 1(13.006' $323346 51,332187 77 Loose Creek 3Master PlanProact 8 2000 J - ' Goose Creel 5 MaslerPlan Project SZ 559.000 $648,333 S'1,335.566 $1,375,833 BoafJer~rePkI1lasterPlanProeel $1653,001 c~2BouldtrGreek3MaslerPlanProiecl ° $1g39.000'I T,,:[2BoulderCreek4MasterPlanProo)ec_t 51i.756.ooJ1 , T,cr2 Goose Greek 4 Master Pton Project 1 $3.928,0103 7„r2GunbarrelIMasterPlanProjeol $1,116,000 7gr2Cunbarref2r;!usLrPfo5 Prninct $939,090 _ _ - . n a r r - 1 1, r rcie_ct $733,400 65 Subtotal - Sewer System Rehabilitation $1,079,152 $903,946 $636,540 $764,957 S1,238,060 $695,564 $716,431 5737,924 $1,400,395 $2,168,430 S2,505,329 $2,365,656 $1,691,523 Wastewater System Expansion Annexation Related WW Svslem Expansion 421436 $0 $717,893 $0 $0 $9 $0 SD . SO s0 so s0 s0 so Subtotal -Wastewater System Expansion s0 _ 5717,693 s0 - 50 . 50 50 SO . $0 . $0 . $0 $0 $0 50 TOTAL CAPITAL USES OF FUNDS $6,833,512 S5,049.587 $9.566.978_ $1,014,957 $1,538,060. $1,181,921 $1,082,359 $2,548,585 $18,217,956_ $4,358,445 $4,505,329 $4,226,602-$16459,1$8 520 2,862,277 2,825,340 09 oriq bud 523 5,951.235 283,006 encce 75- 8,833,512 1,767.591 capeo - 0 173.1350 pond 5 _ E - $5,049,587 08 rev bud SURPLUSI(DEFICIT) vs. ALL RESERVES 510,899,636 S 6,609,722 $ 5,586,784 $ 4,498,861 S 9,092,587 S 2,366,372 5 2,243,959 S 1,238,191 -516,536,730 -$20,342,940,•$24,00 5,980 •$26,136,487.-$39,104,639 A 0 P 0 R S T U V W X Y Z AA 1 ACTION PLAN 2 Assumed Inflation Rate 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 PROJECT NAME PROJECTED pf I PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PR 1 PROJECTED PROJECTED PROJECTED TOTAL Wastewater Treatment WWTP Pumps so s0 s0 $0 so so $0 So - s0 s0 ____so $0 $450,000 _TT LVWTP Permit Improvements si.swI53 $0 $0 s0 $0 S155.797 $0 SO $o $0 5180,611 SO $2,931,223 WWTP Permit Improvements - Projected Boni $0 $14,257,609 $0 50 50 SO SO $0 $0 $0 $0 $14,257,609 31 WWTP Laboratory $0 s0 $0 s0 $0 $0 $o s0 $0 s0 $0 $0 $0 Lower Boulder Creak Enhancement SO_ $0 $0 $0 $0 50 $0 $0 $0 $0 $0 SO $0 WWTPHeadworks $0 so s0 SO SO $0 SO SO 54' to $0 s0 $1.860,661 16 WWTP Headwoft - Projected Bond $0 so $0 $0 $o $0 SO $0 $0 $0 $0 s0 $15,606,607 WWTP Instrumentation7Control _ $0 5o so $0 5o 50 s0 SO 50 $0 _ $0 $0 $175,000 _TT WWTP Electrkal s0 so $0 so s0 s0 50 $0 $0 s4 $D SO 5400,000 WWTP Activated Sludge 5100.,"3 $0 $0 SO 50 50 SIOt,•!87 50 SO $0 $0 $0 $276,691 WWTP Primary Clarifiers $0 SO so $0 s0 s0 SO so $4 $0 $0 s0 $300,000 WWTP Secondary Clarifiers $0 So so s0 so so so $0 $0 $0 s0 s0 5200,000 WWTP UVD,sinfeclion $0 $0 so so 5o s0 SO s0 SO to $0 50 $443,456 WWTP UV Disinfection • Projected Bond s0 SO $0 $0 $O $0 $0 $0 50 s0 50 $0 54,434,562 'IT WWTPPermtImprovements - BondProteed: SO So so SO SO SO $0 $0 $O $0 $0 $0 $6,124,885 Wastewater Treatment Rehabilitation $200,000 $200000 $500,00D $1.000,000 5200,000 $200,000 $11,000,0DO $200000 5200,000 $2,000,000 $2.000,000 S200.000 $12,900.000 Bond Issuance Costs 50 $102.391 5D SO $0 SO $0 $0 $0 $0 $0 $376,221 Subtotal - Wastewater Treatment Plant 51,860,946 $14,560,000 $500,000 $1,000,000 $200.000 $355,797 $1,108,367 $200,000 5200,000 52,000,000 52,180,611 $200,000 $60,736.915 Marshall Landfill Marshall Landfill so SO $D $0 50 $0 $0 50 SO' $0 SO SO 5100,000 77 Subtotal - MarshallLandfll $0 SO SD 50 50 SO So 50 50 50 50 $0 $100,000 Biosolids Recycling _ 34 Valmont Butte _ _$0 $0 SD $0 $0 $0 $0 50 54 50 SO $0 5716,989 Biosolids Handling 8 Dewatenng 50 SO $D $D _ $0 s0 SO SO _ SO' 50 $0 _ SO 5954,765 WWTP Biosolids Digester 50 $0 5o 5D 50 $0 $0 $0 _0- !0 $0 $0 $983,074 WWTP Biosolids Digester- Bond Proceeds SO $o $0 $D SD $0 $0 $0 $0 $0 $0 $0 54,000,000 WWTP Cogeneration s0 50 SD SD s0 $o $0 so So.-- $0 $831,826 WWTP Digester Complex $0 SO $0 $0 $0 $0 $0 $0 SO SO SO SO _ $50,000 WWTP Digester clearing $o SO SO s6 SO 23"sG,L,5 5o $0 $0 $0 $0 $0 $570,711 Subtotal- Blosolids Recycling s0 $207,635 $0 50 SO S233,695 5o $0 $255,365 $0 50 SO $6,110,365 Wastewater System Monitoring and Metering Yards Master Plan Implementation $o s0 SO $o $0 SD s0 $0 $0 50 $o so 5360,000 Automated Meter Reading s0 50 _ SO SO 50 SD $0 s0 5o $o $0 $0 $0 Ulitity Billing Computer System Replacemem _ $o s0 $0 $0 so $0 So $0 SO So s0 So 580,204 Subtotal - Monitoring andMetedng s0 s0 s0 50 $0 s0 SO s0 $D $0 so $0 $440,204 48 Collection and Conveyance System Re_ha_billia_ I Collection System Monitoring $0 $0 $71,288 $0 $0 _ $0 50 582.Cl $0 $1] $0 $0 $255,975 Sanitary Sewer Rehabilitation $,.92.11 $71288n $i1. ?Ci 575 , 9 r~e,~ X802.353 592erX4 SA51'21' E8 5903.05; 5ru 147 5056 a52 516.930292 Sanitary Sewer Manhole Rehabilitation $136,423 $142,576 $146,853 5151.259 $.155.797 $166.471 $165,265 $170,243 $175,351 $18.0.611 $186,029 _$1.91,610 $_3,306,536 IBM Pump Station $0 50 _ 50 . 50 $0 $0 s0 $0 s0 50 $0 50 5619,030 .n, , r! ter Pi,ii F~~%,dCl $242.929 S"313.175@ - - - - - - •r I s Crc!, 4 1 1P FAa56;r Plan PT itCt 1.332.187 - - erlGooseCreek3Mest~rG~nProtect $707833 S707:3~3 1 Goose Creek 5 Master Plan Protect 53.3`9 5?2 (2 Boulder Creek 1 Master Piaaecl SO ilor 2 Bouklar Creek 3 Master Plan Pro $0 T_or 2 Boulder Creek 4 Master Plan Proitict _ _ SO -Ter 2 Goose Creek d Master Plan Proact $ l Ter 2 Gunbonel 1 Masler Plan Prpject _ 50 63 Ter 2 Gunbarret 2 flastcr Plan nroiect So Tmr 2 South 8(:,; : ;r. I klaslcr ~'a^ Pric, _ _ $0 Subtotal • Sewer System Rehabilitation $2.365,656 $1,691,523 $1,660,242 $907,554 5)34,780 $962,824 $991,709 $1,104,102 $1,052,104 $1,083,667 51,116,177 $1,149,662 $27,874,726 Wastewater System Expansion 68 AnnexalctiRolatcdWWSystem Expansion $0 s0 50 SO SO $D $0 SO s0 s0 $0 $0 $717,893 Subtotal -Wastewater System Expansion s0 s0 s0 s0 s0 $4 so SO so s0 $0 $0 $717,893 TOTAL CAPITAL USES OF FUNDS $4,226,602 $16,459,158 $2,160,242 $1,907,554 $1,134,780 $1,552,315 $2,100.075 _ $1,304,102 51,507,469 53,083,667 $3,296,788 51,349,662 , 597,980,103 -77 77 -77 SURPLU51(DEFICIT)vs,ALLRESERVES .-$.26,136,487,.539,104,639 -$38,825379.•$37,879,804.435,775,274,•533,878,238.-531,718,581 425,179,353 -$18,441,555 .$12,877,341 4 7,124,940.$ 1,749,106