Loading...
HomeMy WebLinkAbout6 - Update on watermain break data analysis CITY OF BOULDER WATER RESOURCES ADVISORY BOARD AGENDA ITEM MEETING DATE: February 23, 2009 AGENDA TITLE: Update on Water Pipe Replacement Analysis PRESENTERS: Nick Worley, Temporary Civil Engineer Bob Harberg, Utilities Planning and Project Management Coordinator EXECUTIVE SUMMARY: Staff has recently completed a water pipe replacement analysis that considers an extensive GIS based inventory of the water distribution system pipes as well as break records from the previous 20 years. The analysis is documented in the attached Technical Memorandum regarding Water Main Replacement Analysis and CIP Budget Estimate. STAFF RECOMMENDATION: The technical memo provides recommendations for funding of the future water main replacement program. BOARD AND COMMISSION FEEDBACK: None to date PUBLIC FEEDBACK: None to date ANALYSIS: Please refer the attached technical memo. MATRIX OF OPTIONS: Please refer the attached technical memo. ATTACHMENTS: Technical Memorandum regarding Water Main Replacement Analysis and CIP Budget Estimate AGENDA ITEM # 6 PAGE 1 City of Boulder Technical Memorandum To: Bob Harberg From: Nick Worley CC: Utilities Project Management Staff Date: 2-9-09 RE: Water main replacement analysis and CIP budget estimate Introduction The water distribution infrastructure in cities around the US has begun to come to the forefront of municipality's focus as the piping begins to fail more frequently while costs of repair continue to increase. Dependable water is such a critical part of society and is necessary for the wellbeing of the public. The city of Boulder has over 400 miles of water distribution system piping much of which was installed during the 1950's through the 1970'x. The majority of this aging pipe is still functioning properly although some parts of the city are experiencing more frequent breaks1. The purposes of this technical memorandum are to: 1. evaluate and summarize available data, 2. create a model that predicts future water main break frequency, 3, evaluate new model, and 4. create a capital improvement program budget for water main rehabilitation and replacement -1- Pipe Replacement Technical Memo Table of Contents 1 Literature Search 3 2 Water Distribution System Characteristics 5 2.1 Data Sources 5 2.2 Data Summary 5 3 Water Distribution System Analysis History .........................................................................14 4 Current Water Distribution System Analysis ........................................................................16 5 Model Results .......................................................................................................................16 5.1 Classification 1-one break allowed before replacement ............................................17 5.2 Classification 2-two breaks allowed before replacement ...........................:...............19 5.3 Classification 3-Three breaks allowed before replacement 20 5.4 Classification 4- Four breaks allowed before replacement 21 5.5 Summary of Classifications 22 6 Plan Budget ...........................................................................................................................23 7 Recommendation ..................................................................................................................25 -2- Pipe Replacement Technical Memo 1 Literature Search Over the past few decades more and more research has been conducted on the deterioration of our water distribution system infrastructure. The need for replacement has caused companies and researchers to begin to develop computer models that can help with the decision making process of when and which pipes need to be replaced. These models can be used to either help with the decision making process of how much money should be allocated for future pipe rehabilitation or to assist in the selection process of which pipes to replace. The purpose of this memo is to summarize an innovative method that can be used to help with the budgetary planning process of future pipe replacement. The methods that have been used by others in the pipe rehabilitation selection process can be categorized into the followingz: • Deterioration point assignment methods • Break even analysis • Failure probability and regression methods • Mechanistic methods The first method is the point system that the City of Boulder currently uses for the prioritization process. This method determines which pipes have the highest priority for replacement depending on their characteristics as well as environment conditions. The method gives a certain quantity of points for each characteristic of a segment of pipe. Categories that are typically used are pipe age, pipe material, pipe diameter, soil conditions, water pressure, ambient temperature, etc. The break even analysis is a cost based method that compares repair costs and replacement ~ costs. This method must have a predictive model that can generate a quantity of future breaks/repairs for comparison with the replacement cost. Pipe replacement is necessary when the cost for pipe repair reaches an unacceptable level in comparison with the present worth of the pipe. The failure probability and regression method is the method that uses statistical functions to predict future failures and is the method discussed in this technical memo. This method uses past break data along with the distribution system pipe data to determine a failure curve. The failure curve can be used to find the cost of pipe replacement necessary to keep up with pipe failures. The disadvantage of this method is that it only provides a quantity of pipes that will fail for any given time period and does not predict which ones. A separate analysis must be used in conjunction with this method to assist in the selection of pipes to be replaced. Mechanistic methods are those that gather data and determine failure rate by observing physical specimens that have been subjected to a similar set of conditions. An example of this experiment would be burying a number of sticks of pipe and monitoring the corrosion over time. A failure rate can be then determined based on how the specimens fail. These methods use parameters such as measured corrosion pit depth, soil type, age of pipe, temperature induced stresses, frost load, and other failure processes using underlying physical principlesz. -3- Pipe Replacement Technical Memo Other local municipalities are beginning to analyze their distribution systems and take action to replace deteriorating pipe. The city of Westminster in Colorado is one of the nearby cities that have begun to take action. In 2005 they contracted URS corporation to do a comprehensive study on their system and produce some recommendations for future action3. Much of the metallic pipe in their system is corroding and failing at a faster rate and they have had to become more aggressive in pipe replacement. URS used the city of Westminster GIS data as well as their pipe break records to create a new system improvement plan. The final recommendations made to the city were to increase pipe replacement as the rate of failure is expected to increase over the next few years. Denver Water also is beginning to analyze their water distribution system more intensely. They have had an aggressive rehabilitation plan in action for years that has lined many of their corroding cast iron pipes with cement mortar. Recently they have begun to work with some professors at the University of Texas to create a predictive break model and a new prioritization process that will take into account more criteria than their current point system prioritization process. Corrosion and tuberculation has been the dominant problem in the ®enver water distribution system. They have begun to test soil resistance at every pipe segment that breaks and document it as one of the criteria in the point system analysis. In conjunction with soil resistance, they have begun to incorporate their GIS data into the MWH Infowater modeling program in order to produce pressure and flow output for use in the point system pipe selection method.ls From the literature search, it is apparent that the prediction of future pipe failures is a best estimate only due to hack of data. Record keeping in city public works has not been sufficient over the past 50 years to accurately determine future break patterns. There are many unknown pier_es of data that must be accounted Fr~r by best guess assumptions which brings in uncertainty. Many of the documented pipe break studies have incorporated into the final recommendation several scenarios of how the system wi11 potentially fail as time goes on, The final recommendation comes down to a choice of which scenario is the most likely the one that represents the system most nearly. As more data becomes available as time goes on, the scenarios can be reevaluated in comparison with the system and the budgetary decisions could change. Although there is uncertainty in all the documented analysis, the consensus among municipalities, researchers, and consultants is that more money must be allocated for pipe replacement in the near future. Otherwise the clean, dependable water we now enjoy will be compromised in the future. -4- Pipe Replacement Technical Memo 2 Water Distribution System Characteristics The City of Boulder water distribution system is comprised of many different sizes and materials of pipe totaling over 400 miles in length. The majority of the system was installed during the 1950's, 1960's, and the 1970's along with the sanitary sewer and storm sewer systems. Metal pipes such as Cast Iron Pipe (CIP) and Ductile Iron Pipe (DIP) were the primary materials of choice during installation and many pipes have since failed due to corrosion, joint failure, pressure, and settlement. Other materials such as ACP and PVC were also used starting in the 1970's and 1980's respectively. The scope of this memo is to evaluate the distribution pipes 16 inch in diameter and smaller. Pipes in the system larger than 16 inch will be considered transmission lines and will be excluded from the analysis. The reason for this narrowed scope is because 99% of the breaks occur on pipes 16 inr_h and smaller. The transmission main system accounts for 8% of the total length of installed pipe and has a very low break rate in comparison. These pipes may be considered for rehabilitation or replacement as well but due to the more reliable nature, they have been excluded from the analysis. 2.1 Data Sources The data used in the analysis summarized in this memo was taken from the City of Boulder _ GIS information system database and the utilities maintenance pipe break database. The GIS database is a graphical summary of all the eity's records of water main as-builts and provides a complete plan view of the underground water main infrastructure. It contains information .y about the pipe characteristics and date of installation as well as whether or not the pipe is private or owned by the city. For the purpose of this Technical Memo, only the pipes owned by the city will be evaluated. The utilities maintenance pipe break database was initiated in the early 1990's and contains all the information about the individual pipe breaks that have occurred since that time. Both databases have been significantly filtered for completeness and correctness providing a strong basis for the accuracy of the analysis. 2.~ Data Summary The raw data used in the analysis will be briefly summarized in this section for a complete picture of the distribution system characteristics. This summary of data only includes the pipes 16 inch diameter and less as defined by the scope of the TM. As shown in the following tables, the decade with the most installed pipe was in the 1970's. The piping previous to the 1970's was almost entirely CIP which has been the pipe material with the most breaks. The construction industry began to use DIP in the 1970's and PVC in the 1980's. - -5- Pipe Replacement Technical Memo Table 1 Summary of pipe installed" 1950's 1960's 1970's 1980's 1990's 2000's Total Total Pipes Installed 1245 1412 2205 545 886 580 6873 Total Length of Pipes (mile) 85 86 124 35 52 29 412 Table 2 Pipe material distributions Pipe Length % of. _ Material (mile) Total ACP 1% 4% Cl P 162 40% DIP 124 30% PCCP 2 0.4°l0 PVC 96 23% ST 8 .2% Table 3 Pipe diameter distributions Pipe Length % of _ Diameter (mile) Total- 4 13 3% 6 98 24% 8 2f?3 50% 12 65 16%, 14 4 1 16 26 6% -6- Pipe Replacement Technical Memo Water Pressure Distribution 60 50 t 40 - ~ i ~ i s rn 30 ' J 20 _ ~ _~}_t _ m 0 I. - ^o ~O ~O ,~O ~O ^,~O ^r~j0 ~4j0 ^.~O ^~O Pressure (psi) Figure 1 Water pressure distribution6 The above tables and figure were taken from the GIS database. The following tables and figures were compiled from the maintenance pipe break database. Total l3reaks per Year 140 120 - 100 - Y ~0 - f0 ~ - - - m 60 40 - - - - - 20 - - - 0 0~ 0~ X01 .~O 'l0 1°~ ~~L ~5 °~R 01 ~o ~'3 00 Year Figure 2 Total breaks per yeara Figure 2 shows the total breaks per year that have been recorded. It is important to note that most pipes will break multiple times during their life before being replaced. As mentioned before, the utilities maintenance database was initiated in 1990 and all the pipe breaks previous were found in annual reports. The data showing breaks per year from 1950 until 1960 and 1962 to 1981 is currently unknown. -7- Pipe Replacement Technical Memo Pipes with First Break so 40 ,'41 N 'I f ~ x ~ 30 - - - fi - - ~ n ' m - D L. P - `'r W 6~ ~.a 1y~\ 9.~ 9: ~~1' g4Q' ic"~h 94J °~*g ,SyS~ ~b1~.dS~,dyS~ .dyf~ ,y0l, .~~PP•JO~ Figure ~ Pipes with first break Figure 3 shows the number of pipes that have their first break each year. Many of the annual breaks occur on pipes as repeat breaks. No trend can be seen in either the total annual breaks nor the annual first time breaks. Over the years city staff have discussed the recorded data and come up with different ideas as to what data is representative of the system and what data is not. Some staff have noted during the years that a significant number of breaks have occurred during a problem "event" when the distribution system was stressed by external conditions. An example of this is when maintenance crews open and close valve incorrectly causing a spike in pressure. !n 2U02, work was being done oi~ the Gunbarrel tank when valves were incorrectly operated. A spike in pressure immediately caused 13 breaks in the surrounding distribution system. These breaks could be looked at in two different ways: 1. The pipe that failed was the weakest point in the system and would be the first to eventually break 2. These pipes broke prematurely due to a mistake by the maintenance crew and therefore do not represent true pipe failures These arguments must be kept in mind when viewing the data. The years with particularly large numbers of breaks usually had a number of events that caused an abnormal number of pipe failures. In the following analysis all pipe breaks have been used to model the system as it functions with the seldom operational mistakes that cause event failures. The following figures summarize the entire break data as recorded. Table 4 Recorded pipe break totals6 Total % of Break type Breaks Total Corrosion 292 29% Pressure 116 12% Settlement 534 53% Other 59 6% -8- Pipe Replacement Technical Memo Breaks by Type 50 45 ' 40 35 - ` -Corrosion Y 30 - Pressure ~ 25 -Settlement ~ 20 - 15 f j -Other 10 1990 1995 2000 2005 Year , - - - rs, Figure 4 Recorded pipe breaks6 As shown in the above figure, settlement breaks have dominated in total annual breaks for the past 18 years. A possible theory for this is the use of native soil for pipe bedding causing pipe movement during soil expansion and contraction. Other breaks include joint failure, water system events causing failure, or other abnormal reasons. Weighted Breaks by Material 0.60 ~ ~ 0.50 ~ 0.40 ' - ~ -ACP' L n, 0.30 CtP ~ y - DIP ~ 0.20 -PVC m pp 0.10 0.00 ~ - - - - `1 1990 1995 2000 2005 Year Figure 5 Pipe breaks classified by material6 -9- Pipe Replacement Technical Memo Weighted Breaks by Diameter 0.7 0.6 d 0.5 4 inch ~ 0 4 6 inch e. - 8 inch 0.3 12 inch m 0.2 -16 inch F _ 0.1 - - _ _ 0 1990 1995 2000 2005 L - Year Figure 5 Pipe breaks classified by diameter6 Figure 5 above shows a general relationship that CIP is typically the pipe that has the most annual breaks where PVC being the newest pipe has the least annual breaks. An explanation for the spike in ACP breaks/mile in 2002 was the above mentioned Gunbarrel tank event that caused many breaks around Gunbarrel. ACP was the main pipe material used in the water distribution system in Gunbarrel in the 1970's. Because of the relatively high number of breaks due to the event, the ACP shows a spike in breaks/mile. Figure 6 shows a slight correlation in the pipe diameter where the srnaller pipes tend to have more annual breaks, Weighted Breaks vs Pressure 4.5 4 3.5 - ~ 3 2.5 2 N 1.5 m 1 a~ m 0.5 - - - 0- r---- 0 50 100 150 200 Pressure (psi) Figure 7 Relationship between water pressure and breaks6 Figure 7 shows little correlation between the water pressure and number of pipe breaks per mile of pipe. Intuitively the higher pressure would create more stress on the pipe and more frequent breaks could be expected. This however is not strongly supported by the data. -10- Pipe Replacement Technical Memo The pipe break records from the maintenance department have been integrated into a GIS spatial mapping file so the different breaks can be viewed spatially. This is helpful to locate areas where similar type breaks have happened repeatedly and to understand how pipe replacement can most efficiently be used. The following three figures show the locations of the recorded pipe breaks by type. ~ ~ C f- - I O _ 1,'~~~ I ~II a - J ~ 1J N WE S Legend • Corrosion Breaks ~ Figure 8 Corrosion break locations' -11- Pipe Replacement Technical Memo L~ r- . - ~ - L ' ~ II ~C • • ~ r N-CJ..1~ WE S Legend ' • Pressure Breaks. 'm] Figure 9 Pressure break locations8 -12- Pipe Replacement Technical Memo L r h T - • .,d. i f t r~ i -T ii i lL I ~i l s Legend • Settlement Breaks ~ Figure 10 Settlement break locations9 -13- Pipe Replacement Technical Memo 3 Water Distribution System Analysis History The City of Boulder utilities department began a more intense analysis of the water distribution system in 2002 when Integra consulting was hired to create a new system for pipe replacement selection. This initial report has been evaluated and critiqued by staff as well as other consultants in order to produce additional strategies and methods for pipe cost analysis and selection for replacement. The report that Integra produced summarized a point system that the City of Boulder staff could use to prioritize which pipes are most in need of replacement. Each pipe segment would receive points based on its age, material, size, soil type, and relative location in the city. The points would be summed up for each pipe and the one with the most points has the highest priority for replacement. This point system and methodology was integrated into the water main and main breaks databases and has been used for the prioritization of pipe replacement since 2002. In 2007, the City of Boulder decided to take this analysis a step further and create a prediction model using Integra's methodology. The model utilized a statistical function called the Weibull function which was originally created to model the failure rate of a given population. The water main pipe segments had previously been assigned point values by the point system methodology and the points were used to symbolize failure. Segments with higher point values were assumed to have more chance of failure and thus the data was used to create a Weibull curve. A cut off point value was assumed which signified the point value above which the pipe segments have failed. This cut off point value was chosen based on the estimated total failure of the water main distribution system. The results of this analysis produced pipe replacerrient costs ranging from $6 million to $10 million per year. In April of 2008, the City of Boulder hired HDR to critique the original Integra analysis and the Weibull function results. Their comments on the Integra analysis dealt mostly with the lack of methodic determination of how many points each pipe characteristic should receive, They also took the analysis a step further and suggested that the point system should be used on a per foot basis in order to correctly evaluate break potential between long and short pipe lengths. Little was mentioned concerning the city staff produced technical memo on the Weibull function analysis. HDR continued the analysis of the Boulder water distribution system by trying to find a correlation between pipe breaks and other pipe characteristics. They evaluated several scenarios by grouping characteristics together such as Breaks per Mile vs. Diameter, Breaks per Mile vs. Age-Material groups, and Breaks per Mile vs. Age-Material-Sail groups. A correlation was found when the Age-Material-Soil groups were plotted with the Breaks per Mile and they decided to use this correlation to create a model to show which pipes should be replaced first. The model they created grouped pipes into similar groups and the assumption was made that they will all fail at a similar time relative to other groups. A cut off value was chosen which they called a service level that would determine which "groups" of pipe should be replaced based on the acceptable breaks per year. The model was used to evaluate three different service levels based on the current level of service the city provides. The results of the model produced necessary pipe replacement costs ranging from $4.8 million to $10.6 million per year. -14- Pipe Replacement Technical Memo The prediction model presented by HDR wasn't considered an accurate representation of the distribution system because of the limited data available to use. City staff began to look at additional methods of failure prediction and pipe replacement selection. The critical break area method utilized the GIS spatial mapping to locate hot spot areas where multiple breaks have occurred. An assumption was made that all pipe within the hot spot areas should be priority for replacement within the next 20 years. The resulting cost of replacement would be $4.7 million per year. City staff also looked for other correlations in Breaks vs. operating pipe pressure. The city was able to finalize and run the city water distribution system model in MWH's InfoWater program in 2008 which provided additional data for analysis. Little correlation was found between breaks and main pressure so the city continued to look at other prediction methods. The pursuit of a more correct analysis continued with the use of the Weibull function again in an analysis that used several scenarios to test the sensitivity of the Weibull function. The different scenarios included and excluded different pipe breaks based on different conditions and a prediction model and budgetary CIP was created for each. The analysis produced a wide range of results that were not entirely useful according to the city's desires. The idea of using different scenarios in this analysis is what eventually led to the analysis described in the following section which wa~,chosen as a more system representative analysis. I. I -15- Pipe Replacement Technical Memo 4 Current Water Distribution System Analysis The above mentioned analyses produced relatively conservative values of annual pipe replacement cost that are not possible for the city budget to meet. All the previous models made the assumption that one break on a pipe segment should be considered failure. This assumption has been questioned due to the fact that many of the pipe segments in the city that have broken once haven't broken again since. Many of these breaks were due to distribution system events or settlement in the surrounding soil and don't necessarily reflect a failing pipe. The definition of what constitutes a failure has now been evaluated for a more realistic and less conservative approach to the analysis. The analysis of the water distribution system has continued onward by changing the definition of pipe failure. In this new model, the Weibull function will be used to specifically model the number of first, second, third, and fourth breaks that any given pipe will have. Four separate Weibull functions have been created to model ear_h break classification. These Weibull functions will be calibrated to actual data and used to predict the number of expected breaks in the future. A decision will have to be made as to how many annual breaks will be considered acceptable and from this one of the break classifications or prediction models will be chosen as the desired model to follow. Each prediction model will have different financial implications as less breaks allowed means more replacement casts. The break classifications can be looked at as different paths that can be taken and a predicted number of future breaks will be calculated for each path. 'T'he choice of the best path will d2pend on how many breaks per year are considered acceptable. There will be a balance that must be met between the amount of annual budget spent on break repairs and pipe replacement. The number of breaks that any given pipe is allowed to have will determine how long into the future the replacement is delayed. 5 Model Results The results of the model have been broken down by each break "classification" which correspond to one, two, three, or four breaks that are allowed on a pipe before replacement is necessary. Each classification has a specific curve generated from the Weibull function and are shown on a common graph below. -16- Pipe Replacement Technical Memo Pipe Failure vs Time 12o°i° 100% - _ ~ 80% -First Break i ur i N 60% J I Second Break a a ---Third Break 40% - -Fourth Break 20% - 0% 0 50 1D0 150 200 250 300 350 Pipe Age (years) Figure 11 Pipe failure curveslo 5.1 Classification 1- one break allowed before replacement Typically one break on a pipe is considered failure for most analyses. In this analysis "one break equals failure" is considered the baseline model and most conservative. Many pipes that break once will not break again for many years and the repair can be justified to extend the use of the pipe until further breaks begin to occur. In this analysis all recorded pipe breaks were used and an unrecorded failure factor was used to extrapolate breaks that occurred before the recording system was started. The breaks and total numbers of pipe installed were broken down by decade and the percentage of failed pipes was calculated for use in the Weibull function. Table 5 below shows the data used for the first classification. Table 5 Data used for first break Weibull function° Summary of Pipes and Failures 1950's 1960's 1970's 1980's 1990's 2000's Total Total Pipes Installed 1325 1462 2242 548 886 580 7043 Recorded Pipe Failures 209 217 154 8 17 11 616 Unrecorded Failure Factor 1.48 1.27 1.13 1.03 1 1 Total Pipe Failures 310 278 175 9 17 11 800 Percentage of Failed Pipes 23.4% 19.0% 7.8% 1.6% 1.9% 1.9% 11.4% The Weibull function used the percentage of failed pipes to create the curve and the curve was then used to calculate the number of annual breaks that have occurred and will occur in the future. The total number of breaks recorded was used to constrain the Weibull function and produce a curve that represented the current system. The unrecorded failure factor was then found by iteration. -17- Pipe Replacement Technical Memo The following table shows the comparison of the results of the extrapolated actual data and the predicted data as given by the model. The Weibull curve was fit mainly to the older pipe failures as they had more data points and provide stronger statistical accuracy. The newer pipe showed larger variance from the model. Table 6 Actual and modeled first break comparisonlo Pipe installed Pipe installed Pipe installed Pipe installed Pipe installed in 1950's in 1960's in 1970's in 1980's in 1990's Extrapolated Actual First 310 278 175 9 17 Time Breaks Model Predicted First 343 223 171 16 7 Time Breaks Model Error 11% -20% -2% 78% -59% Pipe Failure vs Time 120% -a 1 p00% c0 80% lJ.. a 40% 20% - - - - 0% ~ ---T- - 0 100 200 300 -Weibull Function Pipe Age (years) • Actual Data Figure 12 Weibull fit for first break The Weibull function created a model that closely fit the actual data for first time breaks. The city however does not replace pipe based on a first time break but typically waits until there are more breaks to justify the replacement. For this reason more break classifir_ations were created using filtered actual break data. -18- Pipe Replacement Technical Memo 5.2 Classification 2- two breaks allowed before replacement As more breaks are allowed to occur before replacement, less pipe replacement is necessary in the near future but more will be required in the medium term. In the second classification the Weibull function will be used to model the frequency of future second breaks. The model is based on the recorded data showing pipes with two or more breaks. This classification is less conservative than the first classification because many of the one time breaks were filtered out and the result shows a system with a Power percentage of failed pipes. Table 7 Data used for second break Weibull functionll _ Summary of Pipes and Failures 1950's 1960's 1970's 1980's 1990's 2000's Total Total Pipes Installed 1325 1462 2242 548 886 580 7043 Recorded Pipe Failures 75 84 43 1 3 2 208 Unrecorded Failure Factor 1.37 1.23 1.11 1.02 1 1 Total Pipe Failures 103 104 48 2 3 2 262 Percentage of Failed Pipes 7.8% 7.1% 2.1% 0.4% 0.3% 0.3% 3.7% Table 8 Actual and modeled second time break comparisonli Pipe installed Pipe installed Pipe installed Pipe installed Pipe installed in 1950's in 1960's in 1970's in 1980's in 1990's Extrapolated Actual Second 103 104 48 2 3 Time Breaks Model Predicted 123 73 51 4 2 Second Time Breaks Model Error 19% -30% 6% 100% -33% -19- Pipe Replacement Technical Memo Pipe Failure vs Time 120% 100% 'a m 80% - v_ ~ 60% - a~ a 40% - 0 20% - w 0 50 100 150 200 250 -weibuil Function Pipe Age (years) ¦ Actual Data Figure 13 Weibull fit for second break 5.3 Classification 3- Three breaks allowed before replacement The third classification is similar to two except more pipes are filtered out of the analysis as only pipes with three or more oreaks are used. Table 9 Oata used for third break Weibull functionlZ Summary of Pipes and Failures 1950'5 1960'5 197Q's 1980'5 1990'5 2000'5 Total Total Pipes Installed 1325 1462 2242 548 886 580 7043 Recorded Pipe Failures 36 40 23 1 0 0 100 Unrecorded Failure Factor 1:44 :1.28 1:14 1.03 1 1 Total Pipe Failures 52 52 27 2 0 0 133 Percentage of Failed Pipes 3.9% 3.6% 1.2% 0.4% 0.0% 0.0% 1.9 % Table 10 Actual and modeled third time break comparison1z Pipe installed Pipe installed Pipe installed Pipe installed Pipe installed in 1950'5 in 1960'5 in 1970'5 in 1980'5 in 1990'5 Extrapolated - - --i- Actual Third 52 52 27 l 0 Time Breaks Model Predicted Third 68 43 33 3 1 Time Breaks Model Error 31% -17% 22% 50% -20- Pipe Replacement Technical Memo Pipe Failure vs Time 100% i ~ 80% - ~ 60% I y 40% a 0 20% - - - - 0 50 100 150 200 250 WeibullFunction~ Pipe Age (years) ~ ¦ Actual Data ~ Figure 14 Weibull fit for third break 5.4 Classification 4- Four breaks allowed before replacement The fourth classification is similar to the second and third where the number of failed pipes has been filtered further. Only pipes with four breaks or more will be considered a failure resulting in less total failures than the previous classifications. Table 11 Data used for fourth break Weibull functionls Summary of Pipes and Failures 1950's 1960's 1970's 1980's 1990's 2000's Total Total Pipes Installed 1325 1462 2242 548 886 580 7043 Recorded Pipe Failures 14 23 8 0 0 0 45 Unrecorded Failure Factor 1.47 1.30 1.15 1:03 1 1 Total Pipe Failures 21 31 10 0 0 0 62 Percentage of Failed Pipes 1.6% 2.1% 0.4% 0.0% 0.0% 0.0% 0.9% Table 12 Actual and modeled fourth time break comparisonls Pipe installed Pipe installed Pipe installed Pipe installed Pipe installed in 1950's in 1960's in 1970's in 1980's in 1990's Extrapolated Actual Third 21 31 10 0 0 Time Breaks Model Predicted Third 37 24 19 2 1 Time Breaks Model Error 76% -23% 90% -21- Pipe Replacement Technical Memo Pipe Failure vs Time 70% 60% ~ 50% ~ 40% a 30% a 20% 0 10% `,7 - 0 50 100 150 200 250 •---Weibull Function Pipe Age (years) ¦ Actual Data Figure 15 Weibull fit for fourth break 5.5 Summary of Classifications Each of the classifications described above are different paths that can be taken financially in the budgeting of pipe replacement. There are advantages and disadvantages of each and therefore a balanced decision must be made in the selection. The balance that must be made is between the money spent now on replacement and the money spent later on repair and replacement, Each of the classification has a unique Weibull curve and failure response over time. From these mathematical functions, annual pipe break curves were created to help evaluate which financial "path" should be taken by the city, The following table shows the predicted number of breaks for each classification. Breaks per Year 180 160 lam. 140 120 - -1 Break=Failure z 100 - - - -~=1- -2 Breaks=Failure A 60 - - 3Breaks-Failure - d Breaks=Failure 60 - - 40 - 20 - - - O N ~ (D CO O N 7 (D 00 O N e} fD N O N d- O O O Ql O O m 01 O O O O O N N N N N m O~ O~ m O O O O O O O O O O O O O O O O O ~ r r r N N N N N N N N N N N N N N N N Year Figure 16 Predicted annual breaks10 -22- Pipe Replacement Technical Memo One of the most important factors in allocating sufficient funding for pipe replacement is the public perception of breaks. Water main breaks can cause the public to distrust the utility's ability to plan for and provide a stable water supply. According to the AWWA benchmarking utility performance, the City of Boulder water distribution system is currently operating with less annual breaks than other municipalities in the region. Above 120 annual breaks puts the city at the average mark and more than 220 annual breaks causes the city to operate at the worst level in the region. In order to keep annual breaks below the 120 threshold in the medium term, a budgetary plan similar to the results of the second classification must be taken. This means that 3 breaks or more would be considered unacceptable and any pipes that have 3 breaks or more will need to be replaced in conjunction with the new failing pipe. From the recorded break data, 135 pipes have 3 or more breaks and will have to be caught up to the current system. This accounts for over $7 million that will have to be invested along with the predicted budgetary amount. 6 Plan Budget Currently the City of Boulder spends around $2 million each year on pipe replacement. The goal for pipe replacement is to keep the distribution system functioning properly without excessive pipe breaks. From the results of the modeled scenarios, a predicted decade by decade cost of pipe replacement has been generated for the City of Boulder to use in budgeting for effective pips replacement in the future. This budgetary information is the goal for the all the modeling as it gives a best estimate for pipe replacement schedule of costs in the future. The following table summarizes the budgetary costs necessary for keeping the distribution system consistent with the classifications discussed in the previous section. The actual average annual pipe replacement during the decade of the 2000's is shown in the first column. Table 13 Rehabilitation cost per decade in 2007 dollars14 Avera e Annual Re lacement Cost and Pi a Breaks 2000 2010 2020 2030 Classification $ 2,177,900 $ 4,121,600 $ 5,702,200 $ 6,575,600 1 39 57 73 85 Classification ~ 2,177,900 8 1,391,200 ~ 2,377,500 $ 3,547,900 2 53 80 107 130 Classification $ 2,177,900 $ 805,200 $ 1,351,300 $ 2,048,200 3 61 92 123 _ 152 Classification $ 2,177,900 S 450,300 ~ 752,400 $ 1,151,800 4 67 101 137 170 The projected annual pipe replacement costs and annual pipe repair costs are plotted in the following charts for all four classifications. These charts visually show at what classification pipe replacement becomes less than annual break repair. A $10,000 repair cost was assumed per break which takes into account an estimated $5,000 direct cost of repair and $5,000 cost to account for potential damages to private property and public inconvenience. The annual cost of a break repair in 2008 was around $5,000. All values are shown in 2007 dollar value. -23- Pipe Replacement Technical Memo One Break Equals Replacement $~,ooo,ooo H $6,000,000 Y d $5,000,000 m $4,000,000 $3,000,000 ~ $2,000,000 U $1,000,000 ---T-- 1995 2000 2005 2010 2015 2020 2025 2030 2035 2040 Cost of Annual Break Repair Year ~ Cost of Annual Replacement Figure 17 Classification 1 break repair vs replacementlo Two Breaks Equals Replacement $4,000,000 w $3,500,000 Y ~ $3,000,000 m $2,500,000 - _ - $2,000,000 $1,500,000 ~ $1,000,000 - V $500,000 1995 2000 2005 2010 2015 2020 2025 2030 2035 2040 Cost of Annual Break Repair Year -a- Cost of Annual Replacement Figure 18 Classification 2 break repair vs replacement''0 -24- Pipe Replacement Technical Memo - - -i Three Breaks Equals Replacement $2,500,000 w ~ $2,000,000 ' m m $1,500,000 m $1,000,000 - E U $500,000 i 1995 2000 2005 2010 2015 2020 2025 2030 2035 2040 Cost of Annual Break Repair ~ Year -~Costof Annual Replacement - - - Figure 19 Classification 3 break repair vs replacementlo Four Breaks Equals Replacement I $2,500, 000 tll ~ $2.000.000 L m $1,500,000 - m $1,000,000 ~ $500,000 U 1995 2000 2005 2010 2015 2020 2025 2x30 2035 2040 Cost of Annual Break Repair Year Cost of Annual Replacement Figure 20 Classification 4 break repair vs replacementlo 7 Recommendation The analysis of the different classifications presented above produced results that can give the City of Bou{der an advantage in preparing for the future. The water distribution system is a critical part of any society and should be well maintained and cared for property. Classification 2 presented above is the best cost estimate for the city to use for planning the future CIP. When considering the annual replacement cost based on classification 2 and the $7 million backlog of pipe replacement needed to reach classification 2, it is recommended that the average annual funding of $2.1 million be maintained during the next deeade. -25- Pipe Replacement Technical Memo 8 Discussion on Confidence The Weibull function is a statistical function that uses current data to produce a future prediction model. There is always uncertainty when trying to make predictions about the future especially when limited data exists. Because of the predictions made in this analysis, the confidence in the accuracy of the results must be discussed. Statistically speaking, the two factors that limit confidence in an analysis are lack of sufficient data and data that doesn't support a common trend. In order to better understand the results produced from the above analysis, a quantification of the confidence was calculated. Quantifying the confidence in the results is highly dependent on the quality of the raw data as well as the goodness of fit it has to a statistical function. As seen in section 2 of this memo, pipe break data has anly been recorded for one third of the current pipe lifetime. This lack of data created the need to extrapolate for unknown data backwards in time before making a prediction about the future. Much of the pipe ages in the system had to be estimated as well due to insufficient recorded data. Approximate pipe age was estimated and grouped by decade which didn't provide many data points to create a curve from. This can be seen in figures 12 through 15. The data in this analysis had to be used to create the Weibull curve and fitting the curve to the data wasn't an exact fit. This ability to fit the data is taken into account when quantifying the confidence level of the results. The better the function can be fit to the data points the higher the confidence will be in the final results. Due to both a low number of data points and the quality of fit to the Weibull function, the greatest confidence that was realistic tc~ use was 80%. The following figure shows the range of values of percent failure by year for the recommended Classification 2. As seen in the figure, there is an 80% confidence that the actual pipe will fail at a rate between the High and Low curves. The Weibull curve in the middle is the best estimate and the curve used in the cost calculations above. Percent Failure by Year 100% ~ 80% - ~ Weibull LL 60% High ~ 40% - - Low d 20% - ~o~ ~~ti ~o~ Year Figure 21 Curves in the 80% confidence range -26- Pipe Replacement Technical Memo Using the values plotted in the above figure, a new cost estimate was created to show the range of values that could be spent within the 80% confidence range. The following table shows the results. Table 14 80% confidence yearly cost estimate Classification 2 Yearly Replacement Cost Range 2010 2020 2030 2040 2050 High Values $5,578,712 $9,343,575 $12,240,255 $12,834,276 $11,543,135 Weibull Values $1,391,200 $2,377,500 $ 3,547,900 $ 4,650,100 $ 5,368,900 Low Values $ 292,152 $ 427,950 $ 567,664 $ 651,014 $ 697,957 As seen in the above table, the possible necessary yearly cost can vary greatly from the recommended estimate. This is where the decision and reevaluation process will need to be used to make use of more available data in the future. As more data is used in creating the Weibull curve, more potential for a higher confidence is possible. 9 " Conclusion " ~~`Jncertainty will exist-whenever the use of a statistical function is used in a future prediction " 'mbclel. We are also uncertain at this point why some pipes will fail and others will not in similar conditions. The use of a statistical failure rate model such as the Weibull function captures the ~~unown failure mechanisms and predicts the future failure rate based on what the water dim ~ribution system has historically experienced. The uncertainty can create doubt in ones mind as to the relevance or importance of the use of statistical functions. The fact is that the Weibull function has been used to create some certainty in the very uncertain pipe failure patterns. City of Boulder staff has made the recommendation for future pipe replacement funding with the understanding that it is the best estimate that can be made at the present time with the available data. The City of Boulder currently provides excellent service to its water customers and the results of the above analysis will help guide the city to continue providing excellent service. -27- Pipe Replacement Technical Memo References and Notes 1. Much of the water main break data is unknown from the 1960's and 1970's although the 1961 COB annual report stated 35 breaks. There has-been a significant increase in annual water main breaks from the 1960's and the models predict even more annual breaks in the future. 2. Arun K. Deb, et al. Prioritizing water main replacement and rehabilitation, AWWA Research Foundation. 2002. 3. URS comprehensive review and assessment of the city of Westminster's water and wastewater infrastructure, 2005. All the following files are located in S:\PIN\ParkCentral\Utilities\Engineering\Nick Worley\Pipe Replacement\Revision 2 Fall 2008 4. New Scenario 1.xls (Point System Basis tab) 5. New Scenario 1.xls (Pipe Data Summary tab) 6: New Scenario 1.xls (Break Data Summary tab) 7, Corrosion Breaks Map.jpg 8. Pressure Breaks Map.jpg 9. Settlement Breaks Map.jpg 10. New Scenario 1.xls (Weibull Function(New) tab) 11. New Scenario 2.xls 12. New Scenario 3.xls 13. New Scenario 4.xls 14. IUew Scenario 1.xls (Cost Summary tab) 1S. Denver Water- Conversation with Alan Crouch 1-27-09 -28- Pipe Replacement Technical Memo