9 - Development Report
MEMORANDUM
TO: Board of Commissioners
FROM: Betsey Martens, Executive Director
Stuart Grogan, Director of Development
Shannon Cox Baker, Project Manager
Kevin Knapp, Project Manager
Liz Wolfei-t, Project Assistant
Lindsey Moss, Project Assistant
SUBJECT: Development Report
DATE: February 2, 2011
This month's development report includes:
Consent: No items at this tune.
Action/Discussion: No items at tlus time.
Updates: High Mar Redevelopment
Red Oak Park
Lee Hill Housing
Broadway West
Attachments: Project Tracking Form and Timeline
CONSENT ITEMS
No items at this time.
ACTION/ DISCUSSION ITEMS
No items at this time.
AAP
UPDATE ITEMS
HIGH MAR REDEVELOPMENT
Previous Board Meeting:
At the last meeting, we provided the following information:
• An update on the site review process, specifically, that we anticipated receiving the
Notice of Disposition the week of December 13, 2010;
• An update on the 2011 City grant process, specifically, that City Housing and Human
Services (HHS) staff and the Technical Review Group (TRG) declined to award High
Mar $450,000 in predevelopment grant funds on the basis that a low income housing
tax credit (LIHTC) reservation was necessary before additional funds could be awarded
to the project; and
• A report that total development costs for the project were $12.8 million, but a
schematic design cost estimate was underway and would be completed by early
January.
Progress since Previous Board Meeting:
Site Review Application: We received the Notice of Disposition from the Planning Department
on January 4, 2011. Planning Board reviewed the project on January 6, 2011 and decided not to
call up the project for further review. Nobody from the public called up the project during the
mandatory two week call-up period. As of January 18, the project has received Site Review
approval and is officially entitled. We will be working with City staff to submit the final mylar
sets of drawings and execute the Development Agreement to complete the process.
Design Schedule: The design team will complete Design Development (a more detailed set of
drawings than Schematics that will inform the final Construction drawings) by the end of March.
We anticipate submitting Technical Documents to the City Engineering Department for a first
round Tech Doe review in mid-February. We estimate the design team will complete the Tech
Doc process in 4-6 weeks and will begin on Construction Documents (CDs) in April. The
project will be building-pen-nit ready by July, 2011.
City Funding: In December, we appealed the HHS staff's decision to deny High Mar's request
for a 2011 grant for additional predevelopment funding. After several discussions between BHP
and HHS, we sent a letter to HHS on January 13, 2011 requesting them to amend our grant
application as follows: that the grant amount be reduced to $350,000; the funds be used to close
the financial gap between total development costs and the available sources of funds (not for
predevelopment activities as we originally requested); and HHS provide us with a letter of intent
to commit the funds to the project once a LIHTC reservation is secured. In the letter, we agreed
to not request any additional funds from HHS for High Mar except in the event of dramatic or
unforeseen changes in the L11-ITC market, debt financing, construction costs, or a related event.
We anticipate a response from HHS by early February.
2
W`
Cost Estimate: The Schematic Design cost estimate is in line with our original expectations. At
the project's outset, we set a hard cost goal (vertical construction, only) of $110 per square foot
(sf). The project as currently designed betters our original expectations and is achieving $98/sf
($102,477/unit). Total all-in development costs (includes: soft costs, site work, horizontal
construction, contingencies and reserves, and developer fee) are $190/sf, or $199,431/unit. Per
the table below, High Mar is within or below the Division of Housing's financial benclunarks in
every category.
HIGH MAR FINANCIAL BENCHMARKS
CDOH RANGE HIGH MAR
Total Development Cost*/SF $135 to $205 $190
Hard Cost/SF (inc. dev. fee) $105 to $160 $117
Soft Cost/SF $25 to $40 $24
Land Cost/Unit $10,000 to $18,000 $7,492
PUPA w/o reserves $3,700 to $4,700 $4,122
Replacement Reserves/Unit $250 (senior properties) $300
Debt Coverage Ratio (yr I.10 to 1.20 1.20
Debt Coverage Ratio (yr 15) 1.10 to 1.20 1.15
Capitalized Operating Reserve 4 months debt, op. costs 6 months
CDO14 investement/Unit $4,000 to $10,000 $7,500
Consultant Team: We procured the law firm of Winthrop & Weinstine (specifically, attorney
Jon Peterson, who worked on the Red Oak Park closing) to represent both High Mar and Lee Hill
throughout the LIHTC and development processes.
LIHTC Schedule: We are on track to submit a LIHTC application on March 1; the first of two
application cycles in 2011. We believe High Mar is very competitive under the criteria
published by the Colorado Housing Finance Authority's (CHFA) Qualified Allocation Plan
(QAP) including site control, team experience and energy efficiency. High Mar is also
competitive under the "readiness to proceed" criterion which includes demonstrating the ability
to implement the project within twelve months, zoning approval, no environmental issues,
schematic drawings and a general contractor prepared estimate.
We further believe that under the final threshold, market study, there is sufficient demand under
several measures that High Mar will lease up quickly. However, the QAP states that recently
approved projects must be afforded the opportunity to lease-up without direct competition from
another tax credit project. CHFA has expressed concern that High Mar will create competition
with, and potentially negatively impact Boulder County Housing Authority's recently approved
senior housing project, Josephine Commons, which is located in Lafayette. We and our market
analyst do not share that concern. As part of our application, we will provide CHFA with data
that explains why we do not believe either project will be negatively impacted if both are able to
move forward.
417
If a 2011 LIHTC Preliminary Reservation is secured during this LIHTC round, construction
could commence as early as July 2011. If a second application is required, we will re-submit in
July 2011. This will delay the commencement of construction until September, 2011 at the
earliest.
Next steps:
• Proceed through the Tee Doc design phase and continue to refine the unit plans and
building elevations;
• Refine the cost estimate and conduct a first-round value engineering exercise;
• Finalize the appeal process for 2011 grant finding; and
• Complete the LIHTC application and submit by March 1.
RED OAK PARK
Previous Board Meeting:
At the last meeting, we provided the following information:
• The project's fifth draw request was funded, which increased total project expenditures to
date to 37% of budget;
• A construction update highlighting a concern that three duplexes in the Phase I were
behind schedule;
• An update on the street installation, specifically that the first layer of asphalt throughout
the site as well as much of the curb and gutter had been installed; and
• An underground storm sewer update, which anticipated the completion of the system in
spring 2011.
Progress since the Previous Board Meeting:
Budget Update: Our seventh draw was funded on January 251'' which increased the amount of
expended funds to almost $6.2 million. In last month's sixth draw, we crossed the half-way
benchmark as 54% our project budget had been spent. We remain in a comfortable financial
position as much of our contingency funds remain unobligated.
Construction and Leasing Update: Construction activities at Red Oak Park continue to
progress at a rapid pace. Currently, the construction team is preparing to deliver the first ten
units to BHP on February 1, the originally scheduled date.
The leasing team reports significant interest in Red Oak Park by potential residents. The current
plan is to have the first four homes occupied on February 1. These four move-ins will fulfill our
lease-up commitment to our tax credit investor for the entire month of February. Some of these
first families are former residents of the mobile homes at Boulder Mobile Manor.
4
We expect fifteen more residential units to become available throughout the month of February,
which will exceed our investors' expectations and give us an early start on the lease-up schedule
we conunitted to at the financial close. Six of the fifteen units are located in the three duplexes
on the southwest conger of the site. Although we expected these duplexes to be available on
February 1 with the other Phase 1 homes, construction delays pushed their delivery back to
sometime around the second week of February. On the upside, we expect to take possession of
all nine of the Phase 2 units (located on the east side of Arnett St.) in late February, three weeks
ahead of their original March 15 delivery date.
Construction on the remainder of the site is also progressing nicely and without major budget or
schedule concerns. We currently have thirty-seven of the forty residential buildings framed and
hope to have the framing contractor complete their work in the first half of February. All
concrete work is also nearly complete. The residential foundations have been poured leaving
only the Community Center slab and patios to be poured before the concrete contractors finish
their work.
ROP Projected Unit Delivery Schedule Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11
Phase 1(16 units)
Phase 2 (9 units)
Phase 3 (10 units)
Phase 4 (9 units)
Phase 5 (8 units)
Phase 6 Q units)
Community Center
Construction Completion
Storm Sewer System and Caisson Drilling: Despite our earlier projection that we would wait
until the spring to finish the storm sewer system, the construction team was able to complete it
shortly into the new year thanks to some above-average temperatures and fair weather. The caisson
drilling was also completed in December. Together the underground utility installations and the
caisson drilling presented some of the larger challenges and risk factors during construction. Both
the caisson drilling and utility work was completed without obstacle and within the original budget.
Next steps:
• Move in the first four households on February 1St;
• Continue the lease-up process;
• Submit Draw 98 in early February; and
• Monitor construction activities to ensure the delivery of 15 more units within February.
5
LEE HILL HOUSING
Previous Board Meeting:
At the last meeting, we provided the following information:
• Our anticipated selection and contract with architectural services, geotechnical services,
survey, and technical services by early February 2011; and
• HHS staff and the TRG's evaluation our appeal for a $300,000 grant, instead of a loan, to
support our predevelopment efforts.
Progress since Previous Board Meeting:
Consultants: We have evaluated and scored the proposals for architectural services,
geotechnical services, survey, and cost estimation. We anticipate finalizing our decision by the
first week of February and comiencing site work and a kickoff design team meeting by the first
week of March.
Predevelopment Funding: The City's HFIS staff and the TRG agreed to provide the project
with a $300,000 grant instead of a loan. These funds will be used for architectural and other
predevelopment services.
Schedule: The predevelopment phase of the project commenced in December 2010. The
neighborhood outreach process will begin in March, during the concept design phase, and will
extend through schematic design. We anticipate the project can complete the design and
permitting process in 12 months, or by March 2012. Our efforts to secure financing will run
concurrently with the design process; our goal is to secure 100% of the financing by December
2011. The construction process could begin as early as Spring 2012 (likely Fall 2012 if we
pursue LIHTC) and will require 10-12 months until completion.
Lee HIII Project Schedule Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11[Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Jan-13
Predevelopment
Concept Design
Schematic Design
Design Development
Construction Documents
Permitting
Construction
Financin ,
Next steps:
• Create a project budget;
• Hire a technical services consultant; and
• Execute a binding partnership agreement with the Shelter.
G
S~
BROADWAY WEST
Previous Board Meeting:
At the last meeting, we provided the following information:
• Broadway West's Land Use Restriction Agreement (LURA) from CHFA had been
signed and recorded, and we expected to receive our 8609 certificates;
• We provided clarifications to CHFA about our Final LIHTC Application;
• We addressed the final questions posed by US Bank regarding the 2nd Capital
Installment; and
• The loan conversion documents had been signed by BHP in preparation for the actual
loan conversion.
Progress since Previous Board Meeting:
Tax Credit 8609 Certificates Received: In December, CHFA accepted our Final L1HTC
Application and sent us the project's 8609 certificates. We signed the certificates and sent a
copy to US Bank. These certificates will allow US Bank to begin receiving the tax benefits
associated with purchasing Broadway West's tax credits, based on the units fully occupied in
2010. We will also use the 8609 to process the Broadway West 2010 tax return.
Capital Contributions and Loan Conversion: On December 6 and 7, we received the 2"d
Capital Contribution from US Bank, totaling more than $3 million. This Capital Contribution
was intended to be used to partially pay down the project's construction loan and to pay a portion
of BHP's developer fee. Upon receipt, the Capital Contribution was immediately transferred to
First Bank and put toward paying down the project's construction loan. This loan was then
officially converted to permanent status. We then drew down the developer fee portion. We will
receive the remaining developer fee through US Bank's aid and 4t" Capital Contribution, which
will be available in the second quarter once the Broadway West tax return and audited financials
are complete.
Next steps
• Apply to receive the 3id and 4"' Capital Contributions in the second/third quarter of 2011.
PROJECT TRACKING AND TIMELINE
The following Development Division tracking tools, which are updated monthly, are attached to
this memo:
• Development Tracking Sheet
• Project Benclunark Timeline
7
k
D v e t o p m e n T r a y i n g 4o
February 2011
Research, Pre Construction Transition/ Leased-Up/
Evaluation, Development Lease-Up Completed
On Hold or
Red Oak Park Red Oak Park
Tracking
(Phase 1)
Existing Unit Acquisition Bridgewalk
Transit Village (RTD)
Wallace Acquistion Lee Hill Housing
28th Kalmia
NoBoYarmo High Mar
Valmont (ROP II)
Armory Redevelopment
Hogan Pancost
Palo Park
Iris Hawthorn
Public Housing
Conversion
Tax Exempt
Partnerships
4e
Infeasible Technical
Landmark Lofts Assistance
Junior Academy Roaring Fork Board Action This Month
Orchard Grove
7000 2010 2011 2012 2010
Sep Oct No, OeC Jan Feb Ms A p( Maw Jun Jul A" 9G0 OCI Nov Dee Jan Feb V. ar Apr May Jun Jui Fu0 Sep
Oct Nov Duo Jan Feb filar Apr May Jun Jul A" Sep 00 Nov ate Jan Fen ma r 'I'd
ecw a:.uc
Red Oak
Park M d+
aM
[Ma"mga 1 i" I x;,,_r. ~ 1...I it !3J'r r•i
High Mar - - - - - -
n;,,:iy c~
an..iq City Apply lcfia] A C PAIY 16r
ity Dr Oftigenca
flu+J[ FwQa
I
E :G:rv_
Lae Hill
Housing Apply for APAY for eppy In!
r~+z^c em Cey f%Tu Dor OeiOenn
F-ds FunIs CndAa
o, 6eadln BHP Dua ClnenO or
I.. Tnnafx DIIWnna
.w Pram ~t.ra««.
:tAYtnq.4
,;uy lwCnyfM05 'eqt _
a;a}!w 6wr fads
C ;r 0.vckPnenl A~ cisn+ _
Fi?IW T. Clear, w-r , F-J .
xyxrnn I`
Ca+wsw~ `c '':R
in xr d hnwcr I•:a: ca