HomeMy WebLinkAbout10.20.2025 WRAB Agenda 5 - Community Broadband UpdateCITY OF BOULDER
WATER RESOURCES ADVISORY BOARD
INFORMATION ITEM
MEETING DATE: October 20, 2025
AGENDA TITLE: Information Item – Community Broadband Update
PRESENTERS:
Joe Taddeucci, Director of Utilities
Chris Douville, Utilities Deputy Director of Operations
Maria Rotunda, Community Broadband Program Manager
Randy Reese, Construction Project Manager for Community Broadband
EXECUTIVE SUMMARY
The purpose of this memorandum is to provide the Water Resources Advisory Board an
overview of the City of Boulder’s Community Broadband Program and highlight Boulder’s
partnership with ALLO Communications in build-out of the last-mile infrastructure that will
deliver high-speed fiber optic internet throughout the community. The Community Broadband
Program includes both current and future initiatives aimed at leveraging existing city-owned
fiber infrastructure (referred to as the backbone) to deliver public benefits such as competitive
pricing and equity advancement. We are providing this overview to the Board to ensure
awareness of the program, particularly given the involvement of city utilities in supporting initial
construction and management of the fiber infrastructure as board members may receive questions
from community members about the project or its impact on city utilities.
BACKGROUND
City officials began searching for broadband solutions in 2015, inspired by examples of nearby
municipalities developing their own publicly built and publicly owned networks to compete with
the regional and national provider incumbents. Then and now, virtually no addresses within
Boulder’s city limits met or meet the Infrastructure Investment and Jobs Act (IIJA) definition of
“unserved” but over two thirds of addresses in the city are only served by one wired provider,
limiting choice for residents and businesses.
In 2016, a city-owned community broadband fiber optic backbone was discussed with City
Council, and a feasibility study was completed. By 2018, Council approved building a dark fiber
backbone along major transportation corridors, recognizing the long-term value of owning the
10.20.25 WRAB Agenda 5 - Community Broadband Update
Page 1 of 4
infrastructure. This initial $20 million investment in high-speed fiber, known as Phase 1,
included 55 miles of infrastructure and marked the first step toward delivering this service.
As Phase 1 neared completion, Council and staff evaluated the various options to proceed with
community broadband, including creating a new dry utility department within the city to directly
provide service (i.e. public option), going with a 100% private model, or a hybrid option. In
2023, Council voted to move forward with the hybrid model including a public private
partnership (PPP) to build-out the last-mile fiber infrastructure for retail internet delivery and
lease capacity from the city-owned backbone. In 2024, the city issued an RFP for a service
provider. ALLO Communications was selected, and the city and ALLO signed a 20-year lease
agreement. Now, in 2025, ALLO is beginning construction on ‘Phase 2’ of Community
Broadband.
The city also manages many other uses of fiber on both newly built backbone fiber and other
legacy owned and leased fiber. One of these long-term networks is the Boulder Research and
Administrative Network (BRAN), which interconnects the City of Boulder, University of
Colorado at Boulder, The National Center for Atmospheric Research (NCAR) and the
Department of Commerce Laboratories, including NOAA and NIST. BRAN provides significant
local fiber optic infrastructure to give these Boulder public institutions a competitive advantage
in research, higher education, and administration while also allowing for cost sharing and cost
avoidance by the partners.
Additionally, the city partners with the Boulder Valley School District (BVSD) in an exchange of
long-term leases of city underground conduit and BVSD dark fiber strands. The city leases
conduit in parts of Boulder to BVSD and BVSD leases strands in its backbone fiber optic cable
for the use of the city. This arrangement reduced the cost and speeded the installation of a
BVSD-owned fiber backbone in Boulder which interconnects schools in a high-speed BVSD
network. Several city facilities within the departments of Utilities, Parks and Recreation, and
Fire-Rescue — including five fire stations — rely on BVSD fiber for connectivity to the greater
city network. Amendments to the city’s lease agreement with BVSD expanded the leased BVSD
fiber assets to connect remote city source water facilities (Kossler Reservoir and Barker Dam)
and fiber strands in Boulder made available to BRAN partners.
ANALYSIS
ALLO: As ALLO begins its build-out, staff will be tracking several key deliverables and
milestones consistent with the 20-year lease agreement. ALLO will utilize a phased approach
that builds in areas with a higher density of affordable housing at approximately the same rate as
it builds in other areas of Boulder. The construction process is expected to be 97% completed by
the end of 2029. The overall ALLO construction effort is scheduled for 5 years and will include
300 miles of private infrastructure. ALLO aims to offer service to five manufactured housing
communities within Boulder.
10.20.25 WRAB Agenda 5 - Community Broadband Update
Page 2 of 4
To support accessibility and community engagement, ALLO will open a centrally located
storefront at the Village Shopping Center near McGuckin Hardware, easily reachable by public
transit.
ALLO’s high-speed fiber offering will help foster healthy market competition and fair pricing for
internet service, as potential customers consider their options between other incumbent wired
internet providers (Comcast Xfinity, CenturyLink, & QuantumFiber) and other future market
entrants.
To support digital equity, ALLO will offer discounted service—at least $30 below its lowest
standard rate—for income-qualified residents. It will also provide free internet to 25 selected
nonprofits through its Community Connector program.
As part of the lease agreement, ALLO will pay the city an ongoing monthly fee that is derived
from its number of subscribers. Based on an initial lease payment from ALLO and the
anticipated monthly lease fees from both residential and business subscribers, the estimated
valuation of the lease agreement is $9M. The company will also install a micro duct in the city’s
second conduit of the fiber backbone. This micro duct will include 288 strands of fiber dedicated
for city use, enhancing municipal broadband capacity and future use options.
City Projects: In addition to BRAN and BVSD, the city has several Intergovernmental
Agreements and projects associated with its dark fiber backbone. The city will continue to utilize
this asset and develop a framework for analysis of additional projects as community broadband
moves forward.
NEXT STEPS
ALLO: ALLO began construction in the Chautauqua neighborhood in September, as part of a
larger set of infrastructure improvements at Chautauqua involving electric utility
undergrounding, minor wet utility work, and repaving of streets. ALLO is securing agreements
with private landowners for critical fiber system infrastructure. Once finalized, the community-
wide construction effort will begin across designated geographic sub-areas. Services will be
offered to nearby residents and businesses as each sub-area is completed.
City Projects: Staff have an opportunity to establish a formal vetting process for current and
future dark fiber projects by implementing a structured decision-making framework. This
proactive approach will guide how new projects are initiated and introduce greater organizational
structure to existing ones. It will also help define project criteria, assess potential benefits, and
ensure consistent evaluation across all initiatives. More Community Broadband information is
available on the city’s webpage.
10.20.25 WRAB Agenda 5 - Community Broadband Update
Page 3 of 4
Additionally, staff plan to provide City Council with an update on Community Broadband in
2026, recognizing the past and current interest in this important community initiative.
10.20.25 WRAB Agenda 5 - Community Broadband Update
Page 4 of 4