MEMORANDUM TO THE LANDMARKS BOARD
January 5, 2022
STAFF
David Gehr, Interim Director of Planning and Development Services
Charles Ferro, Acting Comprehensive Planning Manager
Lucas Markley, Attorney, City Attorney’s Office
James Hewat, Principal Historic Preservation Planner
Marcy Gerwing, Senior Historic Preservation Planner
Clare Brandt, Administrative Specialist II
Faith Hamman, Historic Preservation Intern
LANDMARK ALTERATION CERTIFICATE REQUEST
Public hearing and consideration of a Landmark Alteration Certificate application to restore
the Ball Aerospace Control Cells Building at 5001 Arapahoe Ave., a pending individual
landmark, pursuant to Section 9-11-18 of the Boulder Revised Code 1981., and under the
procedures prescribed by chapter 1-3, “Quasi-Judicial Hearings,” B.R.C. 1981.
Address: 5001 Arapahoe Ave.
Owner/Applicant: Ball Corporation / Guy Fromme, Ball Aerospace & Technologies Corp.
Case Numbers: HIS2021-00292
Case Type: Landmark Alteration Certificate
Code Section: 9-11-18, B.R.C., 1981
SITE INFORMATION
Individual Landmark(s): Ball Aerospace ADO/Control Cells Building (Landmark
application pending HIS2021-00291)
Date of construction: 1956
Zoning: IG (Industrial – General)
Lot size: 4.0 acres (GIS estimate)
Existing Building Size: 15,859 sq. ft.
Proposed Building Size: 5,668 sq. ft.
STAFF RECOMMENDATION
Staff recommends the Landmarks Board conditionally approve the application.
RECOMMENDED MOTION
I move that the Landmarks Board adopt the staff memorandum dated January 5, 2022, as the
findings of the board and conditionally approve a Landmark Alteration Certificate to remove a
1960 addition and restore the Ball Aerospace CONTROL CELLS Building at 5001 Arapahoe
Ave., a pending landmark, as shown on plans dated November 11, 2021, finding that the
proposal meets the Standards for Issuance of a Landmark Alteration Certificate in Chapter 9-
11-18, B.R.C. 1981 and is generally consistent with the General Design Guidelines provided the
stated conditions are met.
Conditions of Approval
1. The applicant shall be responsible for completing the work in compliance with the
approved plans, except as modified by these conditions of approval.
2. Prior to submitting a building permit application and final issuance of the Landmark
Alteration Certificate, the applicant shall submit final architectural plans and
specifications to the Landmarks design review committee (Ldrc), for its final review
and approval to ensure that the final design of the building is consistent with the
General Design Guidelines and the intent of this approval:
a) Details on all windows, doors, grading/hardscaping, and final paint colors.
BACKGROUND AND SUMMARY
• The Ball Aerospace Control Cells Building was designed by Hobart Wagener and
constructed in 1956 and added onto in 1960.
• A condition of staff’s recommendation for Site Review approval for the redevelopment of
the larger Ball Aerospace site is submission of landmark designation application for the
1956 Control Cells portion of the building and a portion of the property (excluding the 1960
addition). A landmark application was submitted on November 19th, 2021; the designation is
pending and contingent upon Site Review approval of the development by the Planning
Board.
• Four other Hobart Wagener-designed buildings on the property, constructed between 1959
and 1962, have been approved by staff for demolition (HIS2021-00293).
• On Nov. 9, 2021, the owner submitted a Landmark Alteration Certificate (LAC) application
for the removal of the 1960 addition and restoration of the building.
• On Nov. 24, the LDRC referred the application to the Landmarks Board for review.
• Staff recommends that provided the stated conditions are met, the proposal will meet the
criteria for a Landmark Alteration Certificate as per 9-11-18(a) & (b)(1)-(4) B.R.C. 1981 and be
generally consistent the General Design Guidelines.
PROPERTY DESCRIPTION
Ball Aerospace & Technologies Boulder Campus at 1600 Commerce Ave. and 5001 Arapahoe
Ave. is located on the north side of Arapahoe Avenue, between Commerce and Range streets
in East Boulder. The property is not located in a potential historic district.
Figure 1. Location Map, Ball Aerospace & Technologies Campus, 1600 Commerce St. and 5001 Arapahoe Ave.
Figure 1. Aerial, Ball Aerospace & Technologies Campus, 1600 Commerce St. and 5001 Arapahoe Ave.
Building Description – 1956 ADO/Control Cells Building
The Ball Brothers Control Cells building was constructed in two phases. The original building
was completed in 1956, and the addition on the west side of the building was completed in
1960. The Regional Modernist building is constructed of painted concrete block with an
alternating pattern of projecting blocks.
Stylistically, the building can best be described as Expressionistic in inspiration with its strong
sculptural forms paired with non-traditional structural elements. The building was constructed
in two phases: a square volume with a butterfly roof and a wing extending from the west
elevation with an accordion roof form. The most distinctive characteristics of the building are
the expressive roof forms, exposed skeletal structural systems, patterned concrete block and
clerestory windows.
Figure 3. Aerial Photograph, shaded to show location of addition and elevation key.
Figure 4. 1956 Ball Brother Control Cells Building shortly after construction. Carnegie Library for Local History.
Figure 5. Original Control Cells Building, South Elevation, 5001 Arapahoe Ave., 2021.
Figure 6. Original ADO/Control Cells Building, East Elevation, 5001 Arapahoe Ave., 2021.
Figure 7. Original ADO/Control Cells Building, North Elevation, 5001 Arapahoe Ave., 2021.
Building Description – 1960 Addition
In 1960, Ball Brothers converted the use of the Control Cells Building from a laboratory to an
administrative office. Hobart Wagener was commissioned to design an addition, which
extends from the west elevation of the original building. The addition is stylistically similar,
with concrete block with an alternating block pattern, clerestory windows, alternating roof
forms and exposed skeletal structural systems. Where the original ADO/Control Cell building
is a single story, the addition is two-stories due to the grade.
Figure 8. 1960 Control Cells Building Addition, South Elevation, 5001 Arapahoe Ave., 2021.
Figure 9. ADO/Control Cells Building Addition, West Elevation, 5001 Arapahoe Ave., 2021.
Figure 10. ADO/Control Cells Building Addition, North Elevation, 5001 Arapahoe Ave., 2021.
Figure 11. ADO/Control Cells Building Addition, North Elevation, 5001 Arapahoe Ave., 2021.
HISTORIC CONTEXT
In the 1950s Boulder began marketing itself as the perfect place for “clean” industry (City of
Boulder website, accessed May 9, 2008). Instead of relying on the land for products to process,
Boulder looked for industries which focused on electrical, engineering, environmental, or
computer science. 1 In 1949, Boulder successfully secured the establishment of the National
Bureau of Standard’s (NBS) Central Radio Propagation Laboratory and the following decades
saw the establishment of several public and private research institutions.
The Chamber of Commerce bought an eighteen-acre tract [in East Boulder], called it the
Boulder Industrial Park, and convinced Ball Brothers Research Corporation to be its first
tenant (first building was completed by May 1956).2 Edmund F. Ball purchased Control Cells
Inc. and founded the Ball Brothers Research Corp in 1956. Ball Brothers Research Corporation
became Boulder’s largest employer outside of the university, with over 3,000 employees.3
O.E. “Pete” Bartoe, was the company’s first employee and worked as a seminal space craft
designer. Bartoe, CU physicist David Stacey, and CU engineer Jim Jackson moved into the
Control Cells building and started designing a new pointing control.4 R.C. “Merc” Mercure,
joined the company in 1957 and became the company’s president. The company started out
with orbiting solar observatories which were crucial in the development of the company.
Mercure said, “We became very skilled at it [making instruments for space] and developed an
enormous reputation among space scientists of the nation because we could take what they
wanted to do and make instruments.”5
1 Bryant, Jennifer, and Carrie Schomig. “Historic Context and Survey of Post-World War II Residential Architecture
Boulder, Colorado,” April 2010. https://www-
static.bouldercolorado.gov/docs/Combined_Post_WWII_Residential_Survey,_2010-1-
201509031405.pdf?_ga=2.250775622.170951014.1608483712-1638280431.1606173491
2 Smith, Phyllis. A Look at Boulder: From Settlement to City. 1981.
3 Michael Paglia, Leonard Segal, and Diane Wray, “Historic Context and Survey of Modern Architecture in
Boulder, Colorado 1947-1977,” June 2000.
4 Todd Neff, “50 Years of Exploration for Ball,” Boulder Daily Camera, August 14, 2009.
5 Neff. Ibid.
Figure 12. Arapahoe Avenue at Boulder Industrial Park before the construction of the multi-story Ball Brothers
building, 1960-1961. Carnegie Library for Local History.
As the company grew, so did the Industrial Park. Hobart D. Wagener, a notable architect in
Boulder and Colorado, was commissioned to design the buildings for Ball Brothers.6 Wagener’s
design for the Control Cells building was realized in 1956 and is the earliest building on the
site.7 A year later, it was converted into a research lab. Around 1960 it was converted into an
administrative building. An addition also designed by Wagener was added in 1960.
A series of “Tech” building (Tech I – Tech III) were constructed in 1959 after design by. Wagener
Associates. A Boulder Daily Camera article from November 1959 captions a photo of the new
Technical Building No. 1 with “Ball Brothers Research Corporation, a growing factor in U.S.
6 “Hobart D. Wagener,” Coronado Eagle & Journal | Coronado News | Coronado Island News, October 2005,
http://www.coronadonewsca.com/obituaries/hobart-d-wagener/article_0486f2ba-aad6-554c-95c0-
b9ed4d769269.html.
7 City of Boulder Historic Preservation Program, “History of Buildings, Ball Aerospace,” December 2020.
space experiments, recently moved into this new building in Boulder Industrial Park … which is
already proving inadequate.”8
The Tech Tower was constructed in 1962 and was another design by Hobart D. Wagener
Associates and was featured in the 1966 book “Mountains, Mines & Mansions: An
Architectural Guide to Colorado.” The Tech Tower served as additional research space, office
and laboratory areas.9
Figure 13. Birdseye view of Ball Aerospace, c.1962. Carnegie Library for Local History.
8 “Ball Brothers Additions: Photo 1,” Carnegie Library for Local History, accessed December 6, 2021,
https://localhistory.boulderlibrary.org/islandora/object/islandora%3A43133.
9 City of Boulder Historic Preservation Program, “History of Buildings, Ball Aerospace,” December 2020.
Figure 14. Rendering for Control Cells Building by Hobart Wagener, c.1955. Carnegie Library for Local History.
Hobart Wagener
Hobart Wagener is one of Boulder’s most well-known and prolific Modernist architects. He
graduated with honors from the University of Michigan School of Architecture and worked in
the offices of Eggers and Higgens in New York City and Pietro Belluschi in Portland, Oregon
before moving to Boulder in 1950. After working in the offices of James Hunter, he opened his
own office in 1953 and practiced until retirement in 1985. He designed over 200 public and
private buildings, including St. John's Episcopal Chapel, First Methodist Sanctuary, Midland
Saving and Loan (the Atrium), Fairview High School, Presbyterian Manor Apartments, Fruehauf
Garden Center and the First National Bank. Sixteen buildings were featured in architectural
and professional publications; ten received national or regional awards from the American
Institute of Architects (AIA).
In 1971, “Hoby” was elected a Fellow in the AIA and in 1985 was recognized as the architect of
the year with the AIA Colorado Honor Award. In 1995, Williams Village received an award as the
outstanding building built in Colorado in the past 25 years. In 1998, the Colorado North
Chapter of the AIA presented him the President's Award for practicing architecture significant
to the professional development of a future generation of architects.
Local Recognition of Buildings Designed by Wagener
The 2000 Historic Context and Survey of Modern Architecture in Boulder, Colorado 1947-1977
identifies Wagener as an acknowledged master of local architecture. The survey identifies “the
most important architects and sixty-six of the most significant buildings of the period.” The
survey included 10 buildings designed by Wagener:
1. Midland Savings and Loan, 1300 Canyon, 1969 (Pending Landmark Designation
Application)
2. Fire Station #2, 2225 Baseline Rd., 1958
3. Green Shield Office Building, 900 28th St., 1959 (individually landmarked)
4. LaBrot House, 819 6th St., 1954 (individually landmarked)
5. Central Fire Station, 2441 13th St., 1957
6. Methodist Student Center, 1290 Folsom St., 1957
7. Short House, 1001 8th St., 1958
8. Thron House, 430 Christmas Tree Drive, 1963
9. Mountain Savings and Loan, 2300 Broadway, 1964
10. Acacia Fraternity Headquarters, 910 28th St.
DESCRIPTION OF PROPOSED WORK
Figure 15. Aerial, 2020 with elevation key.
Figure 16. Proposed Site Plan (addition proposed to be removed shown outlined in dashed line)
Site Plan
• Proposed removal of 1960 addition on the west elevation and c.1956 portion on north
elevation.
• Restoration of original ADO/Control Cells Building based on historic photographs.
• Restoration of 1956 circular drive at south of building.
• Reconfiguration of surface parking lot and addition of landscaping around the building.
Figure 17. Proposed Rendering of Restored ADO Building.
Figure 18. Existing Southwest Elevation.
Figure 19. Proposed Southwest Elevation.
West Elevation
Removal of 1960 addition.
Figure 20. Existing Northeast Elevation.
Figure 21. Proposed Northeast Elevation.
North Elevation
• Removal of east addition; restoration of northeast corner
• Removal of north addition; restoration of north elevation
• Introduction of garage door
Figure 22. Existing Southeast Elevation.
Figure 23. Proposed Southeast Elevation.
East Elevation
• Removal of one-story addition
• Removal of wall
Figure 24. Existing Northwest Elevation.
Figure 25. Proposed Northwest Elevation.
West Elevation
• Removal of east addition; restoration of northwest wall and glass curtain-wall (see
figure 25).
CRITERIA FOR THE BOARD’S DECISION
STANDARDS FOR LANDMARK ALTERATION CERTIFICATES, 9-11-18, B.R.C., 1981
(a) The Landmarks Board and the City Council shall not approve an application for a
Landmark Alteration Certificate unless each such agency finds that the proposed
work is consistent with the purposes of this chapter.
(b) Neither the Landmarks Board nor the City Council shall approve a Landmark
Alteration Certificate unless it meets the following conditions:
1. Does the proposed application preserve, enhance, or restore, and not damage or
destroy the exterior architectural features of the landmark or the subject
property within a historic district?
Provided the stated conditions are met, staff finds the proposal will be generally consistent
with the purposes of this chapter, in that the proposed removal of the 1960 addition and
restoration of the 1956 Control Cells Building will not damage the historic character of the
property.
2. Does the proposed application adversely affect the special character or special
historic, architectural, or aesthetic interest or value of the landmark property?
Provided the stated conditions are met, staff considers the removal of the 1960 addition and
restoration of the 1956 Control Cells Building will not adversely affect the special character or
special historic, architectural, and value of the property as the changes are generally
consistent with the General Design Guidelines.
3. Is the architectural style, arrangement, texture, color, arrangement of color, and
materials used on existing and proposed structures compatible with the
character of the landmark property?
Provided the stated conditions are met, staff considers that the materials proposed for the
restoration of the 1956 Control Cells Building will be compatible with the landmark property.
(c) In determining whether to approve a Landmark Alteration Certificate, the
Landmarks Board shall consider the economic feasibility of alternatives,
incorporation of energy-efficient design and enhanced access for the disabled.
Specific information specific to economic feasibly of alternatives, incorporation or energy-
efficiency design and enhance access for the disabled was not submitted with the application.
The reuse of an existing building is inherently sustainable, and the rehabilitation of the building
will need to meet the City’s energy code regulations and Section 106.5 helps ensure that any
alterations needed to meet the energy will not detract from the historic character of the site.
DESIGN GUIDELINE ANALYSIS
The Historic Preservation Ordinance sets forth the standards the Landmarks Board must
apply when reviewing a request for a Landmark Alteration Certificate (LAC). The Board has
adopted the General Design Guidelines for Boulder’s Historic Districts and Individual
Landmarks to help interpret the ordinance. Design guidelines are intended to be used as an
aid to appropriate design and not as a checklist of items for compliance.
SUMMARY
As outlined in the General Design Guidelines, the Secretary of the Interior provides four
approaches to responsible preservation practices (p22). “Restoration focuses on the retention
of materials from the most significant time in a property's history, while permitting the removal
of materials from other periods.”
The Boulder Revise Code establishes the criteria for the approval of Landmark Alteration
Certificates in Section 9-11-18, including: “The proposed work preserves, enhances, or restores
and does not damage or destroy the exterior architectural features of the landmark or the
subject property within an historic district.”
Staff considers that the proposed removal of the west 1960 addition will restore the
ADO/Control Cells Building to its original 1956 appearance and will retain materials from the
most significant time in the property’s history, as the building was the very first building on the
Ball Aerospace Campus and in the Boulder Industrial Park. While the 1960 addition was
designed by Wagener and in keeping with the architectural language of the 1956 Control Cells
Building, staff considers its removal to allow for the restoration of the very striking west
(Commerce Street facing) glass-curtain wall of the original building. Likewise, staff is of the
opinion that the small portion on the north side (rear) of the original Control Cells Building not
a character-defining feature and its removal would not adversely affect the special character
of the building.
2.4 Parking and Driveways
•Restoration of circular drive based on historic photographs and drawings is consistent
with design guidelines.
3.7 Windows and Doors
•Windows preserved / proposed for replacement – details not submitted; resolve at the
Ldrc.
•New garage door opening on north elevation will not be detrimental to the historic
character of the property as it is located on a tertiary elevation. Its installation will
require the removal of two windows and a small portion of concrete block.
Staff considers that the proposal to remove the 1960 addition and accurately restore the 1956
Control Cells Building and Site features is generally consistent with the Secretary of the
Interior’s Standards for Restoration and the General Design Guidelines for Boulder’s Historic
Landmarks, but that the Landmark Board’s approval be contingent upon details on all
windows, doors, grading/hardscaping, and final paint colors being reviews and approved by
the Landmark design review committee prior to application for a building permit.
PUBLIC COMMENT
Staff has received no public comment regarding this application.
FINDINGS
Staff recommends the Landmarks Board adopt the following findings:
The Landmarks Board finds that the project meets the standards for issuance of a Landmark
Alteration Certificate set forth in Section 9-11-18, “Standards for Landmark Alteration
Certificate Applications,” B.R.C. 1981. In reaching this conclusion, the Board considers the
information in the staff memorandum dated January 5, 2022, and the evidence provided to the
Board at its January 5, 2022 meeting. Specifically, the Board finds, if the stated conditions are
met, that:
•The proposal will be generally consistent with the purposes of this chapter, in that the
proposed restoration will not damage the historic character of the landmark property.
•The proposed restoration will not adversely affect the special character or special
historic, architectural, and value of the landmark property as they are generally
consistent with the General Design Guidelines and Section 9-11-18(b)(3) of the Boulder
Revised Code 1981.
ATTACHMENTS
Attachment A: Applicant Materials
PPlanningg && Developmentt Servicess || 17399 Broadway,, 3rdd Floor
P.O. Box 791 Boulder, CO 80306 303-441-1880
boulderplandevelop.net
Page 1 of 5
Updated March 2021
HIS -
Historic Preservation Landmark Alteration Certificate
(LAC) Application
f REQUIRED MATERIALS FOR PROPOSED EXTERIOR WORK TO ALL PROPERTIES IN DESIGNATED HISTORIC
DISTRICTS AND INDIVIDUALLY LANDMARKED
Signed application
Current site plan and photographs of the property, including the view from the street. See page 2.
Other materials defined by project type and scope. See page 5 for a checklist or required materials.
f TO SUBMIT YOUR LANDMARK ALTERATION CERTIFICATE (LAC)APPLICATION
x Save your materials as PDFs using the naming conventions in the Online Plan Application Guide
x Email application to PDSskipatrip@bouldercolorado.gov. Put Historic Preservation in the subject line.
x Questions? Contact Historic Preservation staff at 303-441-1994 or historic@bouldercolorado.gov
x Si necesita ayuda para traducir esta información al español, llame al 303-441-1905
f APPLICANT CONTACT INFORMATION
Name Phone#Email Address
Address City State Zip
f OWNER CONTACT INFORMATION SAME AS APPLICANT
Name Phone#Email Address
Address City State Zip
f PROJECT INFORMATION THE WORK WILL NEED TO MEET THE GENERAL DESIGN GUIDELINES ANDANY
DISTRICT-SPECIFIC DESIGN GUIDELINES (LINKS BELOW).
Project Address
Historic District
(Check one. Search the
map of Landmarks and
Historic Districts.)
Chamberlain
Chautauqua
Downtown
Floral Park
Highland Lawn
Hillside
Mapleton Hill
University Place
West Pearl
16th Street
Individual Landmark
Name:
Project Description
Date:
PLAN
✔
✔
✔
Ball Aerospace & Technologies Corp.303-210-3831 guy.fromme@ballaerospace.com
1600 Commerce Street Boulder CO 80301
✔
Guy Fromme 303-210-3831 guy.fromme@ballaerospace.com
1600 Commerce Street Boulder CO 80301
guy fromme Digitally signed by guy fromme
Date: 2021.11.04 20:35:51 -06'00'
Ball Aerospace ADO / Control
Cells Building
Appearance preservation and restoration of original 1956 Control Cells Building & Demolition of 1960 addition
✔
Attachment A - Applicant Materials
PPlanning & Development Services | 1739 Broadway, 3rd Floor
P.O. Box 791 Boulder, CO 80306 303-441-1880
boulderplandevelop.net
Page 2 of 5 Updated March 2021
f EXISTING CONDITIONS FOR ALL APPLICATIONS ATTACHED AS SEPARATE PDF
Location Map / Site Plan (paste here or attach as separate PDF) - survey, ILC or screenshot of aerial map showing adjacent streets.
Photographs of each side / elevation of the building (paste here or attach as separate PDF)
front rear
side side
✔
Attachment A - Applicant Materials
PPlanning & Development Services | 1739 Broadway, 3rd Floor
P.O. Box 791 Boulder, CO 80306 303-441-1880
boulderplandevelop.net
Page 3 of 5 Updated March 2021
f REQUIRED MATERIALS ATTACHED AS SEPARATE PDF
Color chips, samples and/or cut sheets for painting and/or roofing work (paste here or attach as separate PDF)
STOP HERE IF THE SCOPE OF WORK IS LIMITED TO THESE ITEMS (CHECK ALL THAT APPLY):
Roofing
Painting
Location of proposed work detailed on plan or mockup (paste here or attach as separate PDF)
STOP HERE IF THE SCOPE OF WORK IS LIMITED TO THESE ITEMS (CHECK ALL THAT APPLY):
Landscaping
Antenna or mechanical unit
Commercial awning
Commercial sign
Commercial patio
✔
Attachment A - Applicant Materials
PPlanning & Development Services | 1739 Broadway, 3rd Floor
P.O. Box 791 Boulder, CO 80306 303-441-1880
boulderplandevelop.net
Page 4 of 5 Updated March 2021
Scaled elevations (for fences, show all dimensions including spacing between pickets*)
existing proposed
existing proposed
existing proposed
existing proposed
STOP HERE IF THE SCOPE OF WORK IS LIMITED TO THESE ITEMS (CHECK ALL THAT APPLY):
Deck
Outdoor kitchen
In-ground pool or spa
Fence located at front of house
Fence at side or rear of house*
Fence taller than 5ft.*
*Side and rear fences with max height of 5’ with min 1” spacing between pickets
can be reviewed by staff.
Attachment A - Applicant Materials
PPlanning & Development Services | 1739 Broadway, 3rd Floor
P.O. Box 791 Boulder, CO 80306 303-441-1880
boulderplandevelop.net
Page 5 of 5 Updated March 2021
f CHECKLISTS FOR OTHER SCOPES OF WORK
For the following scopes of work, check all that apply and include separate PDFs of the required documentation:
Solar panels Completed application, pages 1 - 4
Solar renderings
New free-standing building 340 sq. ft. or smaller
New free-standing building larger than 340 sq. ft.
Demolition and new construction
Addition
Porch
Completed pages 1 - 4
Scaled architectural plans / project drawings: Side by side existing and
proposed, with annotated (measurable) scale.
Initial code review for new construction. See section below.
Doors
Windows
Skylights
Completed pages 1 - 4
Doors / windows replacement worksheet. This supplement will be sent to
the email address included on page 1 once the LAC application is accepted.
f INITIAL CODE REVIEW FOR NEW CONSTRUCTION
This review is intended to identify potential zoning and building code issues for new construction only. Please fill out to the best of your
ability. The verification of this form is a customer service review and does not constitute a formal review of all applicable codes and
regulations. All sections of the Boulder Revised Code must still be adhered to prior to performing any work. Property information can be
found on https://bouldercolorado.gov/planning/property-report
Proposed work is within requiredA2B/.09A Yes No
Existing Proposed new Total after construction Allowed maximum
Building coverage (sq. ft.)
Floor area (sq. ft.)
Height
Will the proposed require a variance or exemption? (check all that apply):
Setback variance (Section 9-7-2, B.R.C., 1981)
Side yard wall articulation standards (Section 9-7-10,
B.R.C., 1981)
Solar exception (Section 9-9-17, B.R.C., 1981)
Bulk plane requirements (Section 9-7-9, B.R.C., 1981)
Exemption from maximum building coverage for accessory buildings
in the rear setback (Section 9-7-ll(d), B.R.C., 1981)
✔
✔
✔
✔
✔
✔
✔
11,040 0 5,668
15,859 0 5,668
approx. 22'-2"0 approx 13'-0"55'
Attachment A - Applicant Materials
Ball Aerospace - ADO / Control Cells Building
Existing Photographs
Arapahoe Ave.Commerce St.NRange St.48th St.Peak Ave.
Ball Aerospace Boulder Campus
AD
ADO
AD Building (1960 Addition) to be Demolished
ADO Building to Remain
(Original 1956 Ball Brothers Research Corp.
"Control Cells" Building to be Restored /
Preserved)
Attachment A - Applicant Materials
KEY PLAN
NCOMMERCE ST.Street View from Commerce Street - Looking Northeast
Attachment A - Applicant Materials
Street View from Commerce Street - Looking East
Street View from Commerce Street - Looking Southeast
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing View of Entry - 1960 Addition
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing View of Entry - Original Building
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing Side View - 1960 Addition
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing Side View - 1960 Addition
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing Back View - 1960 Addition
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing Back View - Original Building / 1960 Addition
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
Existing Back View - Original Building / 1960 Addition
Existing Side View - Original Building
KEY PLAN
NCOMMERCE ST.Attachment A - Applicant Materials
1 ORIGINAL SUBMITTAL 05/28/2021
2 REV 1 08/02/2021
CONTROL CELLS / ADO BUILDING RESTORATION - LOOKING NORTH
10/25/2021
Control Cells Division, South Elevation, Brochure, c.1956
Control Cells Division, South Elevation (facing north), recently constructed, c.1956
Control Cells Division, Southwest and Northwest Elevations (facing East), recently constructed, c.1956
Control Cells Division, Northeast Elevation (facing Southwest), recently constructed, c.1956 000
01 HIST. PRESERV. LAC 11/01/2021
11/01/2021
Control Cells Division, Southwest Elevation (facing Northeast), recently constructed, c.1956
Control Cells Division, Southwest Elevation, Brochure, c.1956
OMMERCE ST BOULDER, COHISTORIC PRESERVATIONAttachment A - Applicant Materials
1 ORIGINAL SUBMITTAL 05/28/2021
2 REV 1 08/02/2021
CONTROL CELLS / ADO BUILDING RESTORATION - LOOKING NORTH
10/25/2021
LANDMARK
BOUNDRY
ADO BUILDING
SCALE:1" = 20'-0"1 HISTORIC PRESERAVATION - AD BUILDING2ADO BUILDING
Ball Aerospace - ADO / Control Cells Building
Overall Area Plan
Original 1956 ADO / Control Cells Building
To Be Preserved and Restored
1960 addition (AD Building)
To Be Demolished
Arapahoe Ave.Commerce St.NRange St.48th St.Peak Ave.
Ball Aerospace Boulder Campus
AD
ADO
SCALE:1" = 20'-0"1 HISTORIC PRESERAVATION - AD BUILDING
BALL BOULDER CAMPUS - AREA MAP
CONCEPTUAL IMAGE OF RESTORED ADO BUILDING
VIEW FROM THE WEST, LOOKING EAST 001
01 HIST. PRESERV. LAC 11/01/2021
11/01/2021
LANDMARK
BOUNDARY
HISTORIC PRESERVATION - ADO BUILDING OMMERCE ST BOULDER, COHISTORIC PRESERVATION1960 AD
BUILDING
ADDITION TO BE
DEMOLISHED
Attachment A - Applicant Materials
LEVEL 01
-2' -0"
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
OPERABLE WINDOWS
EXPOSED ROOF JOISTS
CLAY COLOR CMU
CLAY COLOR OPEN
CELL CMU WALL
LEVEL 01
-2' -0"
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
CLAY COLOR OPEN
CELL CMU WALL
CLAY COLOR CMU
STEEL REVEALS, TYP.
EXPOSED ROOF JOISTS
OPERABLE WINDOW, TYP.
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
CLAY COLOR CMU
OPERABLE WINDOW, TYP.
STEEL REVEAL, TYP.
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
CLAY COLOR OPEN
CELL CMU WALL
OPERABLE WINDOW, TYP.
EXPOSED ROOF JOIST
CLAY COLORED OPEN
CELL CMU WALL
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
CLAY COLOR CMU EXPOSED ROOF JOISTMECHANICAL EQUIPMENT ENCLOSURE
LEVEL 01
-2' -0"
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
CLAY COLOR CMU OPERABLE WINDOW, TYP.
SITE GRADING
EXPOSED ROOF JOIST
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
EXPOSED ROOF JOIST
CURTAINWALL, TYP.
STEEL REVEAL, TYP.
CLAY COLOR OPEN
CELL CMU WALL
PROFESSIONAL SEALS
DESCRIPTIONREVISION DATE
CURRENT DOCUMENT STAGE
PROJECT ABBREVIATION
CHECKED BYDRAWN BY
PROJECT NUMBER
ORIGINAL ISSUE
SHEET NUMBER
REVISION HISTORY
CITY APPROVAL STAMP
Page Southerland Page, Inc.
pagethink.com
TEL
FAX
ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING
Austin / Dallas / Denver / Dubai / Houston / Mexico City / Phoenix /
San Francisco / Washington DC / International Affiliate Offices
370 17th Street
Denver, CO 80202
303 595 0491
303 595 0282
BALL AEROSPACE AND TECHNOLOGIES CORPORATIONBOULDER CAMPUS1600 COMMERCE ST BOULDER, CO 80301HISTORIC PRESERVATIONELEVATION KEY PLAN A-900
11/1/2021
ADO
.
820015
.
AD & ADO BUILDING
(CONTROL CELLS)
EXISTING ELEVATIONS
SCALE:1/8" = 1'-0"A-900
1 EXISTING EXTERIOR ELEVATION - NORTH
SCALE:1/8" = 1'-0"A-900
2 EXISTING EXTERIOR ELEVATION - WEST
SCALE:1/8" = 1'-0"A-900
3 EXISTING EXTERIOR ELEVATION - SOUTH
SCALE:1/8" = 1'-0"A-900
5 EXISTING EXTERIOR ELEVATION - SOUTHWEST
SCALE:1/8" = 1'-0"A-900
6 EXISTING EXTERIOR ELEVATION - SOUTHEAST
SCALE:1/8" = 1'-0"A-900
7 EXISTING EXTERIOR ELEVATION - NORTHEAST
1
2
3
4
5
7
SCALE:1/8" = 1'-0"A-900
4 EXISTING EXTERIOR ELEVATION - NORTHWEST
6
ADO
AD
NORTH
TRUE
1 HIST. PRESERV. LAC 11/1/2021
Attachment A - Applicant Materials
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
GARAGE STYLE DOOR CLAY COLOR CMU
EXPOSED ROOF JOIST
OPERABLE WINDOW, TYP.
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
MECHANICAL EQUIPMENT ENCLOSURE CLAY COLOR CMU EXPOSED ROOF JOIST
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
EXPOSED ROOF JOIST
OPERABLE WINDOW, TYP.
CLAY COLOR OPEN
CELL CMU WALL
LEVEL 02
8' -0"
ROOF LEVEL
20' -2"
PROFESSIONAL SEALS
DESCRIPTIONREVISION DATE
CURRENT DOCUMENT STAGE
PROJECT ABBREVIATION
CHECKED BYDRAWN BY
PROJECT NUMBER
ORIGINAL ISSUE
SHEET NUMBER
REVISION HISTORY
CITY APPROVAL STAMP
Page Southerland Page, Inc.
pagethink.com
TEL
FAX
ARCHITECTURE / ENGINEERING / INTERIORS / PLANNING / CONSULTING
Austin / Dallas / Denver / Dubai / Houston / Mexico City / Phoenix /
San Francisco / Washington DC / International Affiliate Offices
370 17th Street
Denver, CO 80202
303 595 0491
303 595 0282
BALL AEROSPACE AND TECHNOLOGIES CORPORATIONBOULDER CAMPUS1600 COMMERCE ST BOULDER, CO 80301HISTORIC PRESERVATIONELEVATION KEY PLAN A-901
11/1/2021
ADO
.
820015
.
ADO BUILDING
(CONTROL CELLS)
PROPOSED ELEVATIONS
SCALE:1/8" = 1'-0"A-901
2 PROPOSED EXTERIOR ELEVATION - NORTHEAST
SCALE:1/8" = 1'-0"A-901
4 PROPOSED EXTERIOR ELEVATION - SOUTHEAST
SCALE:1/8" = 1'-0"A-901
1 PROPOSED EXTERIOR ELEVATION - SOUTHWEST
1
23
4
SCALE:1/8" = 1'-0"A-901
3 PROPOSED EXTERIOR ELEVATION - NORTHWEST
RESTORED TO ORIGINAL APPEARANCERESTORED TO ORIGINAL APPEARANCE
RESTORED TO ORIGINAL APPEARANCE RESTORED TO ORIGINAL APPEARANCE
NORTH
TRUE
1 HIST. PRESERV. LAC 11/1/2021
ADO
Control Cells Division, Southwest and Northwest Elevations (facing East), recently constructed, c.1956 Control Cells Division, Northeast Elevation (facing Southwest), recently constructed, c.1956
HISTORIC APPEARANCE HISTORIC APPEARANCE
CLAY COLORED OPEN CELL CMU WALL CLAY COLORED CMU WALL BROWN TRIM AT WINDOWS
Attachment A - Applicant Materials