5 - Handout - Technical Memorandum - Boulder Stormwater Strategic PlanLT~(~ I ONE COMPANY
1 1J.~ MeMy So[wtionr`
Technical Memorandum
To: Bob Har6erg, City of Boulder
Fran: Rich Thomton, Jerry Kenny- HDR Project: Boulder Slormwater Strategic Plan
CC: File
Date: February 22, 2007 Job No: 34640
RE: South Boulder Creek Lower Urbanized Storm Center - 700 year Flood Impacts
Introduction
The purpose of this analysis was to develop an order-of-magnitude understanding of the
potential flood impacts within the urbanized subbasins tributary to South Boulder Creek during a
100-year design storm event centered over the southeast portion of the city. This analysis is a
follow-up to the observations noted in the Hydrologic Impacts of Downstream Storm Centers
memorandum (HDR, February 24, 2005) which identified the potential for flood hazards
resulting from local, urban subbasin runoff during an extreme storm event.
Analvsis and Results
The analysis consisted of an evaluation of the basin hydrologic and hydraulic response to a
100-year rain event using the XPSWMM model developed for the Boulder Stormwater Strategic
Plan (SSP). The XPSWMM model developed for the SSP was developed for the analysis of the
city's collector system and as a result includes a more detailed assessment of subbasin
boundaries and local/collector conveyance elements. As such, there are minor differences in
the subbasin boundaries delineated for the South Boulder Creek (SBC) analysis and the SSP
analysis.
The South Boulder Creek Lower Urbanized Storm Center -100 year Flood Impacts analysis
approach and results are summarized in the following sections.
Hydrology
The rainfall depth and temporal distribution associated with a thunderstorm cell centered over
the South Boulder Creek C2 subbasin was entered into the XPSWMM model. Runoff
hydrographs were generated for the applicable subcatchments and then routed through the
collector storm drain and open channel systems. The resulting 100-year runoff peak simulated
in XPSWWM was approximately 1200 cfs. This runoff peak is slightly lower than the 1650 cfs
predicted with the MikeFlood model used in the SBC analysis. The slightly lower peak from
XPSWMM is attributed to runoff being routed through the collector storm drain and open
channel system thus attenuating the hydrograph peak.
~
Flood Risk Assessment
The XPSWMM model was developed for the collector system and used to evaluate the basin
response for relatively minor rairifall events (up to a 5-year design storm). As a result, it does
not provide an adequate, standalone tool to assess potential flood risk and flood hazard
damage. However, the XPSWMM model can be used in conjunction with the XP-2D module to
assess the combination of piped conveyance and surface flow conveyance. The XP-2D model
was developed to route surface flow that exceeds the capacity of the existing storm drain
system. In addition, where flow depths are greater than the open channel top of bank, overland
flow is also routed via the 2D model. Therefore, the potential flood risk was assessed at this
order-of-magnitude level using the XPSWMM/XP-2D model.
A simplified dataset was used for the XP-2D model development. Data for the XP-2D model
consisted of a digital elevation model (DEM) and an average surface roughness. Data such as
ineffective flow areas (e.g. buildings) were not used due to the large urban area the analysis
covers. In addHion, muliiple roughness factors accounting for different land use types and land
cover characteristics were not used, again, as a result of the large urban area the analysis
covere.
The 2D analysis was limited to the C2 sub@asin boundary. The City's (DEM) was sampled at
10-foot grid intervals and used as the DEM within the XP-2D model. The grid cell size within the
XP-2D model was limited to 65-feet due to the large analysis area and model license
requirements. As this analysis is intended to provide a general estimate of flood risk, the
relative{y farge cell size was deemed appropriate. An average surface roughness of 0.030 was
assigned based on the area consisting mainly of pavement, lawns, open space, and buildings.
Analysis results indicate shallow surface flow for a majority of the study area with depths equal
to or less than 1-foot as shown on Figure 1. There are locations where depths exceed 2-feet.
However, these locations are isolated in areas where the DEM identifies localized depressions
in the ground surface. These high inundation depths may be attributed to the accuracy of the
DEM or 2D grid size.
Flood hazard risk can be expressed by the product of overland flow velocity and depth. Typical
definition of low hazard areas is if the velocity-depth product is less than 4. Flood hazard maps
were produced with the XP-2D (Figure 2) and generally indicate low flood hazard risk across a
majority of the study area with risk values of less than 1. However, there are localized areas
where the risk value approaches 4. Speciflcally, there is a depressed area modeled in the DEM
southwest of the intersection of Foothills and US 34 and another location approximately 800-
feet southwest on the Viele Channel.
Given the assumptions used to develop tfiis model, it is anticipated that a 100-year
thunderstorm event centered over the lower subbasins of South Boulder Creek would produce
surface flooding on average less than 1.5-foot in depth. This 100-year inundation depth within a
collector system meets the City's level of service defined within the Design and Construction
Standards.
2-
Depth ~
, ~
4.00
3 56 I
3.11 ' ,~'~ . --- -
' -
2.67
2.22
. - ' ~ It
i.~e ~ - -~_._
1 ~___
1.33 _
..... . _-
_ 1
-
-
0.89
1 _
~J ~`~s~ H
'
0.44
~ ' 1
~'
- ,'=
0.00
- ~- ~
- -
ti
, ,
~ ,
i I
'~ '
~ I-
-- _~._~
\
~
, .., - __
C
~gure 1- Approximate Inundation Depths, 100-year Design Storm
Hazard t I
4.00
~ 3 56 i
~
I - - .- ; .
2.67
222 ; . . ~ ._ ~ ~
~
~
~
{ ~. r ~ ,
178
33
1 i 1.. _
!
._..
~ - ~
-
.
0.89
O.dd `~
~ ~~; `~~ ~
- f~ :
0.00
---~
-
- ~ R
- - --
~.. ., _ ~ •
I
I~ ~
.
_
, ,.r~ ~
- - _-
~
~..~ '~ i
'
~ _ ,
- _._ _ _ _ .
~! 'I
_
`
'
~^ ' ~
,
. . ;c •. ~ }! ~ ~~
~1
-
,r;: _ ~.
" - .fr.J _.^'.. I
I4"_ ,
Y
~ ~ ' ~;
~'~ .
- ~~
~
igure 2- Approximate Flood Hazard, 100-year Design Storm
-3-
waAa.~a~~ u.a
.i
~...y.._..
I
~ ~ ~~~=
f
~~
~.~' / ~.r.e o~
~ ak
~
r - ~
,~f~
~°
,
~~
~ ~: ~~~~
~. _~.
,~~
~
_ ~
,, , i
~ . .. \ N
\~ ~
' C3
~ ~ ~~ 0 1000
Leaend
Modeled network - Bear Carryon Creek - Elmers Twomile Creek I Kings Guich i South Boultler Creek
/~/ Pipes - Bluebell Canyon Creek - Fourmile Canyon Creek i Lower Boulder Creek ~ Twomile Canyon Creek
' CanaU Ditch _ pry Creek _ Goose Creek Middle 8oulder Creek - Viele Channel
/~/ Major drainageway - pry Creek No. 2 - Gregory Canyon Creek , _ Skunk Creek _ Wonderland Creek
Q SBC SubBasin
Figurr 3- South Boidder Creek and Stor~rn~ater Str~ttegc P(nn Subbas:ns
Property Affeetetl by AE antl X Floodplain Delineation
AE City Zoning
Zone Zone Acres Structures
RM-1 Resitlential-Medium 1 21.38 37
RR-1 Residential-Rurall 2720 38
RE Residential-Estate 54.64 160
RH-5 Residential-Hi h 5 33.52 18
RM-2 Residential-Medium 2 31.95 50
RL-1 Res~denGal-Low 1 46.77 34
RH-4 Residential-Hi h 4 7.54 3
P Public 194.29 11
E Enclave 24.96 32
IM Industrial-Manufactunn 5.86 3
RL-2 Residentlal-LOw 2 74.45 169
BC-2 Business-Communi 2 2.08 1
BC-1 Business-Communi 1 27.97 23
IS-2 Industrial-Service 2 3.65 0
BT-t Business-Transitional i 321 3
IG Indusirial-General 114.46 70
Tolal 674 652
X City Zoning
Zone Zone Acres SVUCtures
RM-1 Residential-Medium 1 423 10
RR-1 Residential-Rurall 0.87 B
RE Residential-Estate 23.71 99
RH-5 Residential-Hi h 5 13.67 19
IM Indusirial-Manufaclurin 28.35 31
RM-2 Residential-Medium 2 16.96 74
RL-1 Residential-Low 1 39.16 156
RH-4 Residential-Hi h 4 1.47 6
P Public 29.99 14
E Enclave 2.59 6
RL-2 Residential-LOw 2 95.72 479
BC-2 Business-Communi 2 0.28 0
BC-1 Business-Communi 1 568 17
IS-2 Industrial-Service 2 1.30 0
BT-1 Business-Trensitional i 8.03 14
IG Industrial-General 172.91 68
Total 385 1,001
AE County Zoning
Zone Zone Acres Struetures
A A riculWral 491.11 48
F Forest 0.52 0
C Commercial 3.59 10
LI Li ht Intlustrial 20.82 24
MH ManuNactured Home 6.11 ~ 80
GI Generellndusfrial 59.55 9
XBO Boulder 4.68 4
RR Rural Residential 646.80 257
ED Economic Develo ment 34.56 1
ER Estate Residential 16.42 24
T Transitional 0 95 1
SR Suburban Residential 25.81 25
B Business 1.64 2
Total 1,313 485
X Counry Zoning
2one 2one A~res SVUCtures
A A ricultural 61.98 5
F Foresf 0 32 0
C Commercial 0.00 0
LI Li htlndustrial 1.56 3
MH Manufadured Home 4.23 37
GI Generellndustrial 71.14 1
XBO Boulder 2 05 2
RR Rural Residential 103 56 724
ED Economic Develo ment 5.83 0
ER Estale Residenlial 10.82 27
C Commercial 0.73 1
SR Suburban Residential 26.39 26
B Business 172 10
Total 230 236
Grand Total 1.987 1,137 615 1,237
22 February 2007
PREP Summary Statement on the South Boulder Creek Flood Mapping Project
Climatology, Hydrology and Hydraulics Reports dated February 6, 2007.
The Peer Review Evaluation Panel (PREP) has provided a technical review of the
Climatology, Hydrology and Hydraulics Reports dated February 6, 2007 and are of the
opinion thatthe South Boulder Creek Floodplain Mapping Study meets, and in notable
ways exceeds, the accepted standards of engineering practice for floodplain mapping and
delineation. The effort is commendable in taking advantage of modem data from weather
radars and advanced state-of-the-art computer modeling of rainfall, flood runoff and two-
dimensional floodplain hydraulics. The customized Design Storm for the 100-year return
interval and related rainfall scenarios are considered to be reasonably representative of
the flood producing climatology for the Boulder area. The hydrologic modeling defines a
range of possible flood scenarios which could occur and the 2-D hydrodynamic modeling
provides a high level of detail in defining risks of flooding in east Boulder from South
Boulder Creek. We believe that the reports, supporting data and computer models provide
a scientific information base for deliberations on South Boulder Creek flood plain
management by the Ciry of Boulder and by potentially impacted residents. This opinion
is provided at a point in the study where the climatology, hydrology and hydraulics work
is essentially complete subject to some work to refine details of flood risks and to
respond to regulatory agency policies. The PREP does have some ongoing concerns with
these reports that are provided in an itemized list of detailed comments being provided to
the City.
Lynn Johnson, PhD, PE
Doug Laiho, PE
Gordon McCurry, PhD
Conveyance Zone Determination
Draf~ dated February 26, 2007
The Conveyance Zone identifies the area of the floodplain that should be preserved to
assure that flood flows are conveyed with minimal impact to adjacent properties. It reflects
the loss of floodplain storage and flood carrying capacity due to encroachment into the
flood fringe. Development activities and allowable uses within the conveyance zone are
generally restricted to reduce the hazard within this part of the floodplain. The criteria
defining the conveyance zone differ slighfly between the City and the County. The City
allows encroachment into the floodplain only to the extent that it increases flood water
elevations by 6 inches or less. The County allows encroachments that result in water surface
changes of up to one foot.
They hydraulic model used to simulate the South Boulder Creek floodplain is both fully
dynamic and two dimensional. That is, it represents the movement of water in a way that
accounts for backwater affects, floodplain storage and hydrograph variations as well as
allowing water to move in rivo dimensions. This is in marked contrast to a wnventional
steady state approach that assumes concurrent peak flows, dces not account for any
potential floodplain storage but dces consider backwater and only allows water to move
linearly down the channel. This fundamental difference in modeling approach significanfly
alters the approach to simulating the conVeyance zone.
A conventional evaluation of the conveyance zone encroaches into the floodplain from each
side in a way that equally reduces the conveyance azeas lost in the overbanks.
Encroachment continues until the water surface rise has reached a maximum depth of six
inches within the City or one foot in the County. Because the flow rate is constant, there is
no consideration of floodplain storage and flow moves in only one dimension, Hvs is a
relatively straight forward process.
In the fully dynamic, two dimensional representation, each encroachment has several direct
impacts on the water surface. First, the encroachment imposes a restriction on the potential
flow path and direcflon. Rather than merely constricting the channel, it may actually block
a primary flow path. Secondly, the encroachment may reduce the available floodplain
storage thereby actually increasing the amount of water that remains in the channel.
Finally, as the floodplain is encroached, water may be forced down new or different flow
paths further exacerbating the amount of flow that may have traveled down a previously
identified flow path. These ramifications, in combination, compound the impacts of
encroachment. These resulting complications make the automation of the encroachment
analysis exceedingly difficult. It was concluded that the South Boulder Creek two
dimensional analysis areas were unsuitable for automated conveyance zone determination.
Fortunately, the upper reaches of the South Boulder Creek model were represented using a
fully dynamic model but using one dimensional flow. While the impacts of reductions in
floodplain storage aze still seen, the relatively confined channel doesn t show much storage.
As such, the simulation was able to follow the equal conveyance encroachment approach
used in conventional models. The floodplain boundary was encroached until a maximum
change of one foot was identified corresponding to the standards imposed by the County in
this area. MIKE 11 (the one dimensional engine in MIKE FLOOD) has an automated routine
to establish these limits. After the automated limits were defined, some manual smoothing
and interpolation was required to assure that the one foot rise was not exceeded at any
locations along the channel.
Along the two dimension reaches of the simulation, a more iterative approach was taken.
Prior to initiating any sunulations, a fundamental question needed to be answered: should
the conveyance zone be limited to the main channel areas or should it include the west
valley as well. After considerable deliberation, it was concluded that, if possible, the
conveyance zone should be lunited to the main channel. This was the historic flow path and
should be favored over a disconnected alternative flow path. It was also noted that flows
didn t enter the west valley until approximately the 50-year flood and that a second
conveyance zone would formalize this unanticipated flow path.
Because of the two dimensional nature of the sunulation, no automated process for
conveyance zone delineation existed. It was necessary to define reasonable limits of
encroachment manually and test the assumption. To simulate the conveyance boundary,
the model bathymehy was physically changed to elevate the ground at the limits of
encroachment. This precluded water from flowing outside these boundaries. Because some
of the fributary inflows were introduced into the hydraulic model along the western fringe
of the floodplain, it was aLso necessary to redefine the location and character of inflows.
These were added to the two dimensional grid elements at the appropriate locations or into
channel elements that remained in the model. After evaluaflon, if the results did not
comply with the target water surface rise, refinements could be made and the sunulation
repeated.
As a starting point, the team engaged in discussions and attempted to define a reasonable
boundary based on judgement. The boundaries of the conveyance zone were encroached
considerably in the area near US 36 and in the reaches downstream to Arapahoe. The
conveyance zone was lazgely confined to the area immediately adjacent to the main channel.
The resulting sunulation showed major violations of the allowable water surface rise. Upon
review, several contributors to the exceedance were identified. First, the loss of floodplain
storage and the elimination of the overflow capacity of the west valley resulted in significant
increases in flow rates creating a fundamental rise in water surface. The encroachments
along roadways that were being overtopped also created major backwater impacts that
coniributed to exceedance. The encroachment also limited the ability of flow to move freely
across the floodplain and therefore several alternative flow paths were eliminated forcing
more water down the path along the main channel. In combination, this simulation was
deemed to have an unacceptable impact on water surface elevations.
The team recognized the difficulty of simulating a reasonable limit of encroachment was
going to be difficult using only the professional judgement of the team and their collective
experience. It was concluded that the next iteration should be based on a mathematical
encroachment and was set as being those areas where the floodplain depth was six inches.
It was hoped that this would eliminate those fringe areas where there was little active
conveyance and that the resulting conveyance zone would comply with the prescribed
water surface rise. Unfortunately, this analysis also exceeded the allowable rise
considerably. Afber review, it was concluded that two primary criteria resulted in the
exceedance: the necessary increase in head at roadway overtopping due to the
encroachment into the overflow areas and the loss of the floodplain storage resulting from
the elimination of those ueas less than six inches in depth. In combinaflon with the
introduction of the west valley flow, this presented an unacceptable rise and would require
further refinement.
It was concluded that one additional simulation would be undertaken in the hopes of
finding a conveyance zone that met the established criteria but restricted flows from
entering the west valley. Two major refinements were introduced in response to the
previous results. First, it was acknowledged that storage along South Boulder Creek was an
important characteristic of the floodplain and needed to be retained wherever possible.
Two major storage areas had been eliminabed from the eazlier conveyance zone sunulations:
the inflows into Baseline Reservoir were blocked and the storage near the interchange of US
36 and South Boulder Road was not incorporated into the model. The conveyance zone
boundary was adjusted to preserve both these important storage areas. The second major
adjustment was to broaden the limits of the conveyance zone between US 36 and Arapahoe
to allow water to move freely between flow paths across the main valley floor. This would
allow the increase flows that were introduced from the west valley to find the most efficient
flow path and minimize the water surface rise.
The results of this configuration were determined to be within the prescribed allowable
water surface increases of both the City and the County. While the rise at a specific pixel
within the model may have slighfly exceeded the allowable rise, discussions with FEMA
indicated that an approach that looked at the entire cross secflon in aggregate was
acceptable. This process involved defining cross sections across the conveyance zone and
establishing a computed conveyance zone water surface elevation across the entire cross
section. This elevation was then compazed to the base flood elevation and, if found to be
within the acceptable limits of rise, defined the regulatory conveyance zone water surface
elevation.
The attached figure defines the proposed regulatory conveyance zone.
Proposed Conveyance Zone
22 February 2007
PREP Detailed Review Comments
South Boulder Creek Flood Mapping Project
Climatology, Hydrology and Hydraulics Reports dated 2/6/07
The Peer Review Evaluation Panel (PREP) review of the current documents describing
the Climatology/Hydrology and Hydraulics documents was accomplished in accordance
with the following:
• The PREP "Mission StatemenY' dated February 28, 2004
• Editorial, typographic, grammar and format are not addressed except to the
extent that significa~t issues are involved
• Model input parameters, computations, etc are frequently outside of our view
and at a level of detail we can not review but for which we depend on the
consultanYs team QA/QC process to function properly
• The length of the documents and limited time made available to us to review
them did not permit a full re-read of these documents.
• PREP comments on the Climatology dated December 5, 2005
• PREP comments on the Climatology and Hydrology dated August 3, 2004
• PREP comments on the Hydraulics dated December 8, 2006
In view of the many in-progress documents and reviews that have been conducted over
the last three years, it is possible that some of the following comments have been
adequately addressed at a location that is not readily identifiable or remains to be
addressed in one of the documents. Please let us know where such items have been or
will be addressed or why they will ~ot be.
Climatology / Hydrology Report
1. Page 29, Section 2. Study team has provided an improved descriptioo of the updated
rainfall climatology (note concerns below). Use of the 100-year 6-hour rainfall
corresponds to the thunderstorm characteristics as determined through analysis'of the
expanded number of rainfall events. Also, using the thunderstorm avoids complexities
of a general storm flood runoff upstream of Gross Reservoir.
2. Page 34, Section 23. The use of an expanded radar-rainfall storm data set estabiishes
a rational basis for characterizing the storm climatology for the SBC. However,
assumptions on the design storm areal "footprinP' and its stationary placement are not
well explained.
3. Page 34. It remains unclear how the large increase in volume is due to changing from
a moving storm to a stationary storm. It would appear that the more volume is largely
due to many of the isohyets covering more area. As requested in Comment 8 of our
12/5/OS review memo, please describe in enough physical and numerical detail so that
the explanation is supported.
4. Pages 34-36 There is little comparison of the old and new storms in section 23,
leading us to question the section title or the missing comparison-related text.
5. Page 37, Section 2.4. The expanded number of storm events and statistical reductions
is considered to be an adequate basis for the design storm development.
6. Page 37, Section 2.4. The third criteria on page 31 for selecting past thunderstorms
used for this analysis limits the storms to those with less than 5 inches. This has the
potential to bias the storm duration and volume on the low side. More explanation
and justification to limiting the storm population should be provided.
7. Page 44, Section 2.4. Study team description of the selection of a stationary storm
placement rather than a moving system remains somewhat vague (D-37). The reasons
seem to be driven by the regulatory agency review comments and difficulties with
modeling a moving storm. (Text states that PREP agreed to this but we don'Y recall
that.). Explanation based on storm movement data is lacking.
8. Page 58, Section 6.2. The hydrology study approach to compare three independent
measures of flood frequency and magnitude - 1) standard flood frequency analysis of
the Eldorado gage flows, 2) paleo-hydrologic assessment of flood peaks and
locations, 3) rainfall-runoff modeling - is considered valid in general and represents
an advanced state-of-the-art for these kind of studies. While there are some
shortcomiogs, difficulties and peculiarities associated with each method, the
aggregate outcomes are confirmatory and yield flood peak and volume estimates with
moderate variability.
9. Page 61, Figure 34. The text needs to discuss the terms `weighted skew 0.6' and
`station skew 1.2' in terms of their meaning and significance. The dashed blue and
green lines on this figure need to be labeled or identified in the key. The text needs a
brief discussion on how the 90% confidence limits were developed.
10. Pages 63-65. A paleoflood investigation is a representation of what has happened in
the past and not necessarily "flows likely to be generated". Part of the value of a
paleoflood investigation is that it can provide information on floods that have
occurred outside of the period of gaged record or at locations with no gage; this point
is missed entirely. There is still no clear indication of specifically how this
information was used (e.g. a comparative reference to the paleoflood estimated peak
100-year flow and what meaning this has) and specifics are missing on how this work
helped define the spatial distributiou of large storms. Appendix F is an i~adequate
representation of the work that has been accomplished. We recognize that having a
better product may be outside of consultant team controi and suggest noting that this
section will be updated with the U.S.G.S. report when it is available.
11. Pages 79-80, Section 6.7.12. Calibration of the MIKE FLOOD model to the selected
historical events was limited by a lack of data for significant flood events. However,
the correspondence beriveen recorded and simulated floods is considered to be only
marginally acceptable based on the simulated results underestimati~g observed flow
volumes by 18.4, 14.6 and 33.1 percent compared to the study team's acceptable
threshold of 15% for the calibration storm events, as shown in Table 19. This likely
leads to an under-prediction of simulated flow volumes using the Design Storm. The
Hydraulics repoR should acknowledge this potential under-prediction of flows and
the City should consider this in its upcoming flood risk assessment and mitigation
activities.
12. Page 80, Section 6.7.13. It appears that the sensitivity analyses reported are for a
previous version of the model that had much lower flows. If that is the case, then the
text needs to clearly note that the sensitivity results are not for the version of the
model being used in the study.
13. Page 82, Section 6.7.14. The final paragraph of this sensitivity analysis on
Antecedent Moisture Content inconectly states the results of the `typical' values used
and those of the General Storm. The lower 95% confidence limit on the FFA flows at
Eldorado Springs are 3040 cfs while the sensitivity result for the general storm is
2770 cfs, based on information presented in Tables 16 (FFA flows) and 20
(Sensitivity results). The text should be revised accordingly.
14. Page 82. 080304 comment #32 and to some extent #34 - The description of the
operation of Gross Reservoir in the previous and current narzative is inconectly
represented. The phrase "....Gross could be at spillway crest levels any time during
the year...." may be true, but is misleading. In fact, Gross does not fill every year
and is rarely full during the time of the year when thunderstorms or general storms
typically occur. Furthermore, Gross may have a"limited impact" on major floods
originating from the new design thunderstorm, but is has and will continue to have a
significant impact on more frequent floods produced by general storms (e.g. the 1969
event). This is one reason why South Boulder Creek has rarely been out of bank in
the last 37 years, why the mean annual peak flow in a gage analysis of the full period
of record is so low and even why the consultant team has chosen not to use the period
of gage record after 1954. Please change this wording to represent the facts and
statistics. The current wording does not provide a correct ` justification" of a
modeling assumption. It would be better, simpler and more easily accepted to
describe the final decision on the reservoir level as being a well established policy
that the reservoir can not be used as a flood control reservoir in the model as it was
not constructed nor is it operated to provide that function.
I5. Page 83, Section 6.7.16. The text notes that significant localized trib~tary flooding is
possible under the scenario of downstream storm locations. The City needs to
consider this possibiliry in its flood mitigation efforts and the text should note this
concern.
16. Page 84, Section 6.8. A number of flood scenarios have been examined including the
selected "best estimate", the `bld" design storm, the transposed storms for the Big
Thompson and FoR Collins floods, and the comparison to the Taggert Study. Results
of these simulations yield a range of possible flood flows and inundation areas for the
South Boulder Creek flood plain. It seems that generally reasonable and rational
choices of these factors have been made by the study team, and that the overall study
represents an advanced state-of-the-art of professional practice for this type of
endeavor.
17. Page 85, Section 6.9. Definition of a°single" number which characterizes flood risk
is hard to pin down. There is inherent uncertainty in the complexity of
meteorological, hydrological and hydraulic processes; and in mountainous areas,
these factors can vary within short distances depending on topography, soils, and land
use. Lack of assessment of the uncertainty in the various components that result in the
predicted flows is a major shortcoming of the report. It is understood that some effort
is being directed to this topic which is highly encouraged.
18. Page 85, Section 6.9.1. The text needs to be revised to note that the simulated
General Storm falls below the 95% confidence limits of the FFA flows at the
Eldorado Gage, and discuss the implications of this underestimate.
19. Pages 87-88. While it is stated that the thunderstorm controls the 100-year flood, it is
also stated that the general storm controls floods occuning more frequently than the
25-year event. Is this because of the higher antecedent moisture conditions that
develop during a general storm? It needs to be made clear how this will be reflected
in the hydrology that is proposed to be the new basis for regulation?
20. Page 89, Section 7.0. The wording describing the PREP involvement implies that all
our comments are incorporated into the work. This statement must be changed.
While our opinions and recommendations have in most cases been incorporated into
the project, not all of them have been. We understand that the City together with the
consultant team has the final say on how comments are addressed. A simple
statement in the text that our opinions have been incorporated where judged
applicable would be sufficient.
21. Page 90, Section 7.0. The concluding sentence appears to refer to the incorrect table
of simulated flows (10 vs 24) and should be corrected.
22. Appendix D. This is an improvement over previous drafts in providing mote clear
explanations of the development of the design storm, flood frequency and related
topics.
23. Appendix G. The MIKE-FLOOD model is evidently an acceptable model to FEMA,
although documentation of FEMA acceptance has yet to be provided and should be
included as an appendix and/or posted on the City's project web page. Inclusion of
the MIKE User Guide as an appendix in the Climatology/Hydrology report does not
seem to be necessary and adds to the overall large volume of the report; it also could
be included separately on the City's project web page.
24. Appendix J. The QA/QC Appendix J is brief and barely adequate in describing
procedures for minimizing errors for the modeling study. However, through the
PREP's participation in a number of weekly teleconferences and various meetings
with the study team we acknowledge that the study team has employed state-of-the-
art methods for data collection, a~atysis, computer modeling and, more recently, error
checking.
25. Appendix L. The Storm Center discussion addresses the impacts of placeming a
design storm at other locations which result in local storm flooding greater than what
would be expected from the chosen design storm (which emphasizes main stem
flooding). The assessment is considered reasonable. It is understood that flooding on
the main stem of South Boulder Creek is the primary focus of the floodplain study.
26. Appendix M. The comparison of the MIKE FLOOD model with the Taggert swdy
modeling establishes some basis for comparison between so-called "standard"
methods and the MIKE FLOOD modeling effort. That effort mainly highlights the
differences that can arise given the basic assumptions of rainfall magnitude and areal
distribution. The SBC study effort is considered to be better founded on actual rainfall
climatology and basin conditions than the Taggert study, and therefore the results
obtained are considered more realistic of the flood threats to be expected.
4
Hydraulics Report
1. Page 1. It is considered that the South Boulder Creek study, particularly the 2-D
hydraulics modeling, exceeds the standard of practice typically applied for floodplain
studies. .
2. Page 22 and Appendix E. The sensitivity analyses are informative. Differences
between inundation areas for the range of roughness values aze difficult to discern
from the high resolution maps provided. However, lack of assessment of uncertainty
bounds is a major shortcoming of the report. It is understood that some effort is being
directed to this topic which is highly encouraged.
3. Page 26. The specific values of the smaller volume and the resulting discharges
should be mentioned.
4. Page 8 and Appendix C. Dry Ditch No. 2 was selected for inclusion as a 1-D model
component because its capacity was judged to be greater than 1000 cfs. In the model
runs does this channel carry 1000 cfs ar more? How does Dry Ditch No. 2 get
through the US36/S. Boulder Road intersection? It is not listed on the table of
blockages (pg GS).
5. Page 8. The location and significance of water flowing out of the 2-D grid (such as
into Baseline Reservoir) remains inadequate{y addressed.
6. Page 8.Locations of drainage channel features identified in text are not shown on
accompanying figures. Where is Viele Channel? An overview map of drainage
features with notations of all features mentioned in the text should be provided
7. Page J-6, roughness values in figure do not match values in text.
8. Page J-9. The figure on page J-9 appears to be out of place. Also there is no link to
High Hazard information of web site.
9. Appendix A. The report does not cite the link to FEMA testifying that the MIKE
models are fully acceptable; this needs to be included.
10. Appendices C, D and E. Appendices clarify a number of questions on hydraulic
model parameter selections and rationales for these. The Appendix A- MIKE
FLOOD Documentation - is long (~800 pages) and should not be part of the report
placement on the City's project web site would be adequate.
1 I. Appendices F and I. The appendices F(Floodplain Zone Definitions and Island
Determination) and I(Flood Insurance and Regulatory Implications) are informative
additions to the SBC study reports, and provide valuable guidance to citizens in
understanding the nature of flood plain regulations that may apply to their properties.
12. Appendix D. The calibration/ground-truthing effort using aerial photos of historic
flooding and citizen recollections is understandably limited in accuracy. However, the
effort is perhaps the best that can be done and does provide some guidance in
assessing the hydraulic modeling results.
13. Appendix G. (Floodway/Conveyance Zone) describes the procedures being
developed to define the conveyance zone. It is understood that there are policy
directives from FEMA which dictate these procedures. However, the assumptions
requiring all flow volume to be funneled through the conveyance zone negates the
influences of flood plain storage (occurring mostly in reserved open space) which
greatly reduces the channelized flood volumes. Thus the conveyance zone will be
required to be large in comparison with modeled flood flows associated with the
regulatory flood plain delineation which is based on the 2-D hydraulic model.
14. Appendix I. It needs to be made clear that there are islands, whether they are shown
or not, and how they ue to be handled from a regulation standpoint. Members of the
impacted public may feel that the study may be limited in value if they need to appeal
or process a LOMA.
15. Appendix I. The extensive use of this Zone X and the variety of flooding conditions
that can result in mapping an azea as Zone X are well described, however, the precise
manner in which this zone will be regulated should be more completely described.
16. Appendix J. Although brief, Appendix J on hydraulic modeling QA/QC procedures is
a valuable addition to the study and describes the types of interactions (e.g., field
visits) between the consultant and city staff in explainiug and selecting hydraulic
modeling parameters.