HomeMy WebLinkAbout5 - Introduction of the Wastewater Treatment Plan (WWTP) Strategic PlanCITYOFBOULDER
WATER RESOURCES ADVISORY BOARD
AGENDAITEM
MEETING DATE: January 22, 2007
AGENDA TITLE: Introduction of the Wastewater Treatment Plant (WWTP) Strategic
Plan
PRESENTERS:
Ned Williams, Director of Public Works for Uulities
Robert Harberg, Utility Planning and Project Management Coordinator
Floyd Bebler, Coordinator of Wastewater Treatment
Randy Earley, Engineering Project Manager
EXECUTIVE SUMMARY:
The attached draft Wastewater Treatment Plant (WWTP) Strategic plan is presented to
the Water Resources Advisory Board (WRAB) for comment and review.
The Facilities Plan, prepared in 1990, and the Utility Plan, revised in 2002, were the ]ast
planning documents addressing [he WWTP needs. This strategic plan has been prepared
to bring the wastewater utility planning documents into the new city master plan
framework. The wastewater treatment utility will eventually have a single, utility wide,
master plan. This strategic plan is intended to inform the Wastewater Utility Master Plan
on issues related to wastewater treatment. The draft strategic plan is based upon existing
documents including the Utility Plan submitted to the Denver Regional Council of
Govemments (DRCOG), the Community Environmental Assessment Process (CEAP) for
the WWTP Liquid Stream Improvements project, the CEAP for the Solids Handling
Improvements project (both now in various phases of construction), and updated
population projects.
This agenda item requests a review of the plan by the Board and comments on how to
improve the draft plan. The draft plan will be revised based upon comments and ideas
received within the next month and presented to the WRAB at a future meeting, possibly
the March meeting, for acceptance.
Fiscal Impacts:
Budgetary: The plan itself has no budgetary impact. Funding for the first phase
of the construction cited in the plan is in place. Additional funding will be
required to carryout the second phase of the construction. The Capital
AGENDA ITEM # V PAGE 1
Improvements Project (CIP) budget includes $18,500,000 of improvements in
2010. Future funding of additional construction will probably require additional
user rate increases. •
Staff Time: The impact of the future potential improvements identified on staff
time is unknown at this time.
Other Impacts:
The potential future projects identified in the plan generally improve water quality
in Boulder Creek, protect downstream water users or reduce local impacts from
the treatment facility. The potential future improvements will keep the plant in
compliance with its discharge permit and local requirements.
Economic: The future projects could potentially result in unbalanced social
impacts because lower income customers would be dis-proportionally impacted
by any rate increase.
Community: The impacts depend upon the improvements selected. Far example,
residents in close proximity to the facility could have fewer odors and noise if
noise and odar treatment components are required in future work.
Other Board and Commission feedback: The strategic plan is in draft form and it has
not been presented outside the city staff to the public or other Boards.
Public feedback: None received as yet.
Staff recommendation: Staff recommends that the WRAB review the strategic plan and
provide comments and questions to improve the document and make it more
understandable and useful for future planning.
Analysis:
In most communities WWTP improvements are driven by growth and regulatory
requirements. However, Boulder's growth limitations have minimized the impact of
growth as a`driver' of plant improvements. Boulder's WWTP improvements are
typically driven by regulatory requirements included in the Colorado Department of
Public Health and Environment (CDPHE) issued discharge permit. The discharge permit
focuses on reducing impacts of the wastewater discharge to the aquatic habitat and
protecting downstream water uses.
This strategic plan addresses the improvements to the existing facility required to meet
the 2003 discharge permit limits. The plan also attempts to conservatively estimate
improvements required to meet more stringent discharge permit limits that will likely be
associated with the 2009 permit renewal. The plan presents some future decisions that
will be vital to the WWTP facility's continued success in meeting regulatory
requirements and the Boulder Valley Comprehensive Plan Goals. The strategic plan
demonstrates the approach that has been used to keep the W WTP in compliance with
regulatory requirements and meet community objectives.
All the potential second phase and future improvements presented here will require a
CEAP and, probably, a Boulder County 1041 `Matters of State Interest' review and
AGENDA ITEM # V PAGE 2
approval. As previously mentioned, this plan will be incorporated into the Wastewater
Utility Master Plan.
WRAB can comment on the draft plan either at the Jan. 22 WRAB meeting or by e-
mailing comments to earleyr@bouldercolorado.¢ov. This will enable the draft to be
edited prior to final presentation at an upcoming meeting in which the WRAB will be
asked to accept the draft as a Strategic Plan for the WWTP. The acceptance of the
revised strategic plan will move the utility toward conformance with the business plan
model the city of Boulder has adopted as a framework for master plans.
Attachments
• Attachment A: City of Boulder's Draft Wastewater Treatment Plant (WWTP)
Strategic Plan
AGENDA ITEM # V PAGE 3
G~~Y °t ~u1ry~~
Attachment A: /
Draft Wastewater Treatment Strategic Plan ~~ •,~J,:,/~`
~ ~
T~
Executive Surnmary:
The purpose of this strategic plan is to document past decisions, the facility today, to
present the approach that has been used to reach decisions on process selection and
introduce some future decisions that will be facing the utility. To continue to provide the
level of service required by federal regulations and match the expectations of the
community presented in the Boulder Valley Comprehensive Plan Goals, ongoing
improvements to the treatment facility are necessary.
This strategic plan wil( be a component of a utility wide Wastewater Utility Master Plan.
The City of Boulder's most recent wastewater p(anning documents were the 2002
Utilities Plan and the 1990 Facilities Plan and the more recent Collection System Master
Plan was completed in 2003.
The City has adopted a new framework for City departmental planning documents since
these documents were prepared. The new framework includes a single master plan for
each of the three Utilities; Water, Wastewater, and Stormwater and Flood Management.
Strategic plans will address the major categories of each utility. For example the
Wastewater Utility Master Plan will include sections on the collection system, the
treatment system, and water quality that will be informed by strategic plans on those
components of the utility. The following graphic illustrates the hierarchy of the City's
Wastewater Utility master plans and strategic plans.
City Wastewater Utility Planning Documents
Wastewater
Utility Master
Wastewater Water Quality
Treatment Strategic Plan
5trategic Plan
Wastewater
Collection
System
Strategic Plan
The existing treatment facility includes a trickling filter - solids contacting secondary
process. This secondary treatment process is being upgraded to an activated sludge
process in the Phase 1 improvements project currently under construction. Phase 1
improvements will also include a dissolved air floatation thickener to thicken the solids
produced in the activated sludge process and solid handling improvements. These
improvements, when put on line in early 2008 will allow the effluent to meet the limits in
the 2003 discharge permit. The application of the new limits in the permit has been
January 16, ?007
G\`Y of Boulryer
Attachment A:
Draft Wastewater Treahnent Strategic Plan ~,~},~~. J~
J~
delayed by a compliance schedule intended to allow completion of the new secondary
process construction needed to meet the new limits.
The Phase 2 construction, currently planned for 2010, will include any process changes
needed to meet permit limits in the 2008 permit. Additional, it may include noise and
odor control units, a W disinfection system, and solids stabilization (anaerobic digester)
improvements. The components of the Phase 2 project are still speculative at this time.
The 2008 permit will again drive the facility needs in the Phase 2 project to a large
extent. The 2008 permit could contain requirements for nutrient(s), nitrogen and/or
phosphorus, removal that would require additional treatment processes that would have to
be included in Phase 2 conshuction.
The Colorado Department of Public Health and Environment (CDPHE) issues renewed
dischazge permits to the city every five yeazs. Federal requirements developed by the
Environmental Protection Agency (EPA) are incorporated in the permits. Wastewater
contaminates that may be regulated in the future include endocrine disrupters and
disinfection byproducts (DBPs). Endocrine disrupters have been shown to past through
the plant untreated and DBPs are formed in the disinfection process. Although we aren't
sure what the future permit requirements will be, dischuge permits will continue to be
the primary driver for wastewater improvements in the future.
January 16, 2007 Z
Attachment A:
Draft Wastewater Treatment Strategic Plan
INTRODUCTION
Background
G..y ~t Bo Wae~
h''" .~'' ~
~ ~
~
The City of Boulder 75°i Street Wastewater Treatment Plant (VUW'I'P) is located at 4049 N.
75`~ Street in the SW 1/a of Section 13, T1N, R70W, Boulder County, Colorado. Treated
effluent from the W~WIP is discharged to Segment 9 of Boulder Creek The WW'I'P is
defined as a major facility and operates under a Colorado Discharge Perniit System (CDPS)
perniit (Number CO-0024147) dated February 1, 2003, which expires on January 31, 2008.
The WV~'I'P is being upgraded to meet future wastewater treatment capacity demands and
new ammonia nitrogen limits that were incorporated in the C~PS permit. The upgrades
include improvements to both the liquid stream treatment and solids dewatering processes
(Phase 1). The WWTl' improvements currently under construction (Phase 1) will increase
the treatment capacity to 25.0 million gallons per day (MGD) on a maximum month basis
and provide the capability to reduce ammonia nitrogen concentrations in the wastewater to
levels below that required by the 2003 discharge permit. The Phase 1 improvements will
also keep the total nitrogen discharge at or below it's current level.
January 16, 2007
CITY OF BOULDER 75TH STREET WASTEWATER TREATMENT PLANT
Attachment A:
Draft Wastewater Treatment Strategic Plan
G~r{ ~ B0~'er
,~,~~'
~~ ~
In addition to the liquid stream improvemenu, the solids dewatering process is being
improved to handle increased solids from the liquid stream treatment process and to reduce
the volu~ of de-watered solids that must be transported from the W WI'P site.
It is anticipated that Phase 2 improvemenu will be implemented in 2010 in response to:
• more stringent Q'DS dischazge pernut limitations in 2008,
• the desire to replace the existing chemical disinfection (chlorine and sulfur dioxide)
process with an ultraviolet (iJ~ disinfection process,
• and the need to address biosolids stabilization (digester capacit}~ limitations.
Pu~ose of Strategic Plan
This strategic plan describes how the current W WTP improvexr~enu were selected, how they
will establish the City of Boulder as a proactive environmental stewatd with regards to water
quality preservation, and how these improvemenu will position Boulder to meet anticipated
future wastewater treatment requiremenu. The plan aLso presents:
• The curnent W WTP improvemenu and how they conform to Ciry and County
policies and goals;
• A comparison with historic operations;
• The economic impacu of the current WWTP improvemenu;
^ The implementation plan for current improvemenu (I'hase 1);
^ Strategies for x~asuring system performance; and
• Anticipated future requiremenu and implementation plan (Phase 2)
CLJRRENT SITUATION
Meedng the needs of the community
The existing W WTl' is not capable of treating wastewater w the level required to comply
with the 2003 dischaige permit require~nu for ammonia removal. But the city has been
issued a compliance schedule to allow construction of the new unit processes before those
limiu go into effect. In addition, the eatisting plant rating for oxganic material" (Biochemical
Oxygen Demand) removal is not adequate to treat the increasing organic loads. The existing
WWTP capacityis adequate to meet the needs of the existing community; however, it is not
adequate to treat the wastewater generated by anticipated population and employment
growth in the Boulder wastewater service area.
The W~WTP serves the nine sub-communities of Boulder's wastewater utiliryservice area
(WU3A) depicted in Figure 1.
Jar,,,~y ib, zaa~ 4
Attachment A:
Draft Wastewater Treatment Strategic Plan
G```I of Baulaer
,''' ~'!y'.~
~ ~
~
FiQUre 1. Mav of WUSA Area (WLJSA area denoted by red line
_
~
w
rn
a'~
~ Gunbarrel
~\~r
a~
^
~o
a
~~
North Boulder
~ay Road
~
Palo Park ~
VWVf P ' '~ ~
~
Valmont Road ~o
~
C rossroa s
Central Boulder
East Boulder
Arapaho e Road
olorado Universit
Southeast Boulder Basel ine Road
South Boulder Road
South Boulder
h~wy `?6
Boulder's population and employment continue to grow with the population expected to
reach 128,162 by 2025 based on a revised estimate of Denver Regional Council of
Governments (DRC~G) projections. The Boulder Valley Comprehensive Plan (BVQ')
population and employment growth expectations are similar. The wastewater treatment
planning documents must use DRCOGs population projection when submitting plans and
applying for state level approvals for facility improvements.
The BVQ' has recently been revised to include population and employment projections
through build-out of the service area. The build-out population is expected to be reached in
2030, but no specific year has been assigned to the employment build-out projections.
January 16,1007
G~r{ °~ ~~'e~
Attachment A:
Draft Wastewater Treatment Strategic Plan ~,~y,~,~~y J~
J~
Thi+oughout the planning period, population and employment esricnates from DRCOG
closely follow estunates from the BVQ'. To keep the values consistent with each other, the
employment estixnate value from DRCOG in 2025 has been recalculated to reflect the
BVQ' build-out projection.
The revised values represent a population projection increase of approximately 7,000 people
over previous projections for the year 2030 and an employxnent increase of approximately
23,000 employEd persons. Boulder population projections from DRCOG and the BVQ' are
shown in Table 1.
Table 1. Ponulation Summarv and Pmiection for Areas I& II ( W[JSA)
Pro'ected Po ulation
Souice 2000 2001 2005 2010 2015 2020 Build Out
BVQ' 106,200 109,180 112,160 115,140 118,120 121,100 129,878
DRCOG Anal is -- 106,614' 109,412 112,341' 116,121 119,500' 128,162
lOriginal esamau provided by DROOG
zEstimate based on revised BVQ' pmjectioas
Employm~ent values and projections from the BVQ' and DRCOG are summarized in Table
2.
Table 2. Em lo ent Summa and Pm'ection for Areas I& II WUS
Pro'ected Em lo ent
Souree 2000 2001 2005 2010 2015 2020 Build-
out
BVQ' 101,000 109,260 117,520 125,780 134,040 142,300 167,564
DRCOG Anal is - 106,407 111,0621 119,656 125,228 130,7211 155,921
1 Original es[imate provided by DRCOG
zEstima[e based on revised BVQ' projections
Based on historical values of 102 gallons of wastewater genented per capita per day and 50
gallons of wastewater generated per employEe per day, an additional flow of approximately
1.1 MGD are anticipated as a resuk of the changes in population and employment
projections. This also represents an additional loading of approximately 2,130 pounds of
five-day biological o~cygen demand (BOD~ per day. This represenu an increase of 4.4% in
the design flow and an increase of 7% in BODS design loading. These increases are
generally within the range of accuracy of the initial flow and load projections and therefore
are considered to have no significant impact on the capability of the upgraded wastewater
treatment facilities to handle the projected flows and loads.
The eatisting facility is designed to treat 20.5 MGD; however, the projected capacity
requirement to meet the 2030 population and build-out employment is approximately 25
MGD. Industrial flow projections are estixnated to be 6% of the total annual flow based on
the 2000 and 2001 significant industrial user flows of approximately 0.97 MGD.
Figure 2 shows existing WWTP capacity (20.5 MGD) versus projected flows.
Jaz,,,~y ib, zoo~
Attachment A:
Draft Wastewater Treatment Strategic Plan
G.~V ~t Bourae~
and
Treatrnent Canacitv
2s --- . ~
2s
b
E
24
3
0
w 23 - -
~
~ 22
3
0 21
~
-------- ---------
x
,
, 20
~
- -
19 - --
~
18
2000 2005 2010 ZO15 2020 2025
t DROOG buttl Muc. Month F1ow, mgd ((Average bued on population a[ 102 gpcd, cmployment at 50 gpcd, and SIU flow at 6%) x 1.2)
-+-- BVCP based M:ix. Month Flow (Rased on Census), mgd ((Average based on population at 102 gpid, employment at 50 gpa~, and SI U flow a[ G°k~) x 1.2)
- - -ExistingTreatmentCapadty,mgd II
_ ~ , ~i~., . .. ~ ~, :_ ~, i~ ~~ ~~ ° ~
_ _
If population values increase beyond those predicted (as shown in Tables 1 and 2) the
VUW'I'P will not be able to provide adequate treatment capacity. In that case, treatment
capacity needs will have to be re-examined before the expected build-out date of 2030, and
additional expansion of the WWTP capacity may be required before that time.
Strengths of Existing Wastewater Treatment System
The e~sting WW'IT' liquid stream system includes a"Trickling Filter/Solids Contact"
process that has been operational since 1989. The existing system is shown schematically in
Figure 3. Over the past 18 years the facility has generally met the demands of City residents,
maintained permit compliance, and has discharged satisfactorytreated wastewater, or
effluent, to Boulder Creek For clarification, the liquid stream processes treat the wastewater
removing ~ontaminates and the solid stream processes treat the solids removed from the
wastew~te~.a~d the solids generated by the liquid stream process.
Weaknesses of Existing System
The two primary drivers motivating the current WWTP improvements (Phase 1) are new
ammonia nitrogen discharge limits and increased wastew~ater flow. The existing faciliry, as
shown in Figure 3, will be unable to reduce ammonia nitrogen in the wastewater to the level
required by the 2003 discharge permit, the rated BOD capaciry is routinely exceeded and it
has insufficient capacityto treat the projected wastewater flows.
January 16, 2007 '~
G\,Y o~ Bourcyer
Attachment A: i
Draft Wastewater Treatment Strategic Plan ,~y, %~'
~~ .~
The improvements will allow the WW I'P to treat projected flows and loads through 2030,
treat the wastewater to the level required to meet the 2003 discharge pernlit requirements,
provide more operational flexibility, and increase equipment efficiency.
Fi~ure 3. Schematic of Existing WWI'1'
. ~ ~
~„ ,.. ,.... , . ' Q ,~.,, Q ,,. 4 . . ',
_ "Q . ,,. ....
`~ ~~~- - F.. ~ ~Q Q' ' 4 ,
* 4 -t, 4 Q i~
~ _4
,.
RELATIONSHIP OF THE WASTEWATERTREATMENT IMPROVEMENTS
TO CITY AND BOULDER VALLEY COMPREHENSIVE PLAN (BVCP) GOALS
Both the City of Boulder and Boulder County desire to maintain their proactive status
regarding environmental stewardship. Consequently, they have established goals in the areas
of sustainability and environmental quality. By meeting the objectives of the planned
process improvements, the Boulder WW'TP will also meet several City and County
environmental goaLs. Relevant City and County goals are listed below:
• Improving and protecting water quality;
^ Reducing waste by improving recycling and reuse of biosolids;
^ Protecting the general health and safety of plant workers;
^ Meeting future wastewater treatment capacity demands; and
^ Creating a sustainable community through;
o Improved energy efficiency,
o Minimization of greenhouse gas emissions,
o Cost savings, and
J;uwary 1G, ?GO' 8
G``y ot Baulae~
Attachment A: /~
Draft Wastewater Treatment Strategic Plan ,~y /`
~~ ~
~
o Minimi7.ing chemical usage.
Improving and Protecting Water Quality
The Colorado "303 (d) List" is a list of surface waters within Colorado that are considered
"impaired" with respect to the water quality required for their intended uses. The 2000
Colorado 303 (d) List identifies Segments 9 and 10 of Boulder Creek as being impaired for
aquatic life due to elevated unionized ammonia. The list identified municipal WW I'Ps and
possible non-point sources of ammonia as the cause of impaument. This listing necessitated
implementation of an ammonia Total Maximum Daily Load (TNIDL) study, which
subsequently dictated the ammonia nitrogen limit contained in the Boulder Colorado
Discharge Permit dated February 1, 2003 is in effect until February 2008. Although the
pernut does not place limits on specific nutrients, the City of Boulder recognizes the need to
put mechanisms in place to ensure that anticipated future nutrient limits can be met with
minimal additional construction. The ammonia limit, and potential future nutrient limits, will
contribute to the protection of aquatic life in Boulder Creek. Figure 4 presents an image of
Section 9 of Boulder Creek and the location of the Boulder WW'I'P.
Figure 4. Segment 9 of Boulder Creek and the Location of the Boulder WV~I'P
N r °LJ }J
~
'~ "' •
\ ~
Longmont
~
/i\ ~ •~
~ ` %
_~
I
,
l
~ 1
l i~
~
/
' 't' /
d
~ -1' = i'•.~Il;l ~
O~ . ~.. l;? (
~ Niwot ~ ,'
r~ `\ ~,
' ~,,
~ ,
'~'_ Bi. ~
0
~ t ,
:-ii Rnnldw Rw.nro~~
'
~y
, e~.,~.i ~
~1
~
'
'
ii/~. R
TP ~ -~.j'
~ Bonlder'Sr4 \~
ill
ir~~
:
r • SItMl1'I~TP .+.
~;~illl~~~~i ~
,,
~
J `~•s - ~ ~~ ~ -
Erie °~
~ o e ~'
~
~ x~o~~~
~,uu~ ~
".,oJ 1 il. oul er
/, ~~ ~
1
~_.ti~ `_ / 0 (>
~~ M)Ane
~ ~.
~
~
~,
~
rc,7ti~~
` -
~].
~ ~~v~' . Lafayette
~e 4
~~)iIl
1~ ~`...,. f.k
. ~ G ~
~ M1~,
~~I~ ~g~,
aR n ~
.,
, ~f '~,~ .~,
~ r
, ~1
Selp~flof "-
January 1G,'007
G``y of Boulae~
Attachment A: ~~
Draft Wastewater Treatment Strategic Plan ~,~„%~`
~~ , ~
~
Current improvements to the WW'I'P (Phase 1) will allow Boulder to discharge water of
substantially higher qualiry than the 2003 discharge pernut requires, while also achieving no
net increase in the total amount of nitrogen discharged to Boulder Cxeek. By complying with
permit's limits, the water discharged from the Boulder WWTP will improve the water quality
of Boulder Creek to a level that will protect downstream users and support aquatic life.
Figure 5 presents WWTP effluent constituent concentrations that must be met to ensure
compliance with the 2003 discharge permit.
5. C;urrent ~ttluent Limits tor Jelectect c:onsatuents~~
are basea on
'rEttective until January3l, 2008
"~'"''The ammonia nitrogen value shown is the annual average. Regulatory limits vary monthly and range from
10.9 to 16.9 mg/L. Effective January 25, 2008, the TMDL-based ammonia limits come into effect resulting in
a limit of 53 mg/1 for March, the most stringent month.
Reducing Waste and Improving Recycling and Reuse
The cit~s WWTP represents the one of the biggest investments and efforts the city
continues to make ot reduce and recycle waste generated by the city.
The upgraded liquid stream treatment processes and the anticipated increase in wastewater
flows at the WW'I'P are expected to increase solids production by 25 to 30 percent. The
solids dewatering improvements are designed to treat this new volume and to remove
substantially more water from the solids than has historically been the case. By reducing the
amount of water in the solids, the volume of material removed from the WWTP will
decrease by nearly 50%, resulting in reduced hauling costs and associated fuel usage, and
disposal costs. Figure 6 presents a comparison of the existing and anticipated volume of
biosolids generation as dry tons per day (dtpd).
January 16, 20D7 1 p
G\`y pt BoWprer
Attachment A:
Draft Wastewater Treatment Strategic Plan ~~` ,~y, /~`
~'~y ~..~
~
[in looking at this chart, are we saying that it is "new liquid stream process at buildout" plus
"new process with dew~atering improvements"??]
Solids generated in the wastewater treatment process will be anaerobically digested,
dewatered, and used as a soil amendment on agricultural lands on Colorado's eastern plains.
Alternatively, the solids could be used by a private fum on a contract basis for landscape
amendments or other uses.
Protecting the General Health and Safety of Plant Workers
There was no work time lost from on the job injuries during 2005. The planned
improvements will provide improved working conditions and reduce exposure to hazardous
chemicals. The upgrades will replace old and outdated equipment with newer equipment
that will require less maintenance and reduce potential for possible injury associated with
operation. This will provide a safer environment for plant workers and for the surrounding
neighborhoods and natural areas and will help maintain baseline conditions of zero injunes.
Meeting Future Demands
The population of Boulder is expected to grow to approximately 128,160 people by 2030
and the number of people employ~d in Boulder to increase to approximately 155,920. The
e~cisting facility is not equipped to treat the volume of wastewater generated by this projected
growth, subsequently; an increase in treatment capacity from 20.5 to 25 MGD is needed.
After the Phase 1 improvements in place, the facilitywill meet these future demands.
G~y ot Bou/u'e~
Attachment A:
Draft Wastewater Treatment Strategic Plan ~~y,'~
a~
Creating a Sustainable Community
Sustainability in wastewater treatment is achieved through resource conservation, recy~ling
and waste reduction. Resource consumption will be minim~~pd through proper process
selection, use of eneigy efficient equipment, and operational process optimization.
Prunaryissues of concern include:
^ Eneigyusage,
• Greenhouse gas genention,
~ Cosu, and
^ Chemical usage
Energy Usa~e
Although the eneigy efficiency of the new plant equipment will be greater than that of the
older plant equipment, overall eneigy consumption is expected to nse due to the higher level
of treatment provided and the anticipated higher wastewater flows. In evaluating higher
level treatment alternatives, additional enexgy usage was considered to be an acceptable
tradeoff when evaluated against increased chemical usage.
In addition to the criteria listed above, the Gty is incoxponting I.eadeiship in Enetgy and
Environmental Design (I.EED) concepts into the design of the new dewatering facility.
Facilityupgrades will improve enexgyefficiencyin several ways:
• I.ess fuel consumed
o The mileage associated with hauling of solids offsite will be decreased by
approximately 50%.
o The anticipated replacement of chemical disinfection (chlorine and sulfur
dioxide) with UV disinfection (Phase 2) eliminates the fuel consuxnption
associated with the manufacture and transportation of these chemicals.
~ Electricityconsumed
o Improved eneYgy efficiency of newer equipment will reduce energy waste in the
liquid stream and solids dewatering processes (however, due to eneigy demands
of the new activated sludge process, electrical energy usage is expected to
increase~.
^ Energyproduced
o Increased production of solids will result in more methane production as
wastewater flows increase.
January 16, 2007 ] 2
G,,y pt Bo~l~/er
Attachment A: ~~
Draft Wastewater Treatment Strategic Plan ,~y-,,%~~1~'
'~~ _, '~,
~ y~
Tti
Figure 7 presents data on enecgy usage of e~sting system.
Fi ure 7. Ene Usage
~
20000
a
0
.~
v
~
b
~
15000
-
~
~.
0
~
0
.p
~
~
10000
-
~
a
C~J
a~'n
~. 5000 -
~
W
~
0 _ , _ ; - ~
Fuel Energy Electricity Natural Gas
Consumed'` Produced°~- Consumed~~'~~ Consum~d ~ ^~
(gal) (KWh) (MWh) (NIlVIBtu)
yBased on 2004 data; 2005 data represented an atypical year due to digester cleaning
'~'~Based on 2005 data; 2004 data not available.
Greenhouse Gas Generation
The City of Boulder participates in the Cities for Climate Protection Campaign, an
agreement between U.S. cities that calls for a reduction in greenhouse gas emissions
equivalent to those identified in the Kyoto Protocol. Improvements in energyusage and
reduced fuel consumption lower the WW'I'P's greenhouse gas emissions; however increased
solids production creates more methane gas, one of the s~ primary greenhouse gases.
Costs
WW'1"1' operating costs are based on:
^ Fuel consumption
^ Enetgy usage
^ Chemical usage
Janu~~y ir~, ~oo~ 13
G`\'9 01 Boura~,~
Attachment A: ,
Draft Wastewater Treatment Strategic Plan ~~,~y, ~~~
~`~" .;~`'
^ Equipment costs
^ Personnel costs
The improved wastewatertreatment processes will be more efficient in manyways, and
therefore, some operational costs are expected to be reduced. A considerable portion of the
2005 budget was spent on repair and rehabilitation work at the e~sting WWTP. In addition,
biosolids recycling costs increased by approxirnately 10% and chlorine costs increased by
25% in 2005. Overall upgrades to the treatment process are expected to m;nimi7~
maintenance and repair costs, however, because the new process will be treating the
wastewater to a higher level, some additional costs will be incurred. Figure 8 presents
various expenditures from the existing W~jU'TP.
8. Summarv of ExistinQ WV~I'P Costs
25
20
~
~ 15
8
~
u5~~
76 10
.5
~
h
~
contractor hat~led biosolids loads and an efficiency4 mpg.
Chemical Usa~e
on
The anticipated implementation of UV disinfection, potentially in Phase 2 improvements,
will eliminate the need for chlorine and sulfur dio~de chemicaLs. Figure 9 presents actual
chemical usage data for the e~usting plant.
Ja~~„ry i~, zoo~ 14
Diesel Fuel Utility Usage Chemical Usage Personnel
Consumption*
G``y o1 Boura~,~
Attachment A: r~
Draft Wastewater Treatment Strategic Plan ,,~y-,%,~~''
'''~ ';fi_
Figure 9. Chemical Usage Data for the Existing WV~I'P
- -
600 I
500
~-.
~
~
~ 400
~
~
~
a~
~ 300
y
~
.~r
~
"ti ~oo
~
i-i
~
~
V
100
The use of additional chemicals was considered during the selection process. Several
alternatives evaluated required the addition of inethanol to achieve nitrogen removal. The
chosen process can remove a substantial amount of nitrogen and phosphonis without the
need for chemical addition. This is important since it is anticipated that 2009 Q'DS permit
dischatge limitations will limit the dischatge of one or more of these substances (Phase 2).
HOW THE STRATEGIC PLAN AFFECI'S LIFE IN BOULDER
WVUIT' improvements are necessary for the City of Boulder to continue to meet their
environmental stewardship goals. By addressing the two main drivers of wastewater
treatment improvements, lower ammonia nitrogen limits and increased wastewater treatment
capacity, City goals of furthering community sustainability goals and protecting water quality
will be met. The improvements represent a proactive, or "action" approach, to improving
water quality in Boulder County because they go beyond the minimum required to meet
regulatory requirements.
A comparison between operation goals met by the existing WW'I~' and the WV~1'I'P after
Phase 1 improvements are implemented is shown in Table 3.
J~~~:,,>> i~,?oo~ 15
Chlorine Sulfur Dio~de
Attachment A:
Draft Wastewater Treatment Strategic Plan
Table 3. Comparison of WWTP Capabilities
G~y ot eowae.
!/~%~'''I'
~
Existing WWTP WWI'P AfterPhase 1
Im rovements ~
Meet future ca aci demands X
Meet new ammonia limits
mPS 2003 X
Provide treaunent options for
additional nutrient removal X
Provide shorter operating tixne
iosolids dewaterin X
Eliminate chemical use X- Phase 2
Reduce solids handlin X
Minimize long-term
o rational cosu' X
Muiunize ene re uiremenu X
Minimizx greenhouse gas
emissions X
Minimi~r nei hborhood tra{Eic X
Provide ade uate odor control X X
Muvtniz.e visual im airment X
Im rove air uali X X
~ Long-uan operational costs associated with the e~cisting plant would increase due to reoccurring equipment
repair and rehabilitation.
ZEneigy use will increase based on Pk~ase 1 Improvemenu due to the increased level of treataient provided.
Ene~gy savings from more efficient eqwpment and the improved dewatering process will help w offset the
greacer ene:gy demand from Luger, more extensive treatment.
30dor controls will be placed on solids processes.
The CDI'S perxnit dated February 1, 2003 includes a compliance schedule that allows the
City until January 31, 2008 to comply with the new ammonia limiu. The Phase 1
improvemenu are on schedule to be completed and online before that date.
A schematic flow diagram of the WV~'TP after imple~ntation of Phase 1 improvemenu is
shown in Figure 10.
J~~y ib, zom 16
Attachment A:
Draft Wastewater Treatment Strategic Plan
G\`y ot Baurae~
,,~~:~:~
,~ y~_
T~
w. ~cnemanc riow ~,nar~ or rne ~vew w w 1 r
~n:~s~ z
Alum
~ ^~
Inlernal ~li~ed Liyuor Rec~~clr
InFluent ~ PC Anaerobic Anoxic Aerated SC
*>'~'~ _'~' ~ ' 'i-„ ~~~,~
r ~
Prlmary Sludge
^
i~
WAS
PRINCIPLES GUIDE APPROACH TO WASTEWATER TREATMENT
IMPROVEMENTS
As mentioned previously, the primary motivators behind the WWTP upgrades that
simultaneously serve City and County goals were:
^ Improving ammonia nitrogen reduction capability,
^ Increasing treatment capaciry, and
^ Improving the dewatering process capabilities to meet increased capacity
requirements.
Secondary drivers include:
^ Replacing inefficient equipment with newer, improved equipment; and
^ Reducing chemical usage.
The City is required to provide adequate treatment capacity and meet regulatory
requirements and these upgrades will allow the City to do so. The secondary drivers could
be met simultaneously with only moderate additional cost. These improvements optimize
the system and establish the City as responsibly proactive by implementing treatment
options that improve effluent quality while potentially minimizing future costs.
J.~,t~uy i~, ~ao~ 17
G\`y oE Boulae~
Attachment A: ~~
Draft Wastewater Treatment Strategic Plan ~,ky%,%~'
~~ 'w ~
Tti
LIQLIID STREAM ALTERNATIVES ANALYSIS
As part of the preliminary design evaluation, nine process alternatives were initially
considered for upgrading the Boulder 75th Street WW I'P. For more inforn~ation on the
original nine treatment options and the selection process refer to the Ciry of Boulder
Wastewater Utiliry Plan Amendment 1 and Site Application Report (Brown and Caldwell,
2005).
Based on the initial process review the following five alternatives were selected for detailed
evaluation.
^ Alternative 3. Trickling Filter - Solids Contact Tank - Nitrifying Trickling Filters -
Trickling Filter Recycle - Denitrification Filters - Chemical Phosphotus Removal
(TF-SGNTF-TFR DNF)
^ Alternative 6. Trickling Filter - Activated Sludge ('fF-AS)
^ Alternative 7. Activated Sludge (AS)
^ Alternative 8. Trickling Filter - Membrane Bioreactozs (TF-MBR)
^ Alternative 9. Membrane Bioreactor (MBR)
These alternatives were evaluated in detail and the results of the evaluations are presented in
Figure 13 and Table 4.
Basis of Economic Evaluation
The economic evaluation includes consideration of initial construction costs and ongoing
operation and maintenance (O&N~ costs. It is important to consider both types of costs
since some alternatives may be capital cost intensive and yet require minimal annual O&M
costs, while other alternatives may be less capital cost intensive but require high annual
~&M expenditures. Present Worth Analysis is a technique used to put construction and
O&M costs on a comparable basis so alternatives can be appropriately evaluated. Present
worth costs were evaluated over a period of 20 years.
Figure 11 shows the results of the economic, or present worth, evaluation of these
alternatives.
Js„~~.~,y i~, ~oo~ 1 S
Attachment A:
Draft Wastewater Treatment Strategic Plan
Figure 11. Economic Evaluation for Process Alternatives'
G``y ot Bourae~
~ .'~
~`/~~y~i
T~
70 ._ ^ Total PW O&M Cost
^ Phase 2 PW Consttuction Cost
60 ^ Phase 1 Construction Cost
~ 50 `
a 40
Q 30 _ .
~ 20 -
~
~ 10 - -
Cg ~ , ~- -~ ~ '
Alternative 3 Alternative 6 Alternative 7 Alternative 8 Alternative 9
TF-SCT- TF-AS AS TF-MBR MBR
NTF-TFR
DNF
1 Values rounded to the nearest hundred thousand dollars.
As shown in Figure 11, the most economically feasible alternatives are Alternative 6
(trickling filter-activated sludge) and Alternative 7(activated sludge).
Basis of Non-Economic Evaluation
Non-economic factors were also considered in the evaluation of the wastewater treatment
alternatives. These non-economic factors are particularly important when the economic
evaluation indicates similar costs for two or more alternatives (such as the case with
Alternatives 6 and 7 as indicated in Figure 13) or when non-cost issues represent a high
priority. The non-economic evaluations for the secondary treatment process alternatives are
displayed in Table 4. Each non-economic criterion was scored a value between 1 and 5, with
5 representing the highest or best alternative.
January 16, 20C7 19
Attachment A:
Draft Wastewater Treatment Strategic Plan
Table 4. Non-Economic Evaluation for Process Alternatives
G`\y ot Bou1a~,~
h'' .'~' ~~
~ ~
T~
u ~
~ ~
~" ~
c
~ ~
• ." ~
~
~
~
~
'' yJ
~
~,, a~
~ ,
~
a
~ v
~ ~~
~
~
~
Criteria ~
~
~ ..,
~
u
v~j ~
...
~
~.
~ ~--,
-d
•
~ w
~
~ o
a
a ~
~ ,
`~
~
~ o
'~ ~
H
w .~
~ .~
a
o
~
a~ ~
a~ • ~
C `'~
~ ~ ~ ~
~ v
~ ~ ar W '~ ~
~
~ .
~
a~
~
~~Q OA
...
~ c
,i
'~ u
~ -d
~ °~ 4~.
~
~ ~
o
~.'
i ~'-
i V ~
-, ~-
, c.
i) ~,
„~
Alt. 3- TF/SC, NTF, TFR,
DF, Q'R 3 4 3 3 5 4 3 5 4 4 38
Alt. 6 - Trickling Filter -
Activated Sludge
4
4
4
3
3
4
4
3
4
3
36
Alt. 7- Activated Sludge 5 4 5 5 4 5 4 4 5 4 45
Alt. 8 - Trickling Filter -
Membrane Bioreactor 5 2 2 2 5 2 5 1 4 5 33
Alt. 9- Membrane Bioreactor 5 2 3 4 5 2 5 1 5 5 37
Note: A higher score is more favorable.
Refer to the City of Boulder Wastewater Utility Plan Amendment, September 2004, for more
details on the non-economic evaluation. As seen from the rating inforn~ation presented in
Table 4, Alternative 7(activated sludge) was rated the highest overall from a non-economic
standpoint.
Disinfection Alternatives
The Boulder 75`h Street WWTP currently uses chlorine gas to disinfect the treated
wastewater. Gaseous sulfur dio~de is used to remove residual chlorine following
disinfection and prior to discharge of the wastewater to Boulder Creek. The e~usting
chlorine disinfection system has adequate capaciryto meet the needs of the proposed
expansion of the 75`h Street facility from 20.5 MGD to 25 MGD, however it does not meet
current industry standards associated with the safe handling of chlorine and sulfur dio~de
gases (both chlorine and sulfur dioxide gases are considered hazardous chemicals). This,
along with a broader concern about the safety aspects of transporting and handling
hazardous chemicals and the environmental impacts associated with using chlorine as a
disinfectant, prompted the Ciry to evaluate replacing the existing chlorine disinfection system
with a different system.
Jan~y iv. ?om 2p
Attachment A:
Draft Wastewater Treatment Strategic Plan
The following disinfection alternatives were considered:
G\\`I pt BoWae~
,,~~.~:~
,~` y~-
T~
^ Alternative 1- Chlorine Gas with Sulfur Dio~ude (E~sting Gasous Chemical
System)
^ Alternative 2- I~'igh Strength Sodium Hypochlorite with Sodium Bisulfite (Liquid
Chemical System)
^ Alternative 3- Onsite Sodium Hypochlorite Generation with Sodium Bisulfite
(Liquid Chemicals System)
^ Alternative 4- Disinfection with L1ltraviolet Light (UV Disinfection)
Figure 12 presents an economic evaluation for disinfection alternatives to be used with the
activated sludge process.
Figure 12. Economic Evaluation for Disinfection Alternatives
~ ~ Construction Cost ^ O&M Cost
~ 6.3
6 -
5.2 5.2
~-.
~ 5
`~ 3.4
Q 4 - -
a
0 3 -
.~
~ 2 -
~ i
H
U 1
p - , - ~
Gaseous Chlorine F--figh Strength Liquid Disinfection with W Disinfection '
Disinfeaion Sodium Hypodilorite Low Strength Liquid
Disinfection Sodium Hypochlorite
Generated on Site
As shown in Figure 12, the most economical alterriative is continued gaseous chlorine
disinfection.
The results of an evaluation of non-economic factors for disinfection alternatives is
presented in Table 5.
January 1G, 2G07 21
Attachment A:
Draft Wastewater Treatment Strategic Plan
Table 5. Non-Economic Evaluation of Disinfection Alternatives
G~~Y ~t Bou1aP~
~~;, ,'~/,~~`
~';~" ~y'~_`'
R
~
a~ ~
~
~ ~
a~
a~
~ ~ ~ ~
~
~i l~+'
'~ .p"
~" ~?
~ ~
J~'~'' ~
~ ~
'~'' •~
p~ a
i
~
Criteria o ~ W
~ ~
~ :~ o •°;
~ ~
'
.
~ G~
•~
~ ~
u ~
O
W ~ ~ ~
(~ o
~
Vl
~ V1
~ ~
~ ""~
~
~
~ '~
~ ~
•~ ~y,~
iM r~
~+
~ rt
'~'~' r.1
h~-1 u
~ Cd
a (n
rl
~
~ ~ ~ " ~
~ ~ •.,
z ~,
°' ~,
w ~ on
x ~ ~ .
o
c c
Alt. 1- Gaseous Chlorine 5 4 4 2 4 4 4 5 1 3 3 39
Alt, 2 - High-Strength Sodium
Hypochlorite 5 4 5 4 4 4 4 4 3 4 4 45
Alt. 3 - On-Site Sodium
Hypochlorite Generation 5 4 3 3 4 4 4 3 4 4 4 42
Alt. 4- W 5 3 5 5 4 4 5 2 5 5 5 48
Note: A higher score is more tavorable.
UV disinfection was rated the highest of the disinfection alternatives from a non-economic
standpoint. UV disinfection is the safest for the WW'IT' staff and the community and it
eliminates the need for hazardous chemicals to be shipped to and stored at the WW I'P. UV
disinfection is also very easy to operate and maintain, and will allow the Ciry of Boulder to
continue to meet their effluent disinfection requirements without the negative aspects of
chemical addition. Even though UV disinfection was not the most economical alternative, it
was selected as the preferred disinfection method based on the non-economic criteria.
Because of funding limitations, replacement of the existing chemical disinfection (chlorine
and sulfur dioxide) with UV disinfection is not being implemented as part of the Phase 1
improvement project. It is anticipated this improvement will be implemented as part of the
Phase 2 improvements in 2010.
Activated sludge and LJV disinfection were selected as the preferred wastewater treatment
process to meet Boulder's current and anticipated wastewater treatment needs. Figure 15
illustrate the components of the recommended WWTP upgrades.
Jani~ry 16, ?GO? 22
Attachment A:
Draft Wastewater Treatment Strategic Plan
Figure 15. WW'I'P Upgrades to Existing Facility
~
5 .tt- ~ w . ~.
.~, 'tt
~ ~
~ tt ` ~,...,b. tt .~
I A x
. . . ~ . . . x , .
tt
tt
.... " „~,.,~.
~n
~ ~~ ~ ' ~ -~,~
° ~~,~~
~ #
Ta ~
J ~
tt ` .n ~ p ~.nw
~i ~n~.v~ ~ ' a^., '
kf K
~+a~.n
~wi .
x o M • N Xn .~ ~ Y ~y{`~'d 11 X %
i
+~ •. ~' r
'' j
SOLIDS DEWATERING ALTERNATIVES ANALYSIS
~ca~o:
+f 08T . PRIIL
rv . rn~n
ecr • ea[
ec . sECc
Hfi . NITRI
Cm ~ CIILC
MFf . UIBl1
'Three alternatives were evaluated for the solids dewatering process. These alternatives
included:
^ Alternative 1: Do nothing
^ Alternative 2: Maintain semi-solid (10-12% solids) dewatering (e~sting process)
^ Alternative 3: Transition to a cake (20-24% solids) product (new process~
The Do Nothing alternative requires no capital investment and neither the operations and
maintenance nor the total present worth costs have been estimated. The Do Nothing
approach is not a valid selection because the e~sting facilirycannot treat the projected
generated solids resulting from the new liquid stream improvements.
Alternatives 2 and 3 are based on centrifuge dewatering of digested biosolids produced from
the liquid treatment process. Figure 14 presents an economic evaluation of the biosolids
G`\y pt Boulae~
~~. /~
'~~ ~
~
,
.
~,
+
,
.
.
Y
°m'°~ r
tt ~TM ~~ + a
aai~ i
J~„L,~rv i6, ~oo~ 23
~~ - -
G~~y ~t Bou/ae~
Attachment A: /,~
Draft Wastewater Treatment Strategic Plan ,,~y-,%~'
~~ '~
dewatering improvement alternatives. Present worth costs were evaluated over a 20-year
period.
Fi ure 14. Economic Evaluation for Dewatering Im rovements Alternatives
45 -
^ Total Present Worth ~
40 ^ O&M Cost
^ Capital Cost
.-. 35 ; .
~
0 30 -
A 25
0
~ 20
+ 15 -
~ : ;;..,,.-= _ -
~ 10 -
5
0 - ~- , -
Do Nothing^" Dewatered Semi-Solid Dewatered Cake Solid
'~Note: The Do Nothing approach is not a valid selection.
Table 6 presents a summary of the non-economic evaluations of the dewatering
improvements alternatives.
J~~.,~y i~, ?co~ 24
G`~ ot BoWtler
Attachment A:
Draft Wastewater Treatment Strategic Plan ~,~,G~y,JI'
J~'
~
Table 6. Non-Economic Evaluation Cxiteria for Dewatering Improvements
Altematives
Altematives
Do Nothing
(10-12°k solids)
Semi-solid (10-
12% solids) with
ewsting solids
dewatering
building
~
Cake solid (20-
24°~ solids) with
new solids
dewatering
building
Description
e~usting s}~stem
would replace
existing ones in
existing
dewatering
building.
product and new
high-solids
centrifugein
new building.
Advantages Disadvantages
• I.ow cosu. • Existing system does not have
• No consuuction impacu. capabilityto meet futune WWTP solids
loading rate at flows of 25 MGD.
• Existing system is 20 yeaxs old and it is
difficult to find replacement parts,
reducing reliability and plant
redundancy.
• Would lead to regulatory non-
compliance.
• Inabilityto store non-dewatered
biosolids at lant.
• Regulatory compliance. • New centrifuges would be smaller and
• Makes maximum use of would be required to operate longer.
existuig stnictures. • Structural concems if eatisting building
• Sixnilar operation to eicisting are modified again, limited ability to
process; staff is familiarwith modifyeausting building.
process. • Opinion of probable cost is highest for
this alternative due to retrofittmg
difficulties, longer run tixnes, more
frequent equipment failure, and greater
staffin needs.
• Regulatorycompliance. • Cake storage is needed.
• Makes maximum use of • Requires constnution of new facility.
existing suuctures.
• Lower biosolids volume.
• Fewer truck cosu equal lower
O&M costs.
• Opinion of probable cost is
lowest due to properly sized
structure and equipment,
reducing staffing and hauling
As indicated in Table 6, Alternative 3 represenu more advantages and fewer disadvantages
than the other akernatives.
Based on the economic and non-economic analysis, the recomnlended improvements for
the solids dewatering facility are a new, dewatered cake solid processing facility.
January 16, zoo~ 25
_m of BoWp~er
G
Attachment A:
Draft Wastewater Treatment Strategic Plan ~,~},~-;d,~
Jl
,
In summary, Altemative 3 was chosen because:
1. A cake product is becoming the norm in the industry and produces drier material,
which resulu in fewer truck trips from the WIWIT' site.
2. A new dewatexing building is appropriate for the new equipment due to size
constraints and age of e~tisting building.
3. Retrofitting the existing facilities would resuk in higher lifetime cosu for the WW'IT'.
Cost advantages for consuucting a new building include:
a. Installation of properly sized equipment with lower operating cosu,
b. I.ower staffing needs,
c. Redundant capacity,
d. Greater fle~cibility, and
e. Lower maintenance costs.
INVESTMENT PROGRAM
The 2005 Wastewater Utility Capital Improvement Program (QP) developed by the Boulder
Department of Public Works includes improvemenu to both the liquid stream and solids
stream wastewater treatment process. In December 2005 the C'ity issued a revenue bond to
finance the capital cosu associated with the Phase 1 improvemenu.
The 2005-2010 Wastewater Financial Plan incorporates a series of multi-year rate increases
to cover the cost of the~e projecu. Lhility mte adjustmenu are approved by Gty Council on
an annual basis. For 2005 and 2006, the City implemented 20 percent increases to the
wastewater user chaYges. An additional rate increase of 6 pe~+cent was implemented on
January 1, 2007. Table 7 presenu a comparison of Boulder wastewater rates compared to
those of surrounding communities based on 2005 rates.
J~„azy ib, zoo~ 26
G~y ot eoube~
Attachment A:
Draft Wastewater Treatment Strategic Plan ~y.
~~ ~
Table 7. Front Ran e Communi Sewer Rates'
Number
Communi Annual Sewer
Service Cha e$
1 Erie 321.00
2 Colorado S rin s 219.29
3 Fort Collins 210.30
4 I.o ont 207.00
5 Greele 195.00
6 Westminster 186.00
7 Broomfield 184.20
8 No lenn 171.00
9 Boulder 170.76
10 Thorntan 163.08
11 I.ouisville 153.60
12 Arvada 148.86
13 Lafa tte 138.84
14 Aurora 130.20
15 Denver 128.16
1 Based on in£oima[ion collected of Front Range Communities conduc[ed in 2005.
Investment Strategies
Figure 15 depicu the range of investment strategies considered in determining the extent of
wastewater treatment system upgrades at the Boulder 75'~ Street W WTP.
January 16, 2007 2']
Attachment A:
Draft Wastewater Treatment Strategic Plan
Figure 15. Comparison of Investrnent Strategies
~
v~s~o~~~
No budget constraints.
,
Meet all current and fuhice needs initially.
~ected design
~~
ti n
Additional hinding with constraints.
Meet all curmnt needs and prepate for Futuce
growth.
Financially constrained.
Meet current needs
only.
G\\y of Bou1a~,~
„~,.: ~%h~': ~
~ ~
R
The City of Boulder chose to pursue an action level approach to wastewater treatment
improvements. At this level each area that requires immediate attention has been addressed
and mechanisms have been put in place to prepare for anticipated future requirements.
Unlike actions taken at the visionary level, the upgrade alternatives were selected to provide
the City with the most long term value with respect to cost, system performance, and
environmental impact.
The system upgrade approach was initially based on two phases of implementation. This
phasing approach allows the City to balance capital expenditures by constructing only
necessary components in the near-term, while setting the stage for additional process
improvements that may be required to meet more stringent future effluent limits. Phase 1
improvements include those that were required to meet current design flows and permit
limits and processes that prepare the plant for the Phase 2 upgrades with only moderate
additional costs. Phase 2 upgrades include those that are anticipated to prepare the plant to
meet anticipated future limits, reduce chemical usage, and treat any odor concerns that may
arise.
Construction of Phase 1 improvements began in 2006 and Phase 2 improvements are
expected to begin in 2010. Phase 1 and 2 improvements are as follows:
January 16, 2007 2 g
Attachment A:
Draft Wastewater Treatment Strategic Plan
G\~y pt Boufaer
~~~~=%'
~~ ~
~
Phase 1(2006): These improvements are required to address the 2003 discharge
pernzit limitations (ammonia nitrogen) and to increase the capacity of the
WWTP. In addition, these improvements position the plant to meet anticipated
future discharge pernut requirements with only moderate additional construction
costs.
Phase 2(2010): These improvements are anticipated in response to probable
more stringent Q'DS discharge permit limitations (nitrogen and phosphorus) in
2008, the desire to replace the e~sting chemical disinfection (chlorine and sulfur
dio~de) process with an ultraviolet (LJ~ disinfection process, the need to
address biosolids stabilization (digester capacit~ issues.
Phase 1 Implementation Schedule
Figure 16 depicts the implementation schedule for Phase 1 improvements. The schedule
includes the time required for total project implementation, beginning with project approval
and concluding with fully operational facilities.
Fi ure 16. Pro osed Im lementation Schedule
Com oneni 2004 200"s 2006 200' 2008 2009
Ia' uid Stream Im rorements
C=t: Conr: ~ppio~-a? • ~~~ ~o
DeSi . L' ades \[ar _'OU~ !o Au s: - C•0~
g;d • \Iaich '00
CoS15s~ctio!1 ~oril ~ Q: ro -rsae '_CC"c
Denaterin Im ~ozements
Ciri• Coucii ~ ro-: a:
• X
reinbec. 20Q~
Des. . C ade< -o~ember _'~~ ro\o~embec'_ 6
g:d • O tobei. '_~y~G \o-: embe ~006 ro
CoasxucCOn a,°1 ~'~n`.
The following table presents the current capital improvement program funding for the
wastewater treatment projects discussed in this strategic plan. It does not include funding
for on-going maintenance projects associated with the WWTP.
2006 2007 2008 2009 2010 2011
Phase 1 - Liquid
Stream $47,250,000 $0 $0 $0 $0 $0
Phase 2 - Liquid
Stream $0 $100,000 $200,000 $1,000,000 $10,000,000 $0
Phase 2 - $
Biosolids Digester 0 $0 $0 $850,000 $8,500,000 $0
Anticipated Rate
Increases for
Capital and Other
Needs 6% 4% 4% 10% 4%
2012
$0
$0
$0
3%
january 16, ZOG7 2O
G`,y ot Boulae~
Attachment A:
Draft Wastewater Treatment Strategic Plan ,,~.;/~`
~~ J ~
. ~
MEASURING PERFORMANCE
City objectives were used as guiding principles for the design of wastewater treatment system
improvements and will be used as perforn~ance indicators to measure results from the
improvement projects. To accomplish this, a baseline of each indicator must be established
and compared to indicatots measured at specific intervals following the completion of
improvement projects. Table 8 presents a summaryof suggested performance indicators.
Table S. Summary of Performance Indicators
City goals Performance Indicator
1. Number of occasions WVi/TP is not in
Improving and protecting water quality compliance with permit
2. Nutrient concentration in effluent
Reduce waste and improve recycling and Volume of exported solids
reuse
Improve health and safety of WVUI'P Number of WW'I'P accidents
operators
Meeting wastewater treatment capacity Wastewater flows
demands
1. Amount of Energy use
Creating a sustainable community through 2. Amount of Greenhouse gas emissions
resource conservation 3. Cost of operating plant
4. Amount of Chemical usage
Figure 17 provides an example of how the values of various perforn~ance indicators for the
e~sting process might be compared with values for the same indicators associated with the
WW I'P performance following the improvements. The expecr~l uzlues firnntlae W[XIIP
i~r~r.errrnts a~ n~ sho~cer~ tl~se para~ters mtist l~ Yrx~ritor~l in tlae fisture for ~arison
J:~n~~ry i~, zoo~ 30
Attachment A:
Draft Wastewater Treatment Strategic Plan
Fi~ure 17. Comvarison of performance indicatois
900 ~ - --
i
800 '
-
~
---
700 ~ - _ -
-
600 I
500 i -
400 ~
300 --
200 ~ -
100 =
~ O ~ ~- --- -
0
- -
!
~
~
- -
-
Z - - Old Process
~ ca
• g~
t ~ p ~ --- --- New Process
-
.~ ~ ~ ~ ~ ~ ~ ~ o
~
~ ~ .o ~ c o ~
a~ ~
° ~ >,
y
Y o ~ ~ ~ _
~ ~
8
Z o
~
m c~~
m p ~~ ~
~ -
~~ U
'~'Values vary from 16.9 mg/L to 10.9 mg/L depending on the month
PHASE II IMPROVEMENTS
G~~y ~t Bou~ae~
'~`~%~', /~
~`~ ~~
. ~J
Tti
The existing WWTP has met historical needs by providing adequate treatment capacity and
appropriate treatment capability. The VW~'TT' is currently being upgraded to treat additional
wastewater flows and meet stricter effluent ammonia nitrogen limits in Phasel.
These Phase 1 improvements represent an "action level" position for the City. This position
requires that immediate action be taken on items of the most urgent need; capacity
requirements and pemut limits, with the incorporation of additional proactive elements
based on anticipated regulatoryconcerns, environmental quality, and available funding.
Many anticipated treatment challenges can be more cost effectively dealt with during current
constniction activities than at a later date.
Additional phases of design and construction are expected to follow. Concerns to be
addressed for Phase 2 work include:
^ Disinfection system,
^ 2008 discharge pernut limits,
^ Biosolids stabilization (digester capacit~
^ ~dor and noise
J:~uary ib, zao~ 31
G\~y ot Bawae~
Attachment A: /~
Draft Wastewater Treatment Strategic Plan ,,~y-,,%~~
„~~ '~~
~
Disinfection System
Because of funding limitations, replacement of the e~sting chemical disinfection (chlorine
and sulfur dio~de) with W disinfection is not being implemented as part of the Phase 1
improvement project. It is anticipated this improvement will be implemented as part of the
Phase 2 improvements in 2010. For reasons outlined in previous sections the
implementation of an LJV disinfection system is preferred over the existing chemical
disinfection process.
2009 Discharge Permit Limits
Dischatge pernut limits are revisited everyfive years, and it is anticipated that some level of
total inorganic nitrogen (TIl~ and phosphorus removal may be required by future discharge
permits. Current construction includes provisions to allow these anticipated future limits to
be met with rninimal additional capital expenditure.
Biosolids Stabilization (Digester Capacity)
Based on current projections, the capaciry of the existing digesters will not be sufficient to
adequately stabilize the biosolids for continued land application after the year 2012. The
need for additional digester capacity will depend on the actual solids production once the
improvements are brought on-line in 2008, whether or not land application continues to be a
viable recycling alternative, and the success of privatized composting of the biosolids. These
issues will be evaluated over the ne~ct several years prior to any additional capital expenditure.
Odor and Noise
The Boulder County 1041 pernut stipulates no net increase in either odor or noise from the
tijVW'I'P. Although additional control measures are not anticipated at this time, the City will
continue to monitor odor and noise in compliance with the permit conditions. After the
Phase 1 improvements are operational, the need for additional odor and noise control will be
re-evaluated and appropriate steps taken as necessary.
E,
FUTURE CONSIDERATIONS FOR WAST~WATERTREATMENTNEEDS
• •j ` ''M, ,
•~
Future considerations that are beyond the scope of th~s strategic plan and the current Capital
Improvement Program include l~ stringent total inorganic nitrogen (TIl~ and phosphorus
discharge permit limits, 2) emerging contaminants and 3) biosolids recy~ling or disposal
fle~ubility.
Stringent Total Inorganic Nitmgen (TIN) and Phosphorus Discharge Permit Limits
Chemical addition and/or additional aeration basin volume may be required to remove
additional total nitrogen (7TI~ and phosphorus. If e~remely low.TTN limits are
~
`..
•
J~,~~~y~ ib, -'oc' 32
G.`y ot Boulae~
Attachment A: r~
Draft Wastewater Treatment Strategic Plan ,,,Fy,,/~~'
~~ '~
implemented in the future, a tertiary denitrification treatment process may also be required.
If extremely low phosphorus limits are imposed, tertiary f iltration may be required.
Emerging Contaminants
Emerging contaminants includes pollutants such as endocrine disrupting compounds and
disinfection byproducts. At present little is known about the significance of these
contaminants or appropriate treatment technologies for their removal from wastewater,
however, regulatory requirements associated with these contaminants may be adapted in the
future. If emerging contaminants removal becomes necessary, public education and
additional treatment processes will likely be required. This issue will be evaluated in the
future as appropriate.
Biosolids Recycling or Disposal Flexibility
The current WW'IT' upgrade projects will give the Cary a variety of future biosolids end-use
options. These options include maintaining the existing land application program,
transitioning to privatized land application and privatized composting. The method of final
disposal of the solids generated by the wastewater treatment process is going to be an issued
until a long term solution can be reached. Concerns have been raised about whether land
application should be used when biosolids contain varying quantities of emerging
contaminants. If regulations regarding the end-use of biosolids change, treatment and end-
use options will be evaluated. The current approach is to maintain flexibility in disposal
options so that the utility is in the best position to respond to regulatory changes and
community pressures. Ultimately, the final disposal decision could be dictated to the
wastewater permit holders like Boulder through regulatory restrictions.
January 16, 20C7 33
G\\y pt Boulae~
Attachment A: r,~
Draft Wastewater Treatment Strategic Plan ~,,~y,,/~''
~~ ~
~
STRATEGIC PLAN TO MEET CITY GOALS
Figure 18 illustrates how the current WVUI'P improvements and decisions for future
consideration are directed toward meeting City needs and goals. The tc~p portion of the
figure addresses design elements already incorporated into the WWTP improvements. The
bottom portion of the figure identifies additional challenges that must be addressed to
continue to meet City goals.
Figure 18. Meeting City Needs and Goals
Liquid Stream Improvements Dewaterin~ Improvements
CONTINUE TO SATISFY NEEDS OF PROACTIVELY DELIVER ON CITY
GROWING COMMUNITY
GOALS
-
J~a~,~,y ib, zoc7 34
G~\y ~t Boulp~~r
Attachment A: /
Draft Wastewater Treatment Strategic Plan ~,,~y,,l~'
~~, ,~
~
Future Considerations
Stringent TIN and
Phosphon~s Discharge Emerging Contaminants Biosolids Recycling
Per~nit Limits and Disposal Flexibility
e~
Jam~ary 16, 200' 3 5
Attachment A:
Draft Wastewater Treatment Strategic Plan
TRIPLE BOTTOM LINE INDICATORS
G\`y of BoWae~
~~': /~
~~~ ~
~
The incorporation of adc~itional treatment processes or biosolids handling methods to meet
future regulatory requirements will affect environmental, economic, and social aspects of the
community. Figures 19 - 21 illustrate how future decisions may affect the Boulder service
community economically, environmentally, and socially.
Figure 19. Summary of future decision making on environmental impacts
'GHGs (greenhouse gases)
Figure 20. Summary of future decision making on economic impacts
Replace chemical Increased capital costs,
disinfection system with decreased operadng
LJV disinfecdon costs
Jam~ary 16, 20C7 3C
G\N ot Boulae~
Attachment A: /
Draft Wastewater Treatment Strategic Plan ~,;~y,,/~~
~~ ~
~
Figure 21. Summary of future decision making on social impacts
Additional treatrnent for Improve water quality
TIN, phosphorous and for downstream useis
emerging contaminants
Implement enhanced Greater flexibility for
biosolids stabilization boisolids end uses
from digester capacity
Replace chemical Improve safety of plant
disinfection system with workers and reduce
W disinfection chemical use and
transport
SUMMARY
The Boulder 75`h Street WW'IT' has historically served the City of Boulder well by meeting
regulatory requirements and discharging high quality effluent to Boulder Creek.
Improvements at the wastewater treatment facility are rypically driven by state and federal
effluent discharge limitations. Phase 1 improvements to the WWTI' were necessitated by
the imposition of more restrictive ammonia limits on the discharge and by anticipated
growth in the Boulder wastewater service area population. The system upgrades currently
under construction include improvement to the liquid stream treatment process and to the
solids dewatering process. The liquid stream treatment improvements include converting
the e~cisting trickling filter solids-contact process to an activated sludge process. The solids
dewatering upgrades include the addition of new dew~atering equipment to reduce the
volume of solids that must be hauled from the WW'I~' site. Additional improvements will
be required in the future as wastewater discharge and solids handling requirements change.
Plans have been made to accommodate these anticipated future upgrades with limited
additional capital expenditure.
The current improvements meet City goals and establish Boulder as a proactive
environmental steward.
The costs incurred in implementing the current V~1W'I'P upgrades have been paid through
bond sales and increased user fees.
]anu<Uy i6, ?oc~ 3 ~
G\N pi Boulper
Attachment A:
Draft Wastewater Treatment Strategic Plan ~,~,~-,~,J~
~`~
~
The current W WTP improvemenu have been designed with the intent of ineeting current
treatment requiremenu and suategically positioning the City of Boulder to economically
address anticipated future treatment requirex~nu. The Phase 1 improvements are expected
to be completed in 2008. Anticipated future wastewater treatment and biosolids handling
improvemenu will be implemented as necessary.
REFERENCES
Brown and Caldwell. Ma~h 25, 2005. Amendment 1 and Site Application Report (Ma~+ch
25, 2005) to the Catyof Boulder Wastewater LJtilityPlan (November 15, 2002).
Boulder County. 2006 Boulder Valley Comprehensive Plan.
Brown and Caldwell. March 8, 2004. City of Boulder 75`" Street Wastewater Treatment
Plant Upgrades Communityand Environmental Assessment Process (C~AP) Addendum
No. 1 March 8, 2004.
Rothbe:g, Tamburini & Wmdsor, Inc. May2006. CommunityEnvironmental Assessment
Process for 75`~ Street Wastewater Treatment Plant Dewatering Improvements.
Jaa~y tb, zoo~ 38