HomeMy WebLinkAboutInformation Item: Urban Wildlife Management Plan Scope of Work
M E M O R A N D U M
DATE:
April 12, 2005
TO:
Water Resource Advisory Board
FROM:
Wildlife Management Plan Project Team
Bryan Pritchett, Open Space & Mountain Parks, Project Manager
Mark Gershman, Open Space & Mountain Parks
Alice Guthrie, Environmental Affairs
Bev Johnson, Planning & Development Services
Jeanne Scholl, Parks & Recreation
Stephanie Grainger, City Manager’s Office
SUBJECT:
Urban Wildlife Management Plan Scope of Work
The city-wide wildlife management plan is getting underway and we know this project
and plan is of interest to the board. Staff took the draft scope of work for the Urban
Wildlife Management Plan to the City Council Environmental Goal committee on March
3rd and received input and feedback. Attached are the draft scope and cover letter that
went to the goal committee. Staff will bring the draft work plan to City Council for
discussion under City Manager items on May 17th. Prior to the Council meeting, the
project team will take the draft scope of work to interested stakeholders on April 21st for
feedback before finalizing it for Council's review.
In the meantime, staff continues to gather management plans from other communities,
examine best management practices, inventory existing numbers and locations of species,
and analyze existing conditions.
The process for the Urban Wildlife Management Plan will include opportunities for
public involvement including periodic updates and discussions with Council and the
respective Boards.If you have any questions, need more information, or have any
feedback on the draft scope of work please contact Stephanie Grainger, at 303-441-3005.
Thank you!
M E M O R A N D U M
TO:
Environmental Goal Committee
FROM:
Wildlife Management Plan Project Team:
Bryan Pritchett, Project Manager, Open Space & Mountain Parks
Bev Johnson, Planning & Development Services
Jeanne Scholl, Parks & Recreation
Alice Guthrie, Office of Environmental Affairs
Stephanie Grainger, Assistant City Manager
SUBJECT:
Draft Scope of the City-wide Wildlife Management Plan and Proposed
Work Plan Timeline
DATE:
March 1, 2005
Attached is the proposed scope for a city-wide Wildlife Manage Plan. The plan will
incorporate management recommendations and policies for all of the species of wildlife
in the city that need policy guidance or direction on their management. This broad plan
will require approximately two years to develop. However, since the most pressing issue
facing the city is the management of prairie dogs this will be the initial focus of the plan
and staff work. There are a couple of large projects that will be developed within the
next two years that have significant prairie dog populations and these projects will
require policy direction from the management plan on how to address these large
populations. Also, there are more imminent prairie dog management issues that are
arising at the airport as well as at the Boulder Reservoir.
Staff is proposing that the plan be a “living and breathing” document that can adapt as
species management plans are added and as topics and issues progress through research
and analysis, public process, and in policy considerations and recommendations. Staff
believes that it can complete the prairie dog component of the management plan within
one year. This plan will include policy recommendations on the “steps” of managing
prairie dogs. The new wildlife ordinance has set a priority of (1) mitigation; (2)
relocation; (3) trapping and humane euthanization; and (4) use of poison. Staff will be
evaluating this hierarchy and will make policy recommendations to City Council on
whether the city should follow this protocol or consider more stringent protocols for
management of prairie dogs on public lands.
The community needs to be involved in the conversation about the management of prairie
dogs and other species and a key component to developing the plan will be a public
process. Also, the following boards and commissions will most likely be involved at
some point in the process for review and/or approval: Open Space Board of Trustees,
Parks & Recreation Advisory Board, Environmental Advisory Board, Water Resource
Advisory Board, Transportation Advisory Board, Planning Board, and City Council. As
staff finalizes the scope of the work, it will identify the involvement level and decision
points for each of these groups and for the public. Staff will also identify and work with
various interested external groups.
As is called out in the scope, there are several Front Range communities as well as other
communities in the country with issues and environments similar to Boulder that have
wildlife management plans. Staff will perform a review and assessment of these plans
and will identify “best practices.” Mitigation techniques and approaches for prairie dogs
and other species will also be addressed in the plan and staff will also research and
document leading technology in the field as well as best practices.
Staff also heard from City Council during discussions on the north Boulder prairie dog
fence that it would like staff to consider in its analysis and plan development establishing
designated habitat areas for prairie dogs and non-designated areas; to look into available
unoccupied suitable habitat sites and the possibility of obtaining new sites; to look into
the potential impacts or unintended consequences that mitigation techniques may cause;
to address mitigation approaches and techniques for all park land in the city with prairie
dog issues; and to assess the carrying capacity of city lands for prairie dogs. These issues
will be considered in the plan.
The staff team that developed the wildlife ordinance will continue as a team and will be
doing the work on the city-wide wildlife management plan. Bryan Pritchett is the project
leader and Stephanie Grainger is the project advisor. Additional staff and outside
resources will be used to help develop the plan as needed.
Staff will review the draft plan scope at the Environmental Goal Committee meeting on
rd
Thursday, March 3.
If you have any questions prior to the meeting please contact Bryan Pritchett, Plan
Project Manager, at 720-564-2051 or Stephanie Grainger at 303-441-3005.
WILDLIFE MANAGEMENT PLAN OUTLINE
I.Executive Summary/Overview
-
Background and History
-
Purpose and Goals/Objectives
-
Identification of Issues
-
'HILQLWLRQRI:LOGOLIH±:KDWZLOGOLIe and habitats are included and why
-
Public Process
II.Approach to Ecosystem Management and Best Practices
-
Existing Policies, Ordinances, and Other Related Plans and Master Plans;
Review of Plans of Front Range and Other Communities and
Identification of Best Practices
highlights and commonalities of otKHU&LWLHV¶SODQVDQGGLIIHUHQFHV
from Boulder
-
State and Federal Authority and Responsibility
-
City Authority and Responsibility in Wildlife Management
-
Review of Wildlife Management Plans of Management Philosophies:
Individual animal protection versus ecosystem conservation
Preservation, Conservation, and ThreVKROGV±FRQFHSWRIDSSURSULDWH
numbers of a species and appropriate and inappropriate locations
Public Lands and Private Lands
Mitigation on Public Lands
Education/Information
III.Analysis and Assessment
-
Inventory and mapping of existing numbers and locations of species
-
Identification and analysis of wildlife movement (corridors and islands)
-
Identification and analysis of conflicts and problems
-
Prioritization of wildlife management issues/concerns
-
Capacity of lands and opportunities
IV.Species Specific Plans
Prairie Dog Management Plan:
Ecology, behavior, habitat preference, habitat modifications
Issues associated with prairie dogs: Facts versus myths: plague,
reproduction, burrowing behavior, reloFDWLRQ³NH\VWRQH´UROHSHVWRU
wildlife? Conflicting state regulations
Regulatory Compliance - Federal, state, and local status
Value in urban setting: prey base, education
Problems in urban setting: individuals and colonies
Identification and mapping of colonies:
-Benefits and conflicts of where they are.
-How should conflicts be resolved and when
-:KDWKDSSHQVLIDQDUHDLV³SODJXHG´"
Existing management plans and new city ordinance
Habitat and species preservation and management on city lands and on
private lands
³7KUHVKROGV´IRUDFWLRQ
Establish Policy and Protocol:
$FWLRQ³6WHSV´RU3ULRULWLHV±IRUH[ample: natural control, mitigation,
relocation, transfer, trap and humane lethal control, extermination with
humane lethal control, extermination with poison(?).
Other Species Management Plans: Bears, Mountain Lions, Deer (address
chronic wasting disease), Birds (geese non-migratory), burrowing owls,
eagles and other raptors), squirrels, beaver, muskrats, raccoons, skunks,
foxes, coyotes, fish (game fish and non-game fish), New Zealand mud
snails, mosquitoes (West Nile Virus), invertebrates, threatened or
endangered species. Note: A management plan for each identified
species would be established and will IRUPDVHFWLRQRU³FKDSWHU´RIWKH
wildlife management plan. The detail in each plan will vary with the
number of identified issues, urgency, and ability of the city to manage the
species.
V.Connections and Interrelationship of Species
-
Habitat related issues (wetlands, grasslands, forests, riparian areas, etc.)
-
³1RQKDELWDW´EDFN\DUGVDLUSRUWVHWF
VI.Other Related Issues –
Legal and liability issues/concerns; impacts and on
parks infrastructure and mitigation approach; incorporating policies and
practices into project design and development;
VII.Policy Recommendations
VIII.Action Recommendations
IX.Implementation Plan, Schedule, and Funding
X.Future Considerations and Concerns
To be identified/established:
Review and Approval Steps:
-
Public Process and Input
-
Staff Input and Approval
-
Board/Commission Process and Approval
-
City Council Approval/Adoption