6A - 2002-2007 CIP Tributary Greenways~
^
ri u ar
ree nwa s
.
.
~ GREENWAYS
2002 - 2007 CAPITAL IMPROVEMENTS PROGRAM
OVERVIEW
The 2002 Greenways Capital Improvements Program (CIP) budget is $450,000. The Greenways
CIP has been developed within the context of, and is consistent with, the Boulder Valley
Comprehensive Plan (BVCP), the Transportation Master Plan (TMP), the Comprehensive
Drainage Utility Master Plan (CDUMP), and the Greenways Master Plan. Although the
Greenways CIP has previously been developed for two-year periods, a 6-year plan is being
initiated to be consistent with other city programs.
The city of Boulder Greenways System is comprised of a series of corridors along riparian areas
including Boulder Creek and 6 designated tributaries, which provide an opportunity to integrate
multiple objectives, including habitat protection, water quality enhancement, storm drainage and
floodpiain management, alternative transportation routes for pedestrians and bicyclists,
recreation and cultural resources. In order to maximize the overlap of objectives and to
coordinate projects along the Greenways, identification of projects for the 2002-2007 Greenways
CIP was done as a team effort combining input from Public Works (Utilities and Transportation
groups), Parks and Recreation, Water Quality and Environmental Services, and Open Space/Real
Estate. Transportation and flood control projects were identified from the Transportation Master
Plan, the Comprehensive Drainage Utility Master Plan, and intra-deparhnental meetings to
determine project priorities and timing. Environmental projects were identified during the
~ Master Plan update process and were prioritized based on recent environmental studies, the
overlap with other projects, and the feasibility and effectiveness of the project in meeting
environmental goals. Maintenance of the Greenways system has been under review as part of
the Master Plan update process. To address the identified deficiencies in maintenance and weed
control, the 2002-2007 Greenways CIP is specifying $150,000 to be used for maintenance each
year.
POLICY ISSUES
All projects on the 2002-2007 CIP will go through the CEAP process.
HIGHLIGHTS
Highlights of Greenways projects included on the 2002 CIP are:
• The Fourmile Canyon Creek project between 26~' and 28`~' Streets involves improvements
to the creek, environmental restoration and an off-street trail connecting 26`h to 2g`n
Street. This project is being coordinated with the development of the new Park site and
with major flood improvements proposed in the Fourmile Canyon Creek Master Plan.
• The Iris Avenue Underpass at Elmer's Two-Mile Creek involves the construction of an
underpass to increase flood capacity and improve access for pedestrians and bicyclists.
This project is being coordinated with the Parks Department in conjunction with the
development of Elmer's Two-Mile Park and with the Transportation Division.
• The Bear Creek Reach 1 project includes habitat restoration, habitat preservation, and
water quality Best Management Practices (BMPs). This project is being proposed in
~ conjunction with the development of the Hospital site and will involve coordination with
1
the Open Space Department and Floodplain and Wetlands Management.
Maintenance concerns and weed control have been identified as a priority, with $15Q000 ~
being specified for maintenance each year beginning in 2002.
FINANCING
Greenways projects are funded from the Transportation Fund, Flood Control Fund, and the
Lottery Fund. Existing CIP expenditures are estimated at $450,000 per year for the next six
years. Annual funding distribution for the Greenways Program for 2002-2007 is as follows:
Transportation - $150,000
Flood Control - $150,000
Lottery Fund - $150,000
Program funding levels are currently being evaluated as part of the Master Plan update. Due to
city wide budgetary constraints, no changes to the existing funding levels are anticipated at this
time.
RELATIONSHIP TO OPERATING BUDGET
Staff is currently evaluating the entire Greenways maintenance program and will recommend
efficiency improvements and appropriate funding levels as part of the Crreenways Master Plan
update. In arder to begin addressing the identified deficiencies in maintenance and weed control,
$150,000 has been specified for maintenance each year as part of the 2002-2007 Greenways CIP.
~
~
~
.
~
City of Boulder Captial Improvement Projects, 2002 - 2007
PW/Tributary Greenways
Improvements to the Creek, environmental preservation, habitat restoration and an off-street trail connecting 26th
to 28th Street.
I:
.. RelattonshiptoMasterPian:; ' . ~ , ...~'~`:. ' . ~ :.. ~ .:.:~ `:. ~ . '.~ ~~~ . , .:: .
. . .. -: ~ , . , . .. .: ,:., . , :...: ~......:~..
`~; This project is consistent with the Graenways Master Plan Map and Reach Inventory accepted by City Councll in September 2000. ,~~.
PubllcProcess$tatus,lssues,~ . ~ ~ : ~.~~ ~ . .. '' ~ , :~: ,, .~~ ~. `+ .. , .~: . - . ,:.,, ' i: ;:~.:
..~~~ The CEAP for thfs project will go to the Greenways Advisory Commfttee consisting of inembers from TAB, WRAB, PRAB, OSBT, and ,
" Planning Board. The total project cost for lhe trail and environmental enhancements is $300,250 which results in an unfunded amount of
,:; $100,250. Costs of major flood Improvements are not included.
~'RelaNonshiploCouncllGoals:~ ,; ~
, .. ..:.., .„ ......: ~ .. . ~.~ ..~:-..: . . ,.:;: . ,...
'~~ This project supports the Council goals of environmental sustainability and transportation by improving the off-street trail system and including
~~ ~~ environmental restoration of the stream corridor.
~ ~ Relationsfilp wiflj:Other Departments. ~ ~,
""- This project will be coordinated wlth the Parks Department in conjuoction with the development of the Park site and with the flood ~
"~': improvements proposed as part ot the Fourmlle Canyon Creek Flood Master Plan.
2002 2003 2004 2005 2006 2007 FUNDING TO PLANNED
COMPLETION FUNDING
! !
City of Boulder
Utilities Division
GREENWAYS
i
FOURMILE - 26TH TO 28TH STREETS
~
PROJECT NAME ' Pro)ect Number. Map ~o #
Bear Creek Reach 1 ~ 13
oePnRTMenr.: pW/ Tributary Greenways 5uecoMMUNi17ro Southeast Boulder
FurioiNC souRCE: Tributary Greenways evca nrea Area I ~"
PR4JECT STA7US: ; Existing Facllity- Enhancements / Upgrades ~~ ~~.'~" ~ ~ ~;: ~ ~ -
CEARREQUIRE09 ~Required '~~ ~
PROJECTDESCRIPTION: "
:: . . ., . .. ,. . .. .,, ., . ., . . .. , ,..
'; This project includes environmental restoration, habitat preservation, and water quality Best Management Practices _
;_; (BMPs) in Bear Creek south of Arapahoe. One component of the project may involve improvements for fish
': movement and/or instream flows at the Wellman Canal diversion structure.
RelaHOnshipto.MasterRlan~'°: .. "' ' ~' ' " " ' ' ~~ ~ ~ '
, ..:... .... „ . ,. . . : -~
,. i This project is consistent with the Greenways Master Plan Map and Reach Inventory accepted by City Council in September 2000.
~ PublJo Process~Status, Issues:
~' The CEAP for this project will be reviewed by the Greenways Advisory Committee consisting of inembers from TAB, WRAB, PRAB, OSB
..: :. and Planning Board, This project is associated with the development of the Hospital site and related flood improvements for Bear Creek.
:,~ The total cost for the environmental enhancements is $440,000, which results in an unfunded amount of $365,000. Costs of major flood
"- - improvements are not included.
.-.-.-~ ~ ~.:'
~ ~ ~
V
City of Boulder
Utitities Division
GREENWAYS
BEAR CREEK REACH 1
/
~ 2002-2007 CAPITAL IMPROVEMENTS PROGRAM
~ PROJECT STATUS REPORT ~ ~--~_~~'
PROJECT`NAME Pro)ect Number: Map ID #
Iris Avenue Underpass L~.~ 64
This project includes the construction of an underpass under Iris Avenue at Elmers Two Mile Creek. The
underpass will provide increased flood capacity and access for pedestrians and bicyclists. This project has
''' received approval for $600,000 of federal funding. The Iocal match will be split between Greenways and
Transportation funds at $316,000 each.
i: i; ;
~i;:
~ RelaNonshipto~MasterPlanq~:
.~ This project is consistent with the Greenways Master Plan Map and Reach Inventory accepted by City Council in September 2000, and wilh
~-~" ~ the Transportation Master Plan.
~ - ~ .:;. . .. 'r : ~ ' .. : " .
PubiloProcess'Status,issues ' ~~- ' _ ~ ~ '~ ~~~ ~~~~ ' ;
. ... . . .. .. . ~ :: :.: ..... .. .. :: ..:.. ' . , ..:' .. ~ , .,. .. .. .
.~~ The CEAP for~this project wlll be reviewed by the Greenways Advisory Committee composed ot members from TAB, WRAB, PRAB, OSBT,
:~.: and Planning Board. The project will also be reviewed by TAB due to the strong transportation component of lhe project.
~ RelatfonshlptoCouneilGoals• '; ..'~" ~~ :`. '.. ~ :~: .,:: , , .. - , ~...
~~ ~ This project supports the Council goal of transportation by improving the off-street trail system,~and supports economic sustainability by
~::~ reducing flood risk.
•
City of Boulder
Utiiities Division
GREENWAYS
~
00 ~~
~
~
~ ;.
a
~
IRIS AVENUE UNDERPASS
~
PROJECT NAME ' " Pro)ect Number: Map ID #
Fourmile Improvements Pleasantview to 28th ~._~ _•~ 12
- ., ~ DEPARTMEN7: ~. .~. pW/ T~ibutary G~eenways SUBCOMMUNISY: ~.~ ~ palo Park ~
FUNDING SOURCE:. ~ T~IbUYary Gf20nWay5 ~ ~ BVCP~Nea ;~.; Af28 II ~~~~~~~~~~~~,~~~v_~1 -'~.- ~~ ~
.., ... ;.:. . ~ .
~ PROJECT S1'ATUS, " Existing Pacility - Rehab / Repair / Deficiency Correction ~ ~ ' .. ~ : ~ ~ ~
` CEAP REQUIR~Q9 ~ ; Required .' '
~ ,.::
PROJECT DESCRIPTION: ";`~ . ~. ~ ,. ; ; ~ ..; ... - ~ ': . ~ ; ~ ~ ~ ~ .::~.~ ~ ~ -.
,. , , , ...... ~. , :~. , .. ',.:~, ~ . .. ,.;,.. , ..:. . ... . , . . , .
This project includes improvements to the creek, environmental restoration, and water quality Best Management
Practices (BMPs) along Fourmile Canyon Creek between Pleasantview Soccer Fields and 28th Street.
Relat~onship to~Master Plan:;' ~
~~ This project is consistent with the Greenways Master Plan Map and Reach Inventory accepted by City Council in September 2000.
, PubllcProaess;8l'atus~:lssqes: ~~ "- ~ . . . :' ' ` ..: .. : .- . ~, .~~ '
~ The CEAP for this project wlll be reviewed by the Greenways Advisory Committee consisting of inembers from TAB, WRAB, PRAB, OSBT, ~
~'~ ~~ and Planning Board. Costs of major flood improvements are not included.
~~~Relationshipto:CouncllGoals:, ~' ~_~-~ ~ ~ .~,' ' ~- '"~~~~ ' . ~` ~ ~ ~.'~; . ~~,~
. . ~.,. ... ~~ ............_ ,. .
~ This proJect supports the Council goal of environmental sustainability by enhancing lhe stream corridor. ~
g; ii
~ ~ s
~
City of Boulder
Utilities Division
GREENWAYS
FOURMILE IMPROVEMENTS
PLEASANTVIEW TO 28TH
~ 2002-2007 CAPITAL IMPROVEMENTS PROGRAM ~
.~ -- __
PROJECT STATUS REPORT
PROJECT NAME Project Number: Map ID #
Wonderland Creek Foothills to Diagonal L..~J 62
'~ - DEPARTMENT:.'.,;:. pW/ T~IbUtary G~eeflw9yS ~SUBCOMMUNITY: ' CroSSroadS ~
, FUNDING SOURCE: ~" T~ibutary Gfeenways ~ BVCP Area ~~ ~ q~ea I ~~~ . j ~
' ~ 'PRQJECT STATtIS: ~- New Construction - Not Growth Related ~ ~; `~~,`. ~ o; ' ;;, ~
CEAP REQUIREDfi ' Required , ~
' ':PROJECT DESCRIRTION: ! $'"~
This project includes an off-street trail connection along Wonderland Creek between Foothills Parkway and the
s Diagonal Highway, environmental preservation, habitat restoration, and water quality Best Management Practices
,;;: (BMPs).
RelaNonship to Master Plan: ` ~ ~, ,. , . . . . . . . .. ,. , ,. ,
This project is consistent with the Greenways Master Plan Map and Reach Inventory accepted by Cily Counci( in SeptembeF2000
~ ~ ~
w
City of Boulder
Utilities Division
Greenways
WONDERLAND CREEK
FOOTHILLS TO DIAGONAL
~~ 2002-2007 CAPITAL IMPROVEMENTS PROGRAM ~ ~
PROJECT STATUS REPORT
PRO;IECT NAME Pro~ect Number. Map ID #
Fourmile Sumac to 19th St. ~~ 11 ~
REPpRTMENT:~:~., ; p~l~l/ TfIbUfB~y Gfe@f1W8yS SUBCOMMUNITY: ~~, NOrth BOUIdEf ~rW~
This project is for environmental restor
between 19th Street and Garnet Lane.
~
,
~#-,,
oaes.~ Status~ lssuasb < ,
. , . . .,. -, ~:. . .....:i. . .. . . . ., ... _; .: ., ,.., „
P for this prqect will go to the Greenways Advisory Committae consistlng of inembers from TAB, WRAB, PRAB, OSBT, and '
Board. Major flood improvements are not included in the cost balow. The construction of a multi-use path from 19th to Gamet Lana :
sen Gamet Lane and 26th Street will be re-evaluated in conjunction with the flood improvements.
.., . . .. ..: . . .:~ .. . . .;.
~hipfo~Coundl Goals; ., : . ` . , ~~ .'~.:~ ~:. .~ . , ~: ' . ,'.~i, , ~ ~:! ~ . '.,.,' '
--- ---
re supports t e uncil goals of envlronmental sustainability and transportation by improving the off-street lrail system and including
:ntal restoretion of the stream corridor.
. .., ,~ . . . ..
~ Relaliqnship vyttli;Other Deparkmeots ' - ~ ~ ~
.. :.. ~ . ~ . . ..., .> ..., .. .: : . , _.., .... . . ... ..: . ...:.:
~r~ This project will be coordinated with the flood improvements proposed as part of the Fourmlle Canyon Creek Plood Master Plan.
Projec
'::; `TOTA
~
. ~~r ~ t,j,. ~ ! ,§
2006 2007 FUNDING TO PLANNED
COMPLETION FUNDING
~ ~ ~
~
,
;i
i
:e°;
,,;
; ~.
;~ ~
= ;.~ :.:, :
=' u~~.r ~; ;~E ,.
~ ~'i ci
i M~ti,if` ~ ;`1L~, t ,P.,...i",ri -L ~ ~ ~
- ~'
~~ z -.clyll ;z,~ ~ _i,r~_.. , ~
l.(i ~'.
, i:
F_pc:~i.)~ ;:'i F:' .i.t' " r-. i
y~ . ~.
.
k~f ~i ~ ~ r I .'~ -
i
~ iv .i ,i i~~~ ' ' ,
:t~ t ;,
i:;Ni ~'
-~,,,~,. J.
~,~~ ., -:0~ ~ ~ ~
n r; i
~," _ ~~ ~~ ~~ ~ ' ' ~ ;
City of Bouider
Utilities Division
GREENWAYS
FOURMILE SUMAC TO 19TH ST.
~~U~~
~ -~
r_r~ ~,~
.
~~ ~
r ~ n c'~ :~ s~'~,~
PROJECT NAME ' Project Number: Map ID #
Maintenance and Weed Control L~J
oepnRrMeHr: .. pW/ Tributary Greenways ~ SusCOMMUNirv: System-wide
Fuy4iN~SOURCE:; °; TributaryGreenways BvCPArea System-wide~~~~~~~W~~ ".
~ PROJECTSTA7US: On-GoingPrqects ~ , ~. ~ ..... ~-
.-: ,... , ,i.;; , _,. :~ .
CEAP REQUIREDfi , Not Requlred ~
PROJECT DESCRIPTION: ' " ' ~ ' ~ ' ~ ~ "' ' ~ ~ ~ ~~ ~~. ' ' ~ "~~ ' '~ '
. ~:-... ........ . . ... . .~ . ...,. „ . . ... . ,
Proposed enhancements to maintenance practices along the Greenways will indude weed control and maintaining
'; the stream corridor for habitat. Specific tasks include retaining a weed consultant and summer crew, purchase of
°;; equipment, control and removal of noxious weeds, and planting of natives to discourage re-establishment of weeds.
_-.: °
are important components of the Greenways Master Plan update.
on
Relatlonship to.Councfl Goals'
'' Maintenance of the Greanways for habitat supports the Council goal of environmantal sustalnabilily.
~ , ..,. . ~ . . : .: ~ . . .: . . - , . ., , .
Relatiooship with Other Depdrtments ° '-- ' ~ ~ ~ ~ ~ ~ ~~ ~ ~ '~° ~ ~'~ ~ ~ ~ ~ ~ ~ ~ ~ ~> i ~ ~'
~~ -~ ~ The weed control plan for Greenways will be developed with input from the Open Space Department, the Parks Department, and Boulder ~
'~~~- County. Initial weed control efforts will be performed on City owned properties, lherefore the projects will be coordinated with ihe managing
~~~~ department.
'~~',35li~...: Gy ~
~~~~' ProjectedR
2002 I 2003 I 2004 I 2005 I 2006 I 2007 I CO PIL T ON I FUNDING
~
PROJECS NAME Pro)ect_ N°. m___,ber° Map ID,,_.___._~.....___~
Miscellaneous - Greenways Operating ~~ ~ ~
oePnaTmeNr: p~V/ Tributary~Greenways suscornMUrnTr: System-wide ~
FUNDING 30}JRCE: , :.: TPibutary Greenways evca nree ~ . Svstem-wide ~ , : ~ ~ ~ ~ ~
PROJECT STATUS: = On-Going Projects
CBAP REQU~RED9 ' I Not ReqWred
.:PROJECTDESCRIPTION:~~: , ~ .,. ~
Rest areas and signage; Habitat survey and corridor assessment; Miscellaneous trail connections and
improvements; Miscellaneous stream restoration and water quality projects.
Relationship to-Master~Plan:
~ ~ ~ I ~ .
~.. i~ .:. .- ~~
~ Public ProcesS SWtus; Issues; i ~' ~ ' .:' ' '
" ' ~
..: RelationshiptoCouncllGoals: ~ -
~.. Relatlonship with Other Departments: ~ ~ ~
i
2002
2003
2004
2005
2006
2007
FUNDING TO PLANNED
COMPLETION FUNDING
ProJected Fundin g: ;
~
~
50,000 50,000 50,000 50,000 50,000 50,000 0 300,000 :~
~
-'
~ ''~ ' ~ ~-~ ~ ~,
, 1stYearofFunding: .~ ~'on-going
,
TOTAL CAPITAL COSTS:
lo
to zoo2:
P
ndi
ooo
$5a
On-Going ng pr
r
u ,
~ ~
~
~
~ ~20D1-Approvedfunds:~_
~~~~~ $54,000
~ '
"
; 17 ,..
SUMMARY OF THE 2002-2007
• UTILITIES CAPITAL IMPROVEMENT PROGRAM
June 26, 2001
Overview
The overall program and funding priorities are reflected in the staging and timing of projects
over the 6 year CIP time period. The following primary factors were considered in determining
the overall program and funding priorities:
Water Utilitv
1. Reliability of water treatment and delivery
2. Drinking water quality and other environxnental regulations
3. Worker health and safety
4. Opportunity to collaborate with other city projects, i.e., transportation
5. Potential for operation and maintenance cost savings
6. Accommodating new growth and development
Wastewater Utilitv
1. Reliability of wastewater collection and treatment
2. Water quality and other environxnental regulations
~ 3. Worker health and safety
4. Opportunity to collaborate with other city projects, i.e., transportation
5. Potential for operation and maintenance cost savings
6. Accommodating new growth and development
Flood Control Utilitv
1. Property damage or safety hazard mitigation
2. Water quality and other environmental regulations
3. Worker health and safety
4. Opportunity to collaborate with other city projects, i.e., transportation
5. Potential for operation and maintenance cost savings
6. Accommodating new growth and development
No effort has been made in developing the CIP to target improvements in a certain
geographic area.
Policy Issues
The following policy issues related to the CIP need to be resotved as part of the 2002-
2003 budget process:
i
South Boulder Creek: The evaluation and planning effort related to flood hazard and
mitigation on South Boulder Creek is continuing. A final "Phase A" report was released in ~
the spring of 2001, but it is unlikely that any of the alternatives in the Phase A report will be
implemented. Additional analysis and community input will be required in order to develop
a plan that will receive community support for implementation and funding. A small amount
of city funding ($3.0 million) has been included in the CIP for year 2003. If a larger project
is approved, a higher rate increase may be required in 2003 or beyond.
Highlights
Highlights of the proposed CIP are as follows:
Water Utilitv
1. Continued emphasis on the rehabilitation and improvement of the City's existing water system
infrashucture continues, especially in the area of the City's deteriorated water distribution
system. This philosophy is reflected in the following CIP projects:
Whittier Neighborhood Distribution System Rehabilitation
North Boulder Pazk Area Distribution System Rehabilitation
Goss Grove Distribution System Rehabilitation
South Boulder Water System Rehabilitation
East Boulder Water System Rehabilitation
North Boulder Water System Rehabilitation
West Boulder Water System Rehabilitation
Corroded Waterline Rehabilitation
Kohler Storage Tank Lining Rehabilitation
Maacwell Storage Tank Lining Rehabilitation
2. Water from the Northern Colorado Water Conservancy District (Colorado Big-Thompson
project) is anticipated to play an increasingly important role in the City's overall water
system deliveries. For this reason several projects have been identified to assure the
reliability of water quality and delivery from the Boulder Reservoir WTP including:
Boulder Reservoir WT'P Improvements
Cherryvale Pump Station
Boulder Reservoir High Service Pump Station
Iris Pump Station
Zone 1 Transmission Facilities
Zone 2 Transmission Facilities
Boulder Feeder Canal
Boulder Reservoir Intake and Pumping
•
3. The capacity expansion of the Boulder Reservoir WTP has been once again delayed due to
the anticipated reduction in peak water demand projections as a result of the City's commitment
to a more aggressive water conservation program. A recent report, the Water Conservation ~
Futures Study, indicates that peak water demands are being reduced and continued reductions
~ may preclude the need for an expansion project.
4. Significant repairs to the Barker water system, recently acquired by the City from Public
Service Company of Colorado, are needed. Repairs to this water system are necessary to assure
safe and reliable water deliveries to the Betasso Water Treatment Plant (W'I'P).
Wastewater Utilitv
1. Although the actual budgetary impact is unknown, funding has been budgeted for potential
impacts associated with renewal of the City's WWTP discharge permit, including a potential
conversion from chlorine disinfection to ultraviolet light disinfection.
2. In accordance with the recent intergovernmental agreement with the City of Lafayette
designed to settle the on-going lawsuit, money has been budgeted to relocate the wastewater
treatment planYs effluent outfall pipe downstream of 75`~' Street.
3. The city is currently involved in a joint study with Western Disposal regarding the feasibility
of a composting facility. The consultant, CDM, is performing the study. If feasible, a Class A
biosolids compost facility may be constructed or managed through some type of "partnership"
contract. The city is also reviewing alternatives to improve the biosolids handling and
dewatering process at the WWTP by installing more efficient centrifuges. This may be needed
in either the composting option or in continuing with the land application program.
~ Flood Control Utilitv
1. As in the past several years, the majority of funds in the Flood Control Utility CIP have been
allocated to major drainage way improvements for Goose Creek - 30th Street to Folsom Street
and Elmer's Two-Mile Creek between Goose Creek and Valmont Road. Work is underway
between 30th St. and through the former Branding Iron Mobile Home Park. The funding
proposed in 2002 would complete the project along Goose Creek through the Mapleton Mobile
Home Park. Funding proposed for 2003 would complete improvement along Elmer's Two-Mile
Creek between under the Boulder White-Rocks Ditch to Valmont Road. Partial funding for this
project is provided by the Urban Drainage and Flood Control District.
2. Money is budgeted for potential flood mitigation improvements along Fourmile Canyon
Creek and South Boulder Creek. Recommendations concerning improvements are anticipated in
the near future as part of the on-going flood mitigation planning process.
Projects Recommended for the CEAP Process
Projects recommended for the Community and Environmental Assessment Process (CEAP) in
the year 2002 are:
• Biosolids Composting
~ ~ Tributary Greenways Program
Fourmile Canyon Creek
Bear Creek -:Arapahoe to Foothills ~
Projects for which Specific Approval is Requested
In accordance with the project planning and approval process, specific approval and allocation of
design and construction funding for the following projects is requested. These projects are
considered minor in nature, with the opportunity for public review and comment provided
through the 2002 CIP budget process. Based on this approval, staff will proceed with the design
and construction of these projects in 2002with no additional public process for purpose, need or
funding, although construction coordination and other site specific activities will be discussed
with adjacent property owners if appropriate.
WATER FUND
Boulder Reservoir WTP Improvements
Cherryvale Pump Station
Boulder Reservoir High Service Pump Station
Iris Pump Station
Kohler Storage Tank Lining Rehabilitation
Maxwell Storage Tank Lining Rehabilitation
Goss Grove Distribution System Rehabilitation
Corroded Waterline Rehabilitation
Zone 1 Transmission Facilities ~
Zone 2 Transmission Facilities
Barker Grauity Pipeline Repair
Barker-Kossler Penstock Repair
Barker Dam Outlet Improvements
Barker Relicensing
Barker In-stream Flow Release
Green Lake II Reconshuction
Como Creek Diversion Structure
Boulder Feeder Canal
Boulder Reservoir Intake and Pumping
WASTEWATER FUND
WWTP/CPDES Improvements
WWTP Pump Rehabilitation
WWTP Trickling Filter Rehabilitation
WVJTP Effluent Outfall Relocation
Biosolids Handling & Dewatering Improvements
Interceptor Sewer Rehabilitation
Collector Sewer Rehabilitation
Manhole Rehabilitation ~
~ FLOOD MANAGEMENT FUND
Preflood Acquisition
Crossroads Redevelopment
Master Planning
Master Planning is an element of the decision making process for proposed CIP projects.
Historically, these master plans focused on service area growth and its impact on reIated utility
infrastructure needs. At this point in time, growth is not as important an issue as the need to
rehabilitate and address deficiencies in the existing infrastructure. Identification of these issues
occurs on an on-going basis and ara documented in the Utilities Division Annual Reports as well
as on-going studies and reports.
Master plan summaries are provided in the Boulder Valley Comprehensive Plan and were
recently updated. At this point in time existing master plans provide an adequate basis from
which to formulate tha CIP in conjunction with other information. Exhtbit A provides a
summary of the studies and reports that provide important information regarding the various
wark programs of the Utilities Division and are used in formulating the CIP.
The relationship of each CIP project to the master plans and studies is presented in the detailed
project descriptions.
~ It may be necessary to revise current master plans depending on the extent of changes to the
Boulder Valley Comprehensive Plan including land use designations. For this reason,
anticipated projects in the years 2004-2007 are preliminary and are based on the judgement of
Utilities Division staff:
Financing
Funding for the City's Utilities capital improvement projects is derived from general utility fees
and special external agency grants. The primary revenue sources are Plant Investment Fees
(PIFs) from new customers, monthly water sales to customers and hydroelectric sales to Public
Service Company of Colorado (PSCO). Water sales are relatively stable and reflect the overall
growth of the service area and yearly weather fluctuations.
Other revenue sources include the Colorado Department of Public Health and the Environment
construction revolving loans (none anticipated at this time) for the Wastewater Utility; and the
Urban Drainage & Flood Control District reimbursement grants for the Flood Control Utility.
These revenues are project specific and are highly variable depending on the external agency's
funding situation and priorities. Currently, the following projects are anticipated to qualify for
such revenues:
• Flood Control Utility, Goose Creek
~ • Flood Controt Urility, Elmer's Two-Mile Creek
Flood Control Utility, Fourmile Canyon Creek
Flood Control Utility, Preflood Acquisition
Another possible source of funds are special assessment districts and assessments levied as part
of annexation agreements. These types of funding mechanisms are anticipated for the Water and
Wastewater System Expansion projects.
If the above mentioned funds are insufficient, projects will be funded from new revenue bond
issues with debt service financed by general utility charges. For the year 2002-2003 CIP, it is
anticipated that bonds will be issued for the following projects:
Wastewater Utility - WWTP/CPDES Improvements
Wastewater Utility - Biosolids Composting
Wastewater Utility - Biosolids Handling & Dewatering
Flood Control Utility - Fourmile Canyon Creek
Flood Control Utility - South Boulder Creek
Also, it is anticipated that projects related to the Barker Water System will be funded from the
proceeds of the Windy Gap water sale.
Staff will complete the evaluation of the proposed CIP on rates in conjunction with the
development of the 2002 operating budget. Rate increases are currently projected as follows:
Water Utility:
Wastewater Utility:
Flood Control:
2002 - 9 percent
2002 - 12 percent
2002 - 8 percent
2003 - 3 percent
2003 - 12 percent
2003 - 8 percent
~
.
Public Process
The draft CIP was presented to the Water Resource Advisory Board (WRAB) on April 16, 2001
for discussion. A public hearing before the WRAB concerning the CIP was held on June 18,
2001. The WRAB recommended approval of the proposed Utilities Division 2002-2007 Capital
Improvement Program (CIP) including the preliminary year 2002-2003 operating budget,
monthly utility rates and plant investment fees to the Planning Board and City Council.
i
• EXHIBIT A
CITY OF BOULDER
UTILITIES DIVISION
SUMMARY OF STUDIES AND REPORTS
June 14, 2001
The following studies and reports provide important information regarding the various work
programs of the Utilities Division and are used in formulating the CIP:
Water Resources and Untreated Water Deliverv
Master Plan for the City of Boulder's Mountain Reservoir Water Supply System, Li &
Associates, 1985
Update of Priorities and Cost Estimates in the City of Boulder's Master Plan for Mountain
Reservoir Water Supply System, Simons, Li & Associates, 1986
Raw Water Master Plan, WBLA, 1988
Condition Assessment & Remedial Measures Feasibility Study for the City of Boulder
Watershed Dams, Harza Engineers, 1988
Barker Pipeline Rehabilitation and Related Improvements Study, Harza, 1991
Water Source Impact Assessment, Brown & Caldwell, 1992
Silver Lake Hydroelectric Project Conceptual Design Report. ECI, 1992
~ Lakewood Pipeline and Hydroelectric Project Environmental Report and Associated
Studies, Pazsons Engineering Science, 1994
Lakewood Pipeline and Hydroelectric Project CEAP, City of Bouider, 1994
Silver Lake Pipeline and Hydroelectric Project CEAP, City of Boulder, 1996
Water Treatment and Treated Water Deliverv
Water Facilities Master Plan, Black & Veatch, 1984
Gunbarrel/Heatherwood Area Water and Sewer Utility Master Plan, McLaughlin
Engineers, 1988
Treated Water Master Plan - Phase I Study, Brown & Caldwell, 1990
Corrosion Control Evaluation Study, Black & Veatch, 1990
North Boulder Area Water and Sewer Master Plan, McLaughlin Water Engineers, 1990
Pre-design Report for Corrosion Control and Miscellaneous Water Treahnent Plant
Improvements at Betasso WTP, Black & Veatch, 1991
Treated Water Master Plan - Phase II Study, Brown & Caldwell, 1992
Betasso WTP Sludge Drying Bed Study, Richard P. Arber, 1992
Pre-design Report for Corrosion Control and Miscellaneous Water Treatment Plant
Improvements at Boulder Reservoir W'TP, Black & Veatch, 1995
Hydraulic Analyses, City of Boulder, On-going
Residuals Improvements and Recycle Pretreatment at the Betasso Water Treatment Plant,
~ Black & Veatch, 1997
Treated Water Master Plan Update, Integra Engineers, 2001
Wastewater Collection and Conve,~~ ~
Wastewater Collection System Master Plan Update, McLaughlin Water Engineers, 1983
Gunbarrel/Heatherwood Area Water and Sewer Utility Master Plan, McLaughlin
Engineers, 1988
North Boulder Area Water and Sewer Master Plan, McLaughlin Water Engineers, 1990
Sanitary Sewer Sub-Basin Evaluation for Infiltration and Inflow, RTW, 1996
Hydraulic Analyses, City of Boulder, On-going
Wastewater Treahnent and Discharee
Wastewater Treatment Facilities Master Plan, Brown & Caldwell, 1990
Wastewater Treatment Facilities Plan Amendments, City of Boulder, 1992
Disinfection System Evaluation, Integra Engineering, 1996
Sludge Processing and Dis osal
Sewage Sludge Management Master Plan - Phase I, Richard P. Arber, 1986
Sewage Sludge Management Master Plan - Phase II, Richard P. Arber, 1986
Sludge Disposal Options Study, Richard P. Arber, 1990
Biosolids Recycling Land Acquisition Project CEAP, City of Boulder, 1995
Biosolids Management Study, RTW, 1997 ~
Flood Control and Drainaee
Comprehensive Drainage Utility Master Plan, City of Boulder, 1988 Boulder and
Adjacent County Drainageways - Phase B, Greenhorne and O'Mara, 1987
Storm Water Collection System Master Plan, WRC Engineering, 1984 Gunbarrel Area
Drainage, Boyle Engineering, 1987
Master Plan for Boulder Creek Tributaries, Clack, Greenlee, Hartman & Tucker, 1985
Outfall System Planning, Boulder Gunbarrel Area, Boyle Engineering, 1987
Tributary Greenway Master Plan, City of Boulder, 1990
High Hazard Zone Property Acquisition Analysis, Love & Associates, 1997
Boulder and Adjacent County Drainageways - Phase A, Greenhorn & O'Mara, 1984
University of Colorado at Boulder - Reseazch Park - Master Plan Site Development Plan
and Flood Mitigation Plan, Downing, Thorpe, James, 1989
University of Colorado at Boulder - Reseazch Park - Master Plan Site Development Plan
and Flood Mitigation Plan, Downing, Thorpe, James, 1987
North St. Vrain and St. Vrain Creeks, Engineering Professionals, 1983
Boulder and Adjacent County Drainageways - Flood Hazard Area Delineation,
Greenhorn & O'Mara, 1987
South Boulder Creek - Flood Hazard Area Delineation, Greenhorn & O'Mara, 1986
Boulder Creek/South Boulder Creek Confluence Area - Development of Preliminary Plan ~
- Phase B, Simons, Li & Associates, 1984
8
Lower Boulder Creek - Flood Hazard Area Delineation, Muller Engineering, 1983
~ Lefthand Creek Volume 1- Mouth to Foothills Highway, Gingery Associates, 1981
Upper Lefthand Creek Volume 2- Foothills to Peak to Peak Highway, Simons, Li &
Associates, 1983
Boulder Creek - Flood Hazard Area Delineation - Muller Engineering 1983
Upper Boulder Creek & Fourmile Creek - Floodplain Information Report, Gingery
Associates, 1981
Boulder Creek - Phase B Preliminary Design, URS, 1979
Major Drainageways Planning - South Boulder Creek Volume II, RW Beck &
Associates, 1973
Boulder Creek & Major Tributaries - High Hazard Flood Zone - 0.5' Rise Floodway,
Love & Associates, 1982
Major Drainageways Planning - Urban Storm Drainage - South Boulder Volume 2-
Wright McGlaughlin, 1970
Goose Creek Project CEAP, City of Boulder, 1998
Fourmile Canyon Creek Major Drainageway Planning, Phase A Report, Alternatives
Analysis, Love & Associates, 2000
.
.