6 - Review process for the relocation of the landmarked 1890 Union Pacific DepotMEMORANDUM
February 7'h, 2007
TO: Landmarks Preservation Advisory Board
FROM: Susan Richstone, Acting Long Range Planning Manager
Bill Boyes, Manager, Facilities and Asset Management
Alice Gilbertson, Historic Preservation Intern
Chris Meschuk, Historic Preservation Planner
James Hewat, Historic Preservation Planner
SUBJECT: Review process for the relocation of the landmarked 1890
Union Pacific Depot.
ITEM & ISSUE:
In June of 2006, the City Council reviewed options for the relocation of the 1890
Union Pacific Depot from its current location at the CrossRoads shopping plaza
which is owned by the Regency Retail Partners. The Council chose not to opt for
a proposal to dismantle and store the building until a final location for the
building was secured, but rather to move the building as a whole to a location in
the Transit Village Area (see Attachment A). As part of its motion, the Council
issued a landmark alteration certificate for the building to be moved, employing
the whole building approach as outlined in the staff inemorandum, a condition
of which was that details regarding the methodology of the move be submitted
for review and approval by the Landmarks design review committee (see page 2,
item 2a of Attachment B).
To this end, Facilities Asset Management (FAM) has contracted with a team
consisting of Margaret Hansen, engineer Henry Lopez, and building movers
Rocky Mountain Structural to prepare a detailed report outlining:
Steps that will be taken to prepare the building for the move including
additional bracing and masonry reinforcement;
Detailed methodology for the initial lift and move to a temporary location
(either on the Pollard site south of Goose Creek or to a site just north of
Goose Creek);
S.\PLAN\data\longrang\HIST\DEPO'I~02 07.07 Landmarks Board doc 2/1/2007
• Steps that will be taken to mothball, secure, and maintain the building
during the temporary storage.
• An outline of inethodology that will employed when moving building to
its final location.
This repart will be submitted to the design review committee by FAM far review
and approval by the design review committee once a temporary storage location
has been chosen and the consultants complete their moving, mothballing, and
maintenance report. It is anticipated that completion and review of the report
will occur at the beginning of March, 2007.
ATTACHMENTS:
A Minutes from the June 6, 2006 City Council meeting
B June 6, 2006 Staff Memo to the City Council regarding purchase and
landmark alteration certificate for moving of 1890 Union Pacific Depot
S.\PLAN\dataUongrang\HIST\DEPOT02 OZ07 Landmarks 6oard doc 2/I/2007
Attachment A
Councilmember Schultheiss moved seconded by McGrath, to direct staff to come back
with a pmnosal for a greenhouse aas tax with several options for fundins mechanisms.
The motion carried 9:0.
C. ITEMS RELATING TO THE 1891) UDTION PACIFIC DEPOT PURCHASE AND LANDMARK
ALTERATION CERTIFICATE: - 9:$5 P.M.
1. SECOND READING AND CONSIDERATION OF AN ORDINANCE NO.'7473
AUTHORIZING THE CITY MANAGER TO ENTER INTO AGREEMENTS RELATED
TO Tl~ PURCHASE OF THE 1890 UNION PACIF[C DEPOT LOCATED AT 2275
3O~ STREET (THE "DEPOT")~ ENTER INTO AGREEMENTS TO MOVE THE
DEPOT~ GRANT A RESATE FOR THE GENERAL FUND PORTION OF THE
CONSTRUCTION USE TAX FOR TAE REDEVELOPMENT OF THE CROSSROAD
COMhiONS PUD AMENDMENT FOR 1'HE PURPOSE OF PURCHASING AND
MOVING 7'I~ DEPOT~ AND IMPLEMENT TAE NECESSAHY STEPS TO MOVE THE
DEPOT.
2. PUBLIC HEARIIVG AND CONSIDERAT[ON OF A LANDMARK ALTERATION
CERTIFICATE APPLICATION TO MOVE THE 1890 UHION PACIFIC DEPOT
LOCATED AT 2275 30TH STREET
The hearing on this item will be held under the quasi judicial procedures of
Chapter 1-3, BRC 1981.
The public hearing was opened: ~
1. Betty M. Chronic, 4105 Shawnee Dr., noted that 1971 began the saving of the !
depot. 35 yeazs tater Council is faced with another proposal. She is opposed '
to dismanding, and urged Councii to move immediately, and take ac6on now
on a policy decision to preserve this jewel.
2. Debra Ordway, 3820 N. 26~, spoke to her concern about the "2°d floor at
Whole Foods" and parking lot constraints as well as the construction of the
shopping center where the depot curnntly stands.
3. I.ee Peters, 6803 Jay Rd., representing Boulder Pow Wow, requested the
removal of option three, and requested the depot be moved intact and
promptly.
4. Bud Sorenson, 603 Spruce St., a boazd member of Whole Foods for the past
12 years, suggested Council relocate the depot to a location more in keeping
with its historic value. Whole Foods would like to expand the store to benefit
shoppers in Boulders. The store is a lazge sales t~ payer, employer, good
corporate citizen, key player in the natural foods industry in Boulder, and
100% wind-powered.
5. Curt Williams, speaking on behalf of the Boulder Jaycees, is anxious to see
the building move to the transit village. He encouraged council to make
relceation and preservation a reality.
~ ]une 6, 2006
6. Will Pazadise, president of Whole Foods Rocky Mtn. division, noted that the
local store is arguably the most successful store in the company's hisfory.
They want to build the best, the flagship store in Boulder, and to see the depot
moved and used.
7. Lynn Segal, 538 Dewey, believes it would be better to have small grocery
stores ali over town rather than superstores. She asked whether Who]e Foods
would consider moving into an additional smaller store.
8. Deborah Fmbe, No address given, spoke on behalf of Regency Centers. She
explained the basic plan and the developers concerns for the Depot. They are
very excited about this remodel
There being no further speakers the public hearing was closed.
Councilmember Gray moved, seconded bv Polk to adovt Ordinance No. 7473
into agreements to move the Depot; Qrant a rebate for the general fund portion of
the construction use tax for the redevelo~ment of the Cmssroad Commons PUD
Amendment for the puroose of purchasina and movin¢ the depot: and implement
the necessarv steps to move the Denot. The motion carried 8:1, Stoakes opposed.
Counciimember Gray moved, seconded bv Polk to accent the landmark alteration
certificate aDnlication to move the 1890 Union Pacific Depot located at 2275 30th
Street with the removal of disassembly option item iii and ]ast sentence in
statement # 5(vaQe 36). The motion camed 6:2. A~eton and Schultheiss
o~„posed. Stoakes absent.
Councilmember McGrath moved. seconded bv Aaeton to suspend the rules and
continue the meetine. The motion carried 6:2. 3chultheiss and Eldrid~e onoosed,
Stoakes absent
-11:18 p.m.
D. BTV SQ CONTRACT UPDATE
1. Tim Thomas, 2300 Arapahce Ave., noted the high quality of the video, and
that the business plan detail is above standard. He commented that city
departments should have so much detail in their business plans.
2. Lynn Segal, 538 Dewey, voiced her support for Channel 54 particularly if they
air "Democracy Now".
3. Sally Martin, noted that the 3 PEG channels were supposed to be equal, but it
has not tumed out that way. She supports the $10,000 for Channe154, and
suggested Council hold a study session regazding the 3 PEG channels.
There being no further speakers, the public hearing was closed. - 11:58 p.m.
lune 6, 2006
~
Attachment B
CITY OF BOULDER
CITY COUNCIL AGENDA ITEM
MEETING DATE: June 6, 2006
AGENDA TITLE:
Items relating to the 1890 Union Pacific Depot purchase and landmark alteration certificate:
1. Second reading and consideration of an Ordinance authorizing the city manager to enter
into agreements related to the purchase of the 1890 Union Pacific Depot located at 2275
30t° 3treet (the "Depot"); enter into agreements to move the Depot; grant a rebate for the
general fund portion of the construction use tax for the redevelopment of the Crossroad
Commons PUD Amendment for the purpose of purchasing and moving the
depot; and implement the necessary steps to move the Depot.
2. Public hearing and consideration of a landmark alteration certificate application to
move the 1890 Union Pacific Depot located at 2275 30th Street.
The hearing on this item will be held under the quasi judicial procedures of Chapter 1-3, B.R.C.
1981.
PRESENTER/S:
Planning & Development Services
Peter Pollock, Planning Director
Ariel Calonne, City Attomey
Maureen Rait, Director of Public Works for Development and Support Services
Brad Power, Redevelopment Director
Marie Zuzack, Planner
EXECUTIVE SUMMARY-
The puipose of this agenda item is for City Council to consider an ordinance approving purchase
of the Depot by the city from the Jaycees and approving the rebate of the general fund portion of
the construction use tax on the redevelopment of Crossroad Commons Shopping Center, where
the Boulder Jaycees Train Depot is ]ocated. The item also includes Council consideration of a
landmark alteration certificate approval by the Landmarks Preservation Advisory Board to move
the Depot to a new location with certain cbnditions. If the Counci] supports purchasing and
moving the building, staff seeks Council direction on which of several possible moving strategies
to pursue.
The proposed redevelopment of Crossroad Commons provides an opportunity for the city and
the Jaycees, a non-profi[ organization, to realize a mutual, long-term goal of transferring
ownership of the Depoi from the Jaycees to the city and relocating this historic landmazk to a
more suitable setting. The city and~the Jaycees;have attempted to accomplish this on severai
occasions since the mid-1980s. The owner of Crossroad Commons, Regency Retail Partners
("Regency"), has offered to move the Depot from its shopping center parkiug lot to another
temporary or permanent location, to be selected by the city, provided this can occur,by Mazch
2007. Relocation of the Depot could facilitate substantial redevelopment of the center, enabling
successful retailers to expand, impmving the safety and convenience of site access, and making
the pazking lot more efficient. However, the logistics and costs associated with relocating and
restoring the Depot are significant challenges.
Key issues for this project include: the.purchase of the.De,pot; a rebate of the general fund
portion of the Crossroad Commons redevelopment construction use tax; idenufication of the
relocation site for the buiiding;,the strategy for relocating,the building; and the.cost of and
funding for relocating and restoring the building.
STAFF RECONIMENDATION:
StafF recommends that the City Council take the following actions:
1 Purchase Move Tax Rebate and FundinQ
Staff recommends that the City Counci] adopt the attached ordinance authorizing the city
manager to: enter into agreements to purchase and move the Depot; grant a rebate for the general
fund portion of the construction use tax for the redevelopment of the Crossroad Commons PUD
Amendment for the purpose of purchasing and moving the depot; and implement the necessary
steps to move the Depot. Because it is anticipated that the funding provided by Regency will not ~,
be sufficient to complete the move, restoration and preservation of the building, staff
recommends that the City Council direct staff to seek additional funding for'`the project.
2. Landmark Alteration Certi£icate
Staff recommends that the City Council approve the landmark alteration certificate, adopting the
findings in Attachment H, to move the Depot, subject to the following conditions:
J a. The detailed methodology as to how the relocation will occur shall be subject to
the review and approval of the design review committee of the Landmazks Board;
'' b. Prior to any move, the City and the Jaycees shall be required to enter into a
mutually agreeable contract for the City to city to purchase t}ie Depdt;
~ c. Prior to any move, the City and owners of ]and upon which the Depot now rests
execute of an agreement regazding the each par[y's responsibilify pertaining to the
relocation of the Depot, including financial obligarions;
~d. Prior to or concurrent with any application to move the Depot to its final location,
the applicant shall submit an application to re-designate the Depot as an
individual landmark in its new location; and
,~ The relocation of th'e Depot shall be moved based on the following circumstances
~~ and conditions:
~
The first preference is to move the building intact to a permanent location
in the Boulder Transit Village area if:
A. A permanent location for the Depot is deternuned through the
TVAP process and is available (including any necessary land
purchase) by Mazch 2007 (at the earliest or such later time as
Regency needs the building moved), and
B. Adequate funding is identified and pledged for moving the
building and piacing it on a permanent foundation.
ii. The second nreference is to move the
to a
neaz the permanent site or at the city-owned site at 30`° & Peaz] if:
A. A permanent location for the Depot is determined through the
TVAP process but it is not available by March 2007 (at the earliest
~Y ~ or such ]ater time as Regency needs the building moved), and
~nu
~~ B. Adequate funding is identified and pledged or otherwise
~ ~-y~1 appropriated foi moving the building, placing it on a permanent
U' ~~ foundation, and purchasing land (if necessary), and
~~
~% C. If the temporazy ]ocation chosen is the citv-owned site at 30~' &
Pearl the buildine could be removed b March 2008 (at the
eazliest or such later time as the site work or other redevelopment
activities on the city-owned site necessitates removing the
building).
\~ii. The third preference is to disassemble the building and store it at the city-
~~~ owned former "egg fazm" or such other location as detennined by the city
manager until a permanent location and adequate funding are secured if a
permanent location is not deternvned or not available by March 2007 (at
the eazliest or such later time as Regency neens the building moved)
and/or adequate funding is not identified and pledged for Phases 1& 2&
land acquisition.
COITNCIL FILT'ER IMPACTS:
• Economic: The Crossroad Commons Shopping Center houses several successful national
and local retailers. In fact, Whole Foods Mazket is one of Boulder's top-performing
retailers in terms of local sales tax generarion. The proposed redevelopment plan that
assumes the relocation of the Depot would almost double the size of the Whole Foods
store (to approximately 75,00~ squaze feet), and would develop a new, two-story Bames
& Noble store at the corner of 30~' and Peazl Streets. These expanded retailers would not
only serve as strong anchors for the shopping center, they would also be key to ensurin~
that other retail centers in the Boulder Valley Regional Center (BVRC) and the 28~'/30
Street corridor remain viable into the future. Many national retailers desire locations in
proximity to frequendy visited stores such as Whole Foods.
-7
Environmental: City purchase and relocation of the Depot would likely ensure the
Depot's long-term preservation, which is a form of re-use.
Social: The Boulder Jaycees, a local, non-profit service organization, will lose the Depot
space it has historically used for its ~neetings if the Depot is moved. The Boulder Jaycees
have also, in the past, rented this space at a reasonable rate to individuals and groups.
Whole Foods has offered to provide meering space for. the Jaycees after the proposed
Whole Foods' expansion. During construction, the Jaycees plans to meet at CU.
OTHER IMPAGTS:
• Fiscal: Depending on the strategy selected for moving the Depot, the fiscal impact of the
project could range from $'1,302,500`to $1,733,000.~'This represents the range of total
estimated costs for the project not inc]uding Phase 1, which Regency has offered to pay
for, and not including the difference between $535,000 and the first phase costs, a
difference which Regency has dffered to pay to the city for use on subsequent phases of
the project if tlie ~rst phase costs are less ttian $535,000. The total project cost assumes
moving the Depot to a temporary location, purchasing land for the permanent location,
moving the building to the permanent location, restoring it, and finishing the interior and
exterior for a non-specific use. It does not include the cost of purchasing the Depot from
the Jaycees, which'will be nominal -$10. Phase l of the project entails moving the
Depot to a temporary location: (The details of Phase' 1 for each of four different moving
strategies aze provided in the narrative portion of Attachment B.) The $535,000 figure is
the amount of an earlier cost estimate fot'Ph'ase 1 of moving the Depot intact to the
Transit Viilage area. A number of possible outside funding sources have been identified
for the fiscal impact, but aze not assured: `~
• Staff time: Regency will take the lead in [he first phase of relocating the Depot, and will
oversee the moving contractors' work and remediarion of the present Depot building site.
City staff will assist with any necessary temporary street and utility modifications and
associated off-site logistics. The subsequent phases of th'e pmject - placing the building
at a final location, finishing, restoring; and maintaining the building - would be city
staff's re'sponsibility: If RTD or a private enfify were to lease or purchase the buiiding,
less or no further'staff involvement would be necessazy.
BOARD AND COMNIISSION FEEDBACK:
Because the Depot is a designated landmark, on April 5, 2006'the Landmarks Preservation
Advisory Boazd considered a landmazk alteration certificate application to temporarily relocate
the Depot untii a final site is ready for the building. The Boazd v.oted 5=0 to issue a certificate to
relocate the Depot to the Transit Village azea, subjecYto certain conditions: 1) design review
committee review and approval of a more detailed methodology as to how the relocation would
occur; 2) execution of a contract between the city and the Jaycees for the city to purchase the
Depot; 3) execution of an agreement between the city and Regency Retail Partners regarding the
each party's responsibility pertaining to the relocation of the Depot, including financial
obligations; and 4) moving the building intact, and the means of temporary storage are not
limited to solid temporary foundations.
~
During discussion of the item, board members expressed concem that disassembling the building
may no[ be the best approach from a historic preservation standpoint and that a permanent
location should be found prior to moving the building so that only one move would be necessary.
PUBLIC FEEDBACK:
Much of the feedback from the public has been from members of Historic Boulder, Inc. and
members of the former Depot Task Force. Most support moving the Depot intact to the Transit
Village hub area and preserving it. They aze concemed about storing the building in a temporazy
]ocation without funding eazmazked for the fina] move and restoration. They believe the city
should select a permanent location for the building, move it directly there, and plan development
around it as a community amenity that is significant in the history of the community. One task
force member supports disassembly and suggests fundraising for the reassembiy by having
donors "adopt" a stone and also employing tax increment financing on the Crossroad Commons
redevelopment.
The Transit Viilage Area Plan (TVAP) charrette on May 18-20, 2006, explored the desired
chazacter, transportation network and land uses for the Transit Village hub area, and within that,
a final location for the Depot. Charrette participants included approximately 50 members of the
public and uea property owners, numerous members of Planning Board, Transportation
Advisory Board and City Council, designers from two consulting urban design firms, and staff
from the Planning, Housing and Human Services, and Transportation departrnents. A consensus
seemed to develop for locating the Depot north of Goose Creek at the end of Bluff Street, in
proximity to the future rail platform, in conjunction with a civic plaza. The final location and
future use of the Depot will be determined through adoption of the TVAP by Planning Board and
City Council.
The Boulder Jaycees, owners of the Depot, have expressed support for relocating the building as
a means to ensure preservation of the building. The Jaycees also have stated that its other major
concern - continuing to have a meeting place for its organization - has been met by an
arrangement for future meeting space with Regency and Whole Foods. In addition, the Jaycees
have made it cleaz that they are not in a position to assist with relocation itself or to take the lead
in a fundraising effot to support the project. The Jaycees also warned of a possibility that if the
Boulder chapter's membership number remains below Jaycees state organization guidelines, the
local chapter's assets, including the Depot building, could convert to state organization
ownership. Additionally, they have expressed a desire for the Boulder Jaycees' name to continue
to be identified with the Depot, to acknowiedge that the 7aycees were responsible for saving the
building from destruction in 1973 and have served as its steward for the last 33 years.
Regency Retail Partners, owner of the land on which the Depot sits, has expressed support and
pledged funds for moving the Depot. Letters from Regency and the Jaycees are found in
Atrachment G.
ANALYSIS:
Four different strategies have been analyzed that would realize an ulrimate goal of moving the
Depot from Crossroad Commons to a more appropriate location, restoring and preservina the
historic integrity of the building, and ensuring that it remains a functional community asset. The
fifth strategy is to leave the Depot in place.
~
Rationale
There are a number of reasons that staff is recommending purchasing and moving the Depot,
rather than leaving it as is.
Removing the Depot from Crossroad Commons would enable Ihe shopping center to redevelop
into a more urban and space-efficient configuration. The BVRC Desigu Guidelines indicate that
the district should evolve to an urban character:as redevelopment occurs over time. The
guidelines include locating buildings adjacent to streets; the developmeqt:of multi=story
commercial buildings, and parking that serves multiple stores. The proposed redevelopment of
the Crossroad Commons would place a new, two-story Barnes & Noble store at the intersection.
of 30`° and Pearl Streets. The existing pazking conditions on the site aze undesirable, given the
high volume of shoppers, particularly at Whole Foods. Addirional parking will ease congestion
in the area and will provide Whole Foods and other tenants a better opportunity to increase
e~ciency, and the potential to enhance their sales. A redevelopment plan that enables the center
to utilize the ground currently occupied by the Depot has the potenrial to further increase the
productivity of.W.hole Foods and the other retailers in the center.
Another reason is that the DepoYs current setting - in the pazking-lot of a shopping center - is
dot suitable given the building's historic significance and architectural distinction. The present
siting close to the movie theater building limits visibility and.appreciation of the historic track-
side (south side) of the building. In.addition, the pazking lot on'which the Depot sits suffers from
poor drainage. This periodically floods the interior of the Depot and further deteriorates the
building. If relocated fo the:Transit Village hub area, the building's historic association with
public transit could be restored, and the building's use could support and enhance the azea's
transit function.
Additionally, city intervention is to relieve the Jaycees of the burden of responsibility it assumed
in 1973, when it took ownership of the building to prevent probable demolition by the city. This
burden has become increasingly heavy; as overhead and maintenance costs for the'building have
grown faster than revenues from periodic rental of the building for events and meetings. Since
the mid-1980s the Jaycees have expressed a desire to transfer ownership of the building back to
the city. As a non-profit community service organization, the Jaycees resources are lunited; the
organization believes that its continued upkeep of the Depot is not financially sustainable long-
term. The organization prefers td devote its time and resources to service projects, rather than to
property management.
Furthermore, by intervening and taking ownership of the building, the city can take steps to
repair; restore and preserve the building as a historic landmark.
Proposed City Actions
All the strategies analyzed except the "leave in place" scenario assume the following actions by
the city:
1) Purchase the building
The city would purchase the building from the Jaycees for a nominal amount, $10. The
transfer of ownership would occur when the Depot is removed from its present site. The Jaycees
~~
would have meeting space for its organization in the redeveloped Whole Foods facility. The
purchase proposal is in the form of an ordinance, which is included as Attachment A.
2) Rebate construction use ta1c, in return for fnancial assistance from Regency
Staff is proposing that the relocation and refurbishment of the Depot be accomplished
through a public/private partnership between the city of Boulder and Regency Centers, the owner
of the Crossroad Commons Shopping Center. Under the proposal ~~e~~vr~1~=,gay_for the
__. ___ _.._ _ . __
fqliowing,~l.~ che~first-phase of;the;m~g,~i£'~2.co'sts ~535;~0 ro`r7iiore"` r~~if the ~rsi pl~ase costs
- - - - - - ----__='_- - -.. :-~-; _,._ _... ._~.,:..._-~.T_.. - -
. .. -----r - -• " -
=._ , _ -.~.. - -- - _ _....,.
tlre re~leye~npment.o _ es opp~~n ` The general fund portion of the construcuon use tax
from e pro~ect is currently esUmated to be $156,000. However, this is likely to change as
Regency's redevelopment plans aze reviewed and modified and costs are refined. The rebate of
the ta~c is proposed to the Counci] in the form of an ordinance, which is included as
Attachment A.
3) Secure additional funding for completing project
Significant additional funding - beyond the Phase 1 funding provided by Regency - will
be needed to move and finish building in its final location. The funding shortfall is estimated to
be approximately $1,302,500 to $1,733,000, depending on the strategy selected. The table on
Attachment C lists a cost estimate and potential funding sources for each phase of the four
different strategies.
Funding Options
The following aze potentia] sources of funds:
0
Prior fundraising: $45,996 is available from prior fundraising for the Depot.
This money was raised in the late 1980s by the Depot Project, a coalition of civic
groups, individuals and city govemment, as part of a campaign to move the Depo
to Central Pazk. Fundraising included selling artistic posters, as well as
decorative bricks to be placed azound the building in its final location. The fund
is held in trust by the Boulder Pazks and Recreation Foundarion, and its use woul
be subject to Pazks Foundation Boazd approval, based on a£nding that the use o
the money is consistent with the original intent of the fundraising. The
fundraising project budget included moving the Depot, refurbishing it, and
enhancing the exterior. However, the project did envision its location in a pazk.
The Board may not approve using the funds for a temporary move, and may
stipulate that some portion of the fund be reserved to honor the donations for
bricks.
o Remaining Regency funding: Any remaining funds from the $535,000
minimum that Regency has committed to the initial Depot move will be paid to
the city for use to complete the relocation and interior finish of the building.
o RTD First Phase Regional Bus/ BRT Facility funding: RTD has a$7.8 million
federal grant to design and construct the first phase bus/ BRT (bus rapid transit)
~°~'!~
~~~
~
C~
~G~~~
~~
G~ ~-G~
t ~~n„n
,~,~.-
d Lx~~2~
f G~~CC~(~"
/I
station on the RTD portion (3.3 acres) of their site at 30~` and Pearl for 2006-
2008. As part of the budget estimates developed for the grant, RTD has identified
$25,000 for relocation of the depot, and $250,000 for restoration of the building.
Although funding~has been identified in th8 grant, it should'be noted'that RTD is
not required to use the9e'federal funds foi the Depot. RTD has stated that if these
federal grant funds were used for the Depof; one cbndition of fduding would be
that the building would need to be used as a transit function, and other issues,
such as building owneiship, use, maintenance and additional funding for
relocation ~and rehabilitation; would need to be resolved. Any local or regional
transit function for the building would need to be reviewed and approved by RTD.
However, "it should be noted that RTD is pursuing train platfonns that have
automated ticket vending operations, rather'than stations requiring personnel. It is
uncleaz whether RTD would pursue a commercial use in association wifh regional
transit service, such as a coffee shop or flower shop. Funding fmm RTD for the
Depot as a uansit use woUld be Supp7emental tb ~signifieant other funding sources
and should not be seen as potentially the bulk of the funding for the Depot. A
secondary concern of city staff is that since construction costs have risen
significantly, it is possible that the grant amount may be insufFicient to adeguately
cover the bus station and associated infrastructure; let alone the Depot.
o Future Commuter Rail'fu"nding: RTD'has been asked wliether funds might be
available as part of Fastracks or some other transit source as part of the future
commuter rail implementation. RTD plans for commuter rail implementation are
in 2014, with planning for the commuter rail after completion of the US36EIS
(most likely 2007-2010). RTD Facilities Management is currently iuvestigating
this question.
Colorado Historical Society grant: The Colorad'o Historic Society (CHS)
awazds grants for historic building rehabilitation. Tlie last round of grant awards
included funding for'projects up fo $220,000. In ttie past,'larger grants have been
awazded, and there is no limit. There aie two gtant cycles annually. The grants
are very competitive, as there is great need azound th'e state. A 25% match is
required, unless a waiver is granted. In 1999 the CHS funded a report on the
Depot by the Jaycees (entitled "The Boulder Jaycees D'epot Building Report on
Rehabilitafion, Re=use; and Re-location"). This piecedenf'will sErengthen a grant
application for the building's rehabilitation. However, the CHS will not consider
funding until the building is on'a permanent fouridation and re-designated as a
landmazk. The organization also has indicated that disassembly of the building
would likely preclude eligibility for a grant. ~
Federal Transportation Enhancement Funds: Federal transportation funds for
the Denver metro iegion aze allocated by the Denver Regional Council of
Governments (DRCOG) through a competitive funding process called the
Transportation Improvement Program (TIP). The TIP process occurs every two
years and is governed by TIP criteria adopted by the DRCOG Boazd of Directors.
There is no opportunity for funding from DRCOG outside of the TIP process.
1..~-
DRCOG is cutrently in the final stages of adopting the 2007-2012 TIP. Project
submittals for this TIP were due in September 2005; the next round of TIP
submittals will be in the fall of 2007 for the 2009-2013 TIP. Funding in the first
yeaz of the TIP is typically very limited, so funding will likely be available in the
federal fiscal year 2010, which begins October I, 20Q9.
Transportation-related historic preservation projects aze one of seven project types
that may be funded through the "Enhancements" funding category. However, the
Enhancements funding category also funds bicycle and pedestrian projects, which
have been a policy priority for the DRCOG Board and very popular with DRCOG
member governments. Consequently, this category is the most over-subscribed
portion of the TIP. For the 2007-2012 TIP, 35 bicycle/pedesuian projects with a
total project cost of $31.6 million were submitted for a total of $5.8 miilion in
federal funds. This demand for bicycle/pedestrian pmjects resulted in the
DRCOG Board directing additional funding from another funding category to
bicycle/pedestrian projects. Eighteen bicycle/pedestrian projects were funded in
the 2007-2012 TIP, as were two historic preservation projects. These were: a
Multimodal Historic Interpretation Project submitted by the Historical Society
with a total project cost of $458,000 ($343,000 federal, $115,000 local) and the
US-36: 3rd Avenue Streetscape Improvements submitted by the Town of Lyons
with a total project cost of $300,000 ($240,000 federal, $60,000 local). Two other
historic projects have been funded in the TIP since the Enhancement funding
category was established by the Inter-modal Surface Transportation Efficiency
Act (ISTEA) in 1991. One of them was moving a 1937 concrete gas station,
Johnson's Corner, intact 1.5 miles from the comer of Highway 119 and US-287 to
the Prospect subdivision, Longmont, in 2003 ($77,000 federal).
Project criteria, priorities and funding tazgets for the 2009-2013 TIP will be
established by the DRCOG Board prior to project solicitation in fall 2007. If a
Depot project application were submitted by the city, it would need to compete
under those criteria.
o Railway Heritage grant: The National Railway Historical Society awards a
limited number of grants for projects related to the preservation of railway
heritage, including restoration, education and research projects. The ma~cimum
grant awazd is $5,000. A minimum match of 50% is required. Grants aze awarded
annually, with applications typically due in late April.
Additional funding sources could include:
o Private/ public partnership: The city could sell or lease the building to a private
entity that would put the building to a commercial use consistent with TVAP
goals. In either case, the private party could provide financial support for
relocating the building, refurbishing it, and/or maintaining and operating it on an
on-going basis. It may be possible to par[ner with RTD for on-going maintenance
and operation if the Depot were used for transit activities.
/3
o Further fundraising: A non-profi[ organization could assist with raising funds
from individuals ancUor groups for any phase of the Depot project. Currently,
there is no organization that has indicated an interest or commitrnent to fundraise.
City of Boulder funding: The city could allocate money from its budget for any
phase of [he project. However, the allocation and management of city resources
remains an important focus of the Boulder organization given the revenue and
corresponding expenditure reductions of recent years. As Council and staff
have discussed, the city's Business Plan is the tool being used to more consistently
evaluate information and prioritize proposals more strategically city-wide, not just
departrnentally. CounciLdirec6on has guided.and will continue to provide the
framework for the city'"s Bu'siness Plan. The 2006 Budget is a fiscally constrained
business plan for both our operating and capital budgets; existing resources have
been programmed and'in some cases reallocated'to address priorities. The 2007
Budget is also expected:fo:be fiscally constrained given'the modest improvement
in on-going revenues. The development of the next phase of the city's Business
Plan (the action plan), that.is currently underway, wil] further inform funding
priori6es, additional reallocation opportunities and future ballot measures.
Strategies•~ - .
Staff has considered the five strategies for the Depot, Strategies A-E:
Strategies A, B, C, and D all involve temporary storage of the building until a permanent
location for the Degot is selected through the Transit Village Area P•lan {TVAP) process. The
TVAP is exgected to be completed in December;2006. Further.planning and prepazation of the
selected permanent location would be needed before the building could actually be moved there.
ff the TVAP recommends'that the Depot be located on the 11:2-acre city/ RTD-owned'Transit
Village site, then additional planning to refine the exact building location would occur through
master-.and site-planning of the city/ RTD-owned Transit Village site. The latter process is
expected to begin towazd the end of 2006, and continue through 2007. This will be a public
process in partnership with RTD to develop a master plan for the 11.2-acre site and a specific site
design for-the RTD first phase:regional bus station. The process, is anticipated to take
approximately one yeaz and would include input from RTD, the pubiic;'Planning Boazd,
Transportation Advisory Board, and City Council. The exact location of the Depot would be
identified as part of the bus station design in 2007. Construction of the first phase bus facility is
anticipated in 2008.
RTD has recently stated that RTD is "neutral" about the location of the depot. RTD Faciliries
Management has stated that RTD would include the depot as part of RTD's first phase bus
station if this is Boulder's desire and additional funding is available for relocation and
rehabilitation. Issues such as the level of funding from RTD, the building use and ownership,
and maintenance would have to be resolved with RTD. RTD has stated that the Depot would
need to have a transit function if any RTD funds are involved in the Depot.
A first phase of the housing to the north and west of the bus facility could happen as early as
2008. The city's portion of the 11.2-acre Transit Village site was purchased by the Housing
~~
Division with funding that requires that the land be used for affordable housing. Housing and
Human Services invested $7.1 million, includino funds from the Community Housing Assistance
Proa am Fund, the Affordable Housing Program Funds, and a portion of interim funding through
a Fannie Mae line-of-credit. In order to remain in compliance with funding requirements, if the
land is used for other purposes, other sources of funds would need to be used.
There has been some discussion of linking the Depot closer to the rail-related activities. If the
TVAP recommends that the depot be iocated north of Goose Creek, as part of the RTD future
commuter rail, and RTD is amenable, the exact location could be determined most likely in
2007-2010 as part of future RTD commuter rail planning efforts after the US36 EIS is
completed. Similar to the RTD bus facilities, RTD has recently stated they aze neutral about the
depot as a part of the future commuter rail facility and supports including the depot if the
community is supportive, funding is available and the depot use would have a transit use.
StrateQV A: Disassemble and Store on Citv-Owned Pronertv
Total project cost ("Grand Total" on Attachment B spreadsheets): $1,950,500 -$2,268,000
Under this strategy, the Depot would be deconstruc[ed stone by stone, following cazeful
photographic and graphic documentation of the building, and re-assembled on the permanent site
when ready. 'Fhe roof also would be disassembied: only historic members would be saved; the
rest would be disposed of and replaced with new materials upon re-assembly. The
deconsuucted parts of the building wouid be put on pallets, wrapped in plastic, and trucked to a
secure, city-owned property. The most likely storage facility would be inside the former "egg
fann" wazehouse, owned by the Parks and Recreation Department, on Valmont Road west of
Sterling Circle.
In terms of the buildina s historic integrity and the possibility of securing grant funds to
restore the depot from the Colorado Historical Society, this strategy is the least advisable. In
assessing treatments for historic bui]dings according to the Secretary of the Interior's Treatments
for Historic Properties, disassembly and reconstruction is advisable as a]ast resort. Also, an `but
of sight, out of mind" mentality could delay reconstruction of the building. However, this
strate~y is the simplest and most straightforwazd in terms of moving logistics and offers the most
flexibility in terms of storage, paRiculazly if funding for reconstruction is delayed and/or if for
any zason the pallets need to be moved to another storage location. Additionally, it allows for
interior, protected, and secure storage, away from exposure to the imminent construction on the
city/RTD-owned site, and the accompanying noise, dirt, and heavy equipment that wiil be
involved during construction. It also eliminates the small risk of catastrophic collapse associated
with moving the building intact, and may result in a more structurally sound building once
reassembled. In terms of phasing costs and funding, under the disassembly strategy, funding
from Regency would remain after the move to storage (Phase 1) for use in the move to the
permanent location (Phase 2).
Strateeies B and C• Move Intact to and Store on Citv/ RTD-Owned Transit Villa~e Site
Total project cost ("Grand Total" on Attachment B spreadsheets): $1,837,500 -$ 2,266,500
Strategies B and C would both move the bui]ding for temporary storage on the city/
RTD-owned Transit Village site within the city portion that is not cunently leased to Pollazd
Motors. The building would be stored on steel frame cribbing and protected by fencing and
lighting. Because it would be stored on cribbin~, if necessary the building could be moved a~ain
a shorc distance (up to 300'), for about $25,000 and without geat logistical difficulty.
~~
Strategy B assumes that the same general area, on the south side of Goose Creek, would
be selected as the building's permanent location through the TVAP process. In this case, the
building would be moved intact, ]ikely in one piece, for storage and then moved again on the
same cribbing to the permanent location. ~
Strategy C assumes that a permanent location north of Goose Creek in the proximity of
the future rail platform would be selected through the T'VAP process. Because moving the
building to the future rail azea would likely require tuming street corners, the building would
have to be cut into two pieces. ~ ''
Intact moving and storage i5 appropriate from a historic preservation perspective,
provided secure cribbing can be constructed and the building is appropriately mothballed and
protected from vandalism. Existing cracks may worsen, and new cracks could open, but these
could be repaired during restoration. However, this method does carry a small risk of
catastrophic collapse of the building during the move. In addition, from a logistical standpoint,
intact moving is much more complicated, difficult, and disruptive than disassembled moving, as
it entails ciearing and leveling the route-way, dropping power lines; removing trees; clo'sing or
diverting traffic, and a larger staging area in the pazking lot cuaently surrounding the Depot.
Also, fhe city-ow+ned site is highly visible: There is a risk that a public perception could develop
that the temporary storage location is permanent. The building stored on cribbino there could be
considered an eyesore, 6ut if also could serve as a reminder and motivator tasecuie a permanent
home for the Depot. In teims of phasing costs and funding, there would probably-be little, if any,
funding from Regency remaining'after the inove to the temporary location (Phase 1) to use for
the move to a permanent fodndauon (Phase 2).
Strate2v D• Move Intact to and Store in Proximitv of Future Rail Platform
Total project cost ("Grand Total" on Attachment B spreadsheets): $1,915,000-$2,232,500
Strategy D anticipates that the permanent location foi the Depdt might to.be in proximity
to the future rail platform, which is north of Goose Creek and the city/ RTD-owned Transit
Village site, and moves the building directly there. Although this:location could be selected
through the TVAP process that ends in December 2006, it is unlikely that the necessary
subsequent site acquisition and prepazation could be carried out betweenTVAP adoption and the
move deadline of Mazch 2007. In this case; if the building were to be just moved once, the
permanent Depot ]ocation would have to be selected in advance of the TVAP completion.
Alternatively, the building could be stored temporarily in the vicinity of the future rail platform
on private property leased by the city, until the permanent site nearby is ready to receive the
building.
Because the moving route from Crossroad Commons to the future rail area would likely
require turning street corners, the building would have to be cut into two pieces. Each piece then
would be moved intact separately.
As with Strategies B and C, intact moving and storage is appropriate from a historic
preservation perspective, provided secure cribbing can be constructed and the buiiding is
appropriately mothballed and protected from vandalism. Existing cracks may worsen, and new
cracks could open, but these could be repaired during restoration. However, this method dces
cany a smail risk of catastrophic coliapse of the building during the move. In addition, from a
logistical standpoint, intact moving is much more complicated, difficult, and disruptive than
disassembled moving, as it entails clearing and leveling the route-way, dropping power lines,
removing trees, closing or diverting traffic, and a lazger staging area in the parking lot currently
surrounding the Depot. In terms of phasing costs and funding, for Phase i(move to the
! ((/
temporary location), al] the funding from Regency would be used and additional funding would
likely be needed.
The table below provides an overview of pros and cons of disassembly (Strategy A) versus
movin~ intact (Strategies B, C and D).
Pros and Cons for Disassembly vs. Moving Intact
Disassemble (Strate A) Intact (Strate 'es B, C, D)
Pros Cons Pros Cons
+ less risk during move - loss of historic + supports historic - risk of building damage
integrity and state preservation goals during move and/or neazby
historical society and state historica] imminent construction or due
funding option society funding to vandalism
option
+ flexibility for storage and - higher average cost + lower average cost - disruption of traffic,
permanent siting; possibly businesses, and urilities
less time-pressure to find during move and prepazation
funding and secure for move
permanent location
+ more secure storage - less assurance of + more assurance of - storaae neaz 30`h & Pearl
restoration restoration would be hiahly visible and
+ better structural integrity may be considered an
when rebuilt eyesore
- risk of public expectation
+ funding from Regency will that temporazy storage
remain from Phase 1 for use location will become
in Phase 2 ermanent
3trateQV E: Leave in Place
This strategy assumes that the Depot would remain in place and the Jaycees would
continue as owners of the building. Redevelopment of Crossroad Commons would likely to be
limited to cosmetic changes over time. The challenge for Regency would be to retain their roster
of successful tenants in an environment of increased competition for retailers from newly
developed locations in communities adjacent to Boulder. Physical]y, the Depot is likely to
continue to deteriorate as the Jaycees struggle to fund maintenance and interior flooding re-
occurs. Regency has indicated that the current offer of funds to move the building is based on
negotiations with current tenants and the Site Review redevelopment plan that was submitted on
May 1.
Strategy Selection
Staff is recommending that either Strategy A, B, C, or D be selected and pursued by staff in
January 2007 depending on:
/7
- the outcome of the TVAP,
- the availability of the permanent site selected for the Depot, and
- the city's success in securing enough funding to, at a minimum, move the building to its final
location, place it on a permanent foundation, and stabilize it.
The conditions for selecting a strategy aze detailed under the Staff Recommendation section of
this memo. The logic for selecting a strategy attempts to balance:
- concerns about maintaining the historic integrity of the building,
- imminent construction on the RTD-owned portion of the Transit Village site, and
- possible neaz-term construction on the city-owned portion.
The cost of each strategy was not a major consideration, as there is not a great difference among
them. Prepazations for the move according to whichever strategy is selected need to get
underway by Januazy 2007.
Cost Estimates
T'he feasibility and estimated costs of Strategies A, B, C, and D were developed and refined by
staff from the city Facilities and Asset Management Division and several different engineers:
- Atkinson-Noland Associates, whom the city contracted in January for an initial moving
feasibility study;
- Bob Hunnes with JVA Engineenng, who was recommended by Historic Boulder; and
-Regency Retail Partners.
Aktinson-Noland and Regency each consulted with several different building movers.
Cost estimates for all four strategies assume: moving the building twice, restoring it, and
finishing the interior and exterior for a non-specific use.
A line item cost for land acquisition is included in each strategy. Staff assumed a number of $36
per squaze foot for acquisition costs. This price reflects a speculative value anticipating
increased density in the area. This has not yet been determined. Including a land acquisition
cost is a conservative approach: No land is cunently programmed for the Depot, however, it may
be possible to trade off land for the Depot for additional density or some other development
advantage through a development agreement with a private property owner.
The cost estimates are detailed in Artachment.B. The table in Attachment C totals the costs for
each strategy by project phase, and also provides possible funding sources.
NEXT STEPS:
If City Council takes the actions recommended by staff (outlined under Staff Recommendations),
next steps for the project will include the following:
- Staff will seek additional funding to complete relocation, restoration and preservation of the
Depot.
- Staff will continue in the TVAP process for determining the final location and future use of tl~e
Depot, as well as exploring possible neazby temporary storage locations, if one is needed.
- Upon selection of the relocation strategy, staff and Regency will return to the Landrriarks
Preservation Advisory Boazd and City Council [o request removal of the landmazk designaGOn of
the land beneath the Depot. This would effectively also remove the landmark designation of the
building itself. (Any landmazk designation of a building includes both the building and the land
~~
beneath it.) Council wi11 see this request in the form of an amendment to the ordinance that
originally designated the Depot as a landmazk. The building will be re-designated as a]andmazk
once it is in its final location.
Approved By: • ~
~ ~ ~
Frank W. Bruno,
City Manager
ATTACHMENTS:
A. Ordinance
B. Detailed cost spreadsheets and narrative
C. Costs and Possib]e Funding Sources by Phase
D. Map of Depot location and Transit Village vicinity
E. Depot history overview
F. Old photographs of Depot
G. Letters from the Jaycees and Regency
H. Findings for Landmark Alteration Cer[ificate
%~
~VHFRE r['ltE ~~1ARK~T1'1~ACE 1VTEETS
~'_"~(r~rsi~ir~n
~
EARN CREDITS FOR
CONTINUING EDUCATION.
Choose from over 85 worid class seminars,
workshops, panel discussions and tours of
Boston's famous landmarks. Architects earn
more than 21 Continuing Education Credits.
HUNDREDS OF PRODUCTS.
Meet face-to-face with over 200 exhibitors
and suppliers of historically accurate products
antl services for the restoration, renovation
and traditionally inspiretl new construction
markets.
NETWORKING.
loin your colleagues and our esteemed
speakers for unparalleled networking
opportunities, including the Traditional
Building Gala Reception and the Traditional
Building Pub Crawl.