HomeMy WebLinkAboutItem IV-B Consent Agenda PR Update
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
TO: Parks and Recreation Advisory Board
FROM: Yvette Bowden, Director, Parks and Recreation Department
Ali Rhodes, Deputy Director
Jeff Haley, Planning, Design and Community Engagement Manager
SUBJECT: Consent Agenda
DATE: June 26, 2017
A. Approval of Minutes from May 22, 2017
B. Parks and Recreation Development Update
The following information is intended to provide the PRAB with relevant updates on specific
projects as they reach major milestones. This section is not all inclusive of all current projects
and only illustrates major project updates. For a complete list of all current projects and details,
please visit www.BoulderParkNews.org.
Planning and Design
The following projects are currently in the planning and design process that involves research,
alternatives analysis, public involvement and development of planning documents and design
plans to guide decision making and future capital improvements.
Boulder Reservoir South Shore Site Management Plan: The planning process begins
this month and includes a significant public engagement effort as well as PRAB
engagement. Efforts begin with staff interviews followed by meetings with reservoir
camps, clubs and vendors on July 5th, a public open house on July 18th and a second
public open house to be held at the reservoir on July 23rd. Staff will update the PRAB on
results of stakeholder engagement efforts at the August 28 meeting and will be seeking
PRAB comment and feedback at that time. The overall approach to the project was born
from the Boulder Reservoir Master Plan (BRMP) hat outlined a set of goals and
objectives intended to achieve a vision for the future of the Boulder Reservoir that states:
“Recognizing that the Boulder Reservoir is first and foremost a source of clean water
and valuable natural resources, the community envisions a Reservoir where high quality
and appropriate recreation activities are managed and sustained in a manner consistent
with preserving and enhancing the environment.”
Among many objectives, the BRMP sets forth an objective to develop a Site Management
Plan for the South Shore area to address programmatic opportunities, operation and
management thresholds, sustainable business model(s), vehicle and trail access and future
capital improvements. The process will include:
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
1. Developing a Site Plan
Incorporate public, staff and stakeholder engagement findings;
Identify existing site infrastructure suitable for re-use or continued use;
Develop and illustrate proposed locations of site design and program
elements;
Incorporate and seamlessly integrate with current planning efforts for the new
Visitor Services Center; and
Promote visitor safety.
2. Promoting a Sustainable Business Model
Support multiple-user, multiple season use of the facility;
Identify staff resources needed to support current and expanded services; and
Include opportunities for public/private partnerships to offset development
and operational costs.
3. Promoting Sustainable Development
Protect water quality and minimize water pollutant sources;
Support the City of Boulder’s sustainability goals;
Address city criteria for sustainability in the planning process;
Incorporate sustainable development practices; and
Protect sensitive wildlife and plant species and habitat.
4. Incorporating Public Engagement
Actively engage the public, staff user groups, stakeholders and policy makers
in the planning process;
Recognize that the Boulder Reservoir is owned, operated and managed by a
variety of public and private entities; and
Garner broad community involvement and support in the planning process.
Chautauqua Pedestrian Safety Access and Lighting Improvements: Construction is
complete on the 2014 voter-approved Community, Culture and Safety Tax funded
Chautauqua Project to address the safety hazard caused by the lack of sidewalk on the
south side of Baseline Road from west of Sixth Street to west of 10th Street. The project
scope included building a sidewalk on the south side of Baseline Road between 6th and
10th streets, improving pedestrian crossings within the project area, reconstructing the
transit stop near 10th Street (also known as King’s Gate) to be ADA compliant and
improving pedestrian connections to Open Space and Mountain Parks-designated access
trails and existing department paths. Pedestrian lighting along key park access points is
scheduled for the second phase of the project, currently anticipated to occur in 2018. A
completion celebration that included a Meadow Music event, was held at the park on
June 5th.
Scott Carpenter Outdoor Pool Redevelopment: BPR selected Essenza Architecture as
consultant to prepare design and construction drawings for the Scott Carpenter Outdoor
Pool Redevelopment project. Essenza completed the concept plan for Scott Carpenter that
was approved in January 2017. Over the next several months, staff will work with
Essenza to develop design drawings. The PRAB will be updated as the plans progress.
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
Planning Projects Underway: Staff or contractors continue to work on the following
projects and will update the PRAB as major milestones are achieved:
o Asset Management Plan;
o Boulder Junction Park;
o Boulder Reservoir Visitor Services Center Design Development;
o Lighting Ordinance Compliance Assessment;
o Parks Planning, Construction, Operations and Maintenance Manual; and
o Urban Forest Strategic Plan.
Construction
The following projects are scheduled for construction, under construction or have been recently
completed. For additional details please visit www.BoulderParkNews.org.
Arapahoe Ridge Park Renovation: Construction of Arapahoe Ridge Park is underway.
Arapahoe Ridge is the first of three neighborhood parks scheduled for renovation in
2017. Demolition of the playground and shade shelter walls began the second week of
June and will continue through the end of the month.
Christensen Park: Construction of Christensen Park nature play and traditional
playground is complete. The nature play features were inspired by the 2015 Nature Play
Symposium hosted by the department. A summary of the symposium can be found
online. Community members have been invited to join staff for a re-opening celebration
on June 29th for light refreshments, youth activities and a drawing for recreations center
or pool passes.
Civic Area Park: Construction activities in the Civic Area continue to progress on
schedule with completion anticipated in December 2017. A significant schedule
milestone was completed the week of June 12 with the successful relocation of a major
utility line. This relocation involved the shut-down of power to the Municipal Building
on Friday, June 16 and restoration on Saturday, June 17. This relocation will allow for the
construction of a second access point to Boulder Creek.
Upcoming work items and milestones include:
o Installation of nature inspired playground equipment and water play features;
o Excavation of the creek terrace under the new bridge;
o Final connections to the Boulder Creek Path; and
o Landscaping and irrigation work on the north side of creek.
Significant changes to circulation north of Boulder Creek can be expected in July. These
changes will be communicated through the Civic Area website, internal communications,
and external communications, as necessary.
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
Summer activities at the site include:
o Free Nature Play programming for children Monday/Wednesdays 9-11 a.m.;
o Bandshell Boogie, Mondays 7:30-9:00p.m., June 12, 19, 26 and July 17, 24, 31;
o Boulder Farmers Market, Wednesday afternoons and Saturday mornings;
o Boulder Art and Jazz Festival July 1-2;
o Summer Fest, July 29;
o Hometown Festival, September 2-4;
o Bee Boulder Pollinator Festival, September 23; and
o The Cult Classic Movie Series, October 3, 10, and 20.
Elks Park Arbor: The artistic wheel house arbor commissioned through a competitive
selection process in 2015 is currently being fabricated with installation in Elks Park
expected in late summer. The wheel house arbor concept was developed to integrate with
new features while preserving the agrarian character of the park by reflecting the forms
found in a historic windmill and pump. The artistic arbor is the second of the two
functional art installations at Elks Park. The first functional art piece was installed as a
mosaic tile wall inside the shelter. Pieces of tile in the mosaic were procured from
neighbors and integrated into the artwork.
Tantra Park: Irrigation replacement on the north field at Tantra Park will begin the
renovation construction. North field irrigation was scheduled to accommodate upcoming
reservation schedules and joint-use for Summit Middle School. Playground renovation
and other irrigation replacement in the park are scheduled to begin in early August as the
north field irrigation replacement is completed.
Valmont Dog Park: Last fall, two islands within the dog park were reconfigured for user
access. Original islands of trees and native shrubs were inaccessible to users for
vegetation establishment. The reconfigured islands were opened to users with additional
sod, new irrigation and tree replacements, where needed. Due to a high level of
popularity with the users, this summer, three more islands will be reconfigured for user
access.
Construction Projects Underway: Staff or contractors continue to work on the
following projects and will update the PRAB as major milestones are achieved:
o Holiday Park Shade Shelter;
o Howard Heuston Park; and
o North Boulder Recreation Center Aquatics Facility Renovations.
Forestry and Natural Lands Management
The following projects, focused on habitat and wildlife management in an urban environment,
are currently being managed by the Urban Resources staff:
Integrated Pest Management (IPM): Staff continues to participate in the city-wide
West Nile Virus and Nuisance Mosquito Management programs that met recently to
discuss program changes. There are multiple sites that have not bred nuisance nor vector
mosquitoes in over a decade. Sites visits to these nine parks and recreation sites and 80 to
determine suitability for continued inclusion in the monitoring program will be conducted
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
by staff. Any reduction to the number of sites included in the monitoring program, will
result ia cost savings.
Field staff Field staff continue to monitor and control for State regulated noxious weed
control, however, new species and new areas are continually added to the mandated
eradication list requiring additional monitoring and eradicating hours. As of June 16th,
over 200 hours have been spent in the field controlling just the A-list species such as
myrtle spurge, Mediterranean sage and Dyer’s woad. This does not include education,
planning or B-list eradication mandated species.
The Goat Extravaganza with its innovative programs
for weed control, educational opportunities to learn
about and meet the goats and the yoga practice was a
great success. During the staff debrief of the
program, additional opportunities were discussed for
2017 and beyond. The next opportunity is a Meet and
Bleat (no yoga) from 5-7 p.m. on June 22nd at
Christensen Park.
Urban Wildlife Management: The City Manager’s Office recently accepted all six 2017
staff recommendations from the Prairie Dog Working Group (PDWG):
1. Create guidelines and criteria for prioritizing relocation/take sites on both public
and private land;
2. Create guidelines and criteria for prioritizing receiving sites on public lands
within existing plans and develop recommendations for making receiving sites
more feasible;
3. On approved receiving sites, ensure that the number of prairie dogs to be
relocated have adequate accommodations;
4. Define successful prairie dog relocation, including evaluation criteria and
processes;
5. Develop a research proposal for the use of the sylvatic plague vaccine on the
southern grasslands in 2018 and beyond; and
6. Create a subgroup to work with staff to further develop the above
recommendations.
Staff will proceed with implementing the 2017 recommendations in a collaborative
manner, and will either report out further at a City Council Study Session tentatively
scheduled for September 26, 2017 or alternatively at a later date after the working group
has learned from the 2017 efforts and had a chance to make longer-term plan and policy
recommendations. The final IP packet can be found at
https://bouldercolorado.gov/osmp/prairie-dog-working-group.
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
Emerald Ash Borer Management: The Colorado Emerald Ash Borer Response Team
(EAB Team) is a multi-agency group formed after the discovery of emerald ash borer
(EAB) in Boulder and allowed all affected agencies to share communication while
developing mitigation and management strategies and outreach materials for EAB in
Colorado. Agencies participating in the EAB Team include: USDA Animal and Plant
Health Inspection Services, Colorado Department of Agriculture (CDA), City of Boulder,
Boulder County, University of Colorado (CU), Colorado State Forest Service (CSFS),
and Colorado State University (CSU).
The CO EAB Team and City of Boulder Forestry Division are hosting four free EAB van
tours in mid-August in the City of Boulder. The tours are geared towards city officials,
municipal foresters and tree care professionals from Boulder and nearby communities.
The tours will visit infested sites around the city to give attendees experience diagnosing
EAB in the field by learning to assess symptomatic trees. Management considerations,
biology and regulation will also be discussed. The tours are free but space is limited and
reservations are required.
Forestry and Natural Lands Projects Underway: Staff or contractors continue to work
on the following projects and will update the PRAB as major milestones are achieved:
o Regulations and Seasonal Wildlife Closures (Species of Concern); and
o Natural Lands Volunteer Recruitment and Training.
C. Operations Update
Boulder Creek Festival Update: The 30th annual Boulder Creek Festival, presented by
the City of Boulder and produced by Boulder Creek Events (BCE), included a
transformed footprint to accommodate construction in the Civic Area. This year's festival
encompassed the area between Broadway to 14th Street, Canyon Boulevard and
Arapahoe Avenue, the Arapahoe library parking lot, and the Boulder High School soccer
fields.
Despite the footprint change, the 2017 festival featured three stages of music, a carnival
area, an artisan tent, food, two beer gardens and numerous vendor and non-profit booths.
BCE worked with city staff to implement a zero-waste plan and promote multi-modal
transportation. Additional information on event metrics and diversion will be shared with
thePRAB at future meetings.
The event’s footprint will continue to transform as construction advances and BCE will
produce the event again in 2018.
Sugary Sweetened Beverage Distribution Tax Update (SSBDT): Following the update
on the SSBDT provided to the PRAB at the April business meeting, staff issued an
invitation for Requests for Proposals (RFPs) to fund existing 501(c)(3) nonprofit
agencies, educational or governmental entities which have the express purpose of
promoting health and preventing diseases associated with sugary drink consumption.
RFPs were due June 23rd and requested funds to support or enhance existing programs
with the 2017 revenues from the SSBDT.
3198 Broadway, Boulder, CO 80304 | www.boulderparks-rec.org | O: 303-413-7200
The city also invited community members to apply for membership on the Health Equity
Advisory Committee (HEAC). The HEAC’s intent is to ensure tax fund expenditures
align with the intention of Ballot Issue 2H and to make funding recommendations to the
City Manager. The seven-member panel will meet beginning at the end of June to review
2017 RFPs, assist with the identification and prioritization of success measures for
SSBDT funding and provide input on effective outreach strategies to reach residents most
affected by chronic disease and lack of access to health services.
Funding recommendations will be shared with City Council in an Information Packet (IP)
in early August.
Silver and Fit Update: To increase resident access to wellness opportunities, the
department will enter an agreement with the ‘Silver & Fit’ division of American
Specialty Health, that provides fitness center access to older adults on eligible insurance
plans. The agreement is intended to act as a complement to the existing discounted senior
entry rates to recreation centers and ‘Silver Sneakers’ program. This addition leverages
existing services oriented towards older adults and provides a broader range of eligible
insurance plans. Silver & Fit access will be integrated directly into the Active.net
platform and is on track for implementation at the start of the fall 2017 season.
Boulder Reservoir’s Star Spangled Splash: Beginning in 1955, many generations of
Boulder residents have enjoyed spending their July 4th at the Boulder Reservoir. This
year, on Tuesday, July 4, the reservoir will open for self-directed sunrise meditation and
early morning yoga. At 8:00 a.m., community members are invited to run the Craig
Tower Freedom 5k and 10k. The swim beach and a beer garden will open from 10:00a.m
and wills serve beverages until 4:00 p.m. Standard admission fees apply for this event.