C I T Y O F B O U L D E R
INFORMATION ITEM FOR:
TRANSPORTATION ADVISORY BOARD –May 12, 2014
ENVIRONMENTAL ADVISORY BOARD –May 14, 2014
OPEN SPACE BOARD OF TRUSTEES –May 14, 2014
PLANNING BOARD –May 15, 2014
PARKS AND RECREATION ADVISORY BOARD –May 19, 2014
WATER RESOURCES ADVISORY BOARD –May 19, 2014
GREENWAYS ADVISORY COMMITTEE AGENDA ITEM
MEETING DATE:May 22, 2014
SUBJECT:
2015-2020Greenways Capital Improvement Program
REQUESTING DEPARTMENT:
Kurt Bauer–Flood and Greenways Engineering Project Manager
PURPOSE:
The 2015-2020Greenways Capital Improvement Program is being provided to
board members as an information item. If you have any comments or concerns regarding the
2015-2020Greenways Capital Improvement Program, please pass them along to your
Greenways Advisory Committee representative. If you have questions on this material, please
contact Kurt Bauerat 303-441-4232or bauerk@bouldercolorado.gov.
GREENWAYS ADVISORY COMMITTEEACTION REQUESTED:
A recommendation from the Greenways Advisory Committee to the City’s Planning Board
and City Council concerning the proposed Greenways Capital Improvement Program is
requested.
Attached is information concerning the proposed 2015-2020Greenways Capital Improvement
Program (CIP) for review and consideration. A recommendation by the Greenways Advisory
Committee to the city’s Planning Board and Council will be requestedat the May 22, 2014GAC
meeting.
Attachment A: Greenways 2015-2020Capital Improvement Program Overview
Attachment B: Greenways 2015-2020Capital Improvement Program Summary Spreadsheet
Attachment C: Greenways Program CIP Map
Attachment D: Timeline for Floodplain Mapping, Mitigation Planning and Capital
Improvements
1
Attachment A: Greenways 2015-2020CIP Program Overview
GREENWAYS
2015-2020CAPITAL IMPROVEMENTS PROGRAM
The city of Boulder Greenways System is comprised of a series of corridors along riparian areas
including Boulder Creek and its 14tributaries, which provide an opportunity to integrate
multiple objectives, including habitat protection, water quality enhancement, storm drainage and
floodplain management, alternative transportation routes for pedestrians and bicyclists,
recreation and cultural resources.
The Greenways CIP follows an opportunistic approach, contributing funding toward projects that
are being completed by other departments or private development in order to meet the various
objectives of the Greenways Program. The Greenways CIP alsolooks to leverage funds with
outside agencies in order to move projects forward that meet more than one objective of the
Greenways Program, but may not be the highest priority when evaluating any one particular
objective.Projects included in the Greenways CIP are typically called out in the Greenways
Master Plan and are projects that Greenways staff can take the lead in coordinating.
Funding Overview
The total 2015Greenways capital budget is $320,441, with $105,000 inthe operating budget.
Greenways projects are funded from the Transportation Fund, Stormwater and Flood
Management Utility Fund, and the Lottery Fund. Annual funding distribution for the Greenways
Capital Program for 2015is as follows:
Transportation-$97,500
Flood Utility-$97,500
Lottery Fund-$125,441
Starting in 2015, the Lottery contribution is expected to be reduced to $125,441, based on
Greenways receiving 15% of the city’s funding allocation, with a projection of total Lottery
proceeds being $836,275.
Accomplishments and Highlights
The following presents a summary of the projects that were completed prior to the flood in 2013:
The Boulder Creek Flood Mapping Update was submitted to FEMA in early 2013.
Significant progress was made on the design of the Wonderland Creek Greenways and
Flood improvement projects (Foothills to 30th and 30th to Winding Trail) including
hiring an artist and working through design details with the Burlington Northern
Railroad.
The Wonderland Creek Diagonal to Winding Trail CEAP was completed inearly 2013.
Upper Goose Creek and Twomile Canyon Creek Flood Mapping Study was presented to
WRAB in a public hearing in May.
High resolution LiDAR (light and radar) data was collected in the spring of 2013 to
update the city’s topographic and GIS data.
1
Staff completed aperiodic update to the city’s asset management database for all
drainage infrastructure along all major drainageways in the spring of 2013.
In September 2013, a major storm eventbrought unprecedented rainfall to our region causing
significant flooding, loss of life and widespread damage. The following provides a summary of
the efforts completed following this event:
Staff performed damage assessments along Boulder Creek and the 14 major
drainageways and determined the limits of the flood boundary associated with the
September flood for each drainageway.
Seven Open Houses were conducted in coordination with the Community Planning and
Sustainability Department to share flood extent and flood recovery information with the
public.
Emergency channel repair work and sediment removal was completed along Twomile
Canyon Creek, Wonderland Creek and Boulder Creek in conjunction with the Urban
Drainage and Flood Control District.
A post-flood evaluation of the Fourmile Canyon Creek and Wonderland Creek flood
mapping was initiated in December.
Projects Completedin 2014
Goose Creek Restoration Project includes restoration improvements along Goose Creek
th
between Foothills Highway and 55Street. This project is expected to be completed in
2014. This project is primarily being funded through a Section 206 Restoration grant
through the U.S. Army Corps of Engineers. The city’s 35% funding match is being met
mostly through credits from city owned real estate.
A flood mitigation major drainageway plan for South Boulder Creek is anticipated to be
completed by the end of 2014.
The Urban Drainage and Flood Control District also completes maintenance projects
along the major drainageways. In 2014 this includes a request for sediment removal
along Wonderland Creek from Foothills Parkway to the confluence with Goose Creek.
This maintenance project will help provide the necessary conveyance capacity required
when the Wonderland Creek Greenways Improvement Project is completed.
Projects Expected for Completion in 2015
th
Fourmile Canyon Creek at 19Street is in preliminary design but was put on hold
following the September 2013 flood event. It is anticipated that development of this
project will continue in late 2014 with a CEAP completed in 2015.
Flood mapping studiesfor Upper Goose and Twomile Canyon Creeks; Skunk, Kings
Gulch and BlueBell Canyon Creeks; Boulder Slough and Bear Canyon Creek are
anticipated to be completed in 2015.
Projects Starting in 2015, but Not Completed
th
Construction of the Wonderland CreekFoothills to 30Greenways Improvement Project
is anticipated to begin in 2015.
th
Construction of the Wonderland Creek (28Street) Diagonalto Winding Trail
Greenways Improvement Project is anticipated to begin in 2015.
Aflood mitigationplan was initiated in 2014 for Boulder Creek, Bear Canyon Creek and
2
Gregory Canyon Creekand is anticipated to be completed 2015.
Highlights of 2015 –2020 Projects
The focus of the 2015-2020Greenways CIP is on flood mitigation, bicycle and pedestrian multi-
usepaths and underpasses, and habitat and water quality improvements along the Fourmile and
Wonderland Creek corridors. In addition to the projects along Fourmile Canyon Creek and
Wonderland Creek, possible habitat restoration projects during the next few years include:
Stream bank restoration along Boulder Creek at Eben Fine Park
Confluence of Bear Creek and Boulder Creek at Foothills Community Hospital
Dry Creek habitat improvements through Flatirons Golf Course
th
Goose Creek, railroad to 47Street tree plantings
Fish Passage enhancement projects in association with Fishing is Fun grants
South Boulder Creek minimum stream flow
th
Removal of Russian Olive trees east of 75Street along Boulder Creek
Relationship to Guiding Principles and Master Plan and Prioritization
Greenways projects address many of the CIP guiding principles. Greenways projects are
identified in multiple master plans and meet the community sustainability goals. Most of the
Greenways projects leverage outside or interdepartmental funding.Greenways habitat
improvements seek to be sustainable and are intended to reduce the future maintenance required.
The Greenways CIP has been developed within the context of and is consistent with the Boulder
Valley Comprehensive Plan (BVCP), the Transportation Master Plan (TMP), the major
drainageway plans, the Comprehensive Flood and Stormwater Master Planand the Greenways
Master Plan.The Greenways Master Plan wasupdated in 2011to reflect improvements that had
been completed,and adopted changes that have been made in other master plans, city policies
and ordinances that affect the Greenways Program since the last Master Plan update in 2001.
Information from other existing master plans for seven additional tributaries wasalso
incorporated intothe Greenways Master Plan update. Future opportunities will also be
coordinated with the Open Space and Mountain Park’s Grassland Plan and Visitor Master Plan
and Trail Study Area plans where appropriate.
Many of the Greenways projects shown in the CIPare being designed and constructed in
coordination with major flood or transportation improvements. The Greenways funding
associated with these projects focuses on habitat restoration, water quality improvements and
trail connections. In addition to leveraging funding with the Transportation and Flood Utilities
budgets, funding for Greenways projects is also available through the Urban Drainage and Flood
Control District and Federal Transportation funds.
It should be noted that the city is still recovering from the September 2013 flood event that
resulted in extensive flooding along most of the city’s major drainageways. Following the flood,
additional funds have been allocated in the Flood Utility CIP to reflect an increased interest in
pursuing flood mitigation efforts along the city’s major drainageways. Continued evaluation of
the impacts from this event may result in additional changes to the Flood Utility and Greenways
CIP in upcoming years.
3
New Projects
The 2015 -2020 CIP continues to focus on Fourmile Canyon and Wonderland Creeks. The
Flood Utility is currently updating the flood mapping for the following creeks and tributaries:
Boulder Creek, Boulder Slough, Upper Goose Creek, Twomile Creek, Skunk Creek, Bluebell
Creek and King’s Gulch. Once the new mapping has been approved by FEMA, a flood
mitigation analysis will be completed for each of these tributaries to determine if it is
economically feasible to reduce the flood risk through construction of capital improvements. A
flood mitigation plan is being initiated in 2014 for Boulder Creek, Gregory Canyon Creek and
Bear Canyon Creek. This plan will identify potential economically feasible CIP projects which
Attachment B
may provide opportunities for future Greenways Improvements. presents a
Attachment D
spreadsheet of proposed funding for these upcoming projects. graphically
presents the anticipated timeline for these projects.
Operation and Maintenance Impacts
$105,000is budgeted each year for Greenways operations and maintenance. $80,000 of the
operating budget is dedicated to habitat maintenance. The Greenways habitat crew works
closely with Parks and Open Space maintenance staff to provide on-going maintenance, as well
as on collaborative projects as part of the operations budget. Major drainageway improvements
are maintained by the flood maintenance staff and multi-use paths and underpasses are
maintained by either Transportation or Parks maintenance, depending upon jurisdiction.
Deferred Projects, Changes and Unfunded Needs
Since the Greenways Program is opportunistic, taking advantage of projects that are funded
through other departments, there are no unfunded needs.
th
The Wonderland Creek from Foothills to 30Street was granted Federal Transportation
Improvement Program (TIP) funds in the amount of $2 million (2012-2014). Additional TIP
th
funding was granted for the Wonderland Creek at 28Street project in the amount of $900,000
(2013-2014).
Emerging Needs
None
BOARD ACTION
The Greenways Advisory Committeewill reviewthe Greenways CIP on May 22, 2014and will
be asked to make a recommendation for approval to the Planning Board and City Council.